DocketNumber: No. 08 NO 347.
Citation Numbers: 2008 Ohio 6212
Judges: WAITE, J.
Filed Date: 11/25/2008
Status: Precedential
Modified Date: 7/6/2016
{¶ 2} Although we were presented with a somewhat similar situation inThe Whitacre-Greer Fireproofing Co. v. M.B. Operating Co., Inc. (Feb. 23, 1983), 7th Dist No. 459, the instant case is distinguishable. InWhitacre-Greer, the public roadway was being used for private purposes. The instant case involves a public use of the roadway easement for a gas line being shared by multiple residences along the road. Given that Appellee had permission from the county commissioners to install the publicly used gas pipeline in a public highway right of way, the trial court correctly granted summary judgment to Appellee. *Page 2
{¶ 4} The trial court ruled on the summary judgment motion on January 4, 2008. The court indicated that the only pieces of evidence timely filed in the action were the affidavits of Lee A. Robinson, Andy Rataiczak, and Janice J. Sandy. The court found by uncontroverted evidence that Appellee had permission from the county commissioners to install the pipeline, that it was installed on the county road right of way, and that the pipeline was used to provide natural gas service to a number of households in the area. The court found that Appellee was a de facto natural gas utility and that the pipeline did not constitute an added burden on Appellants' property. The court granted summary judgment to Appellee. This appeal followed on February 1, 2008. Appellants' two assignments of error are related and will be treated together. *Page 3
{¶ 6} "THE COURT ERRED IN MAKING A DETERMINATION THAT DEFENDANT-APPELLEE IS A DE FACTO PUBLIC UTILITY CONTRARY TO LAW."
{¶ 7} This appeal is a challenge to a ruling in summary judgment. When reviewing a trial court's decision to grant summary judgment, an appellate court applies the same standard used by the trial court and, therefore, engages in a de novo review. Parenti v. Goodyear Tire Rubber Co. (1990),
{¶ 8} When moving for summary judgment, a party must produce some facts that suggest that a reasonable fact-finder could rule in his or her favor. Brewer v. *Page 4 Cleveland Bd. of Edn. (1997),
{¶ 9} The record does not support Appellants' argument that there are material facts in dispute about one or more of the claims in the complaint. Appellants' complaint refers to one defendant, Andy Rataiczak, and contains allegations of conversion, unjust enrichment, trespass, and quiet enjoyment. The conversion claim is not justiciable because conversion only applies to personal property. Ohio Tel. Equip. Sales, Inc. v. Hadler Realty Co. (1985),
{¶ 10} As far as the trespass and related unjust enrichment claim, the record indicates that Appellee had permission from the Noble County Commissioners to lay his gas pipeline within the public roadway easement. The Ohio Supreme Court defines trespass as follows: "``A common-law tort in trespass upon real property occurs when a person, without authority or privilege, physically invades or unlawfully *Page 5
enters the private premises of another whereby damages directly ensue * * *.'" Apel v. Katz (1998),
{¶ 11} Appellants did not submit rebuttal evidence in the manner prescribed by Civ. R. 56(E), which requires each party to submit "[s]worn or certified copies" of supporting evidentiary documents. As it stands, Appellants rely only on bare assertions to support their argument. The party opposing summary judgment cannot rely on mere allegations, bare assertions, or unfounded denials. Civ. R. 56(E).
{¶ 12} Appellants' remaining arguments attempt to undermine the fact that Appellee had permission from the county commissioners to install the pipeline. Generally, an abutting landowner owns title to the land underlying a county road, *Page 6
while the public is entitled to use the road for highway purposes.Ohio Bell Tel. Co. v. Watson Co. (1925),
{¶ 13} "The board of county commissioners of any county may convey the fee simple estate or any lesser estate or interest in, or permit the use of, for such period as it shall determine, any lands owned by such county and acquired or used for highways, bridges, or culverts, or owned by such county in connection with highways or as incidental to the acquisition of land for highways * * *."
{¶ 14} There is no dispute that the road easement at issue in this case was lawfully obtained from private landowners to create a public roadway. There is no dispute that private property cannot be taken by the state to be put to a private use, in conformity with the
{¶ 15} The Ziegler case involved a water company that intended to put a water pipeline in a road right of way in Union County. One of the abutting landowners protested that she had not been compensated by the water company for the added burden of the pipeline on her property. TheZiegler Court agreed that, if the pipeline was judged to be an added burden, the landowner should be compensated. Id. at 102. The Court examined whether the water pipeline was consistent with the public purpose for which the road easement was originally acquired:
{¶ 16} "Obviously, highways are primarily for the use of the public, in traveling from place to place. Although modern-day travel on our highways is predominately by motor vehicle, highways certainly are not limited to such use. The effect of the use of a highway upon abutting land has always been variable and subject to change. The complexities of modern life have produced uses of highways which would have been unheard of at the time many easements for public highways were granted.
{¶ 17} "We are unable to discern any substantial burden visited on plaintiff's property by the intended construction. A denial of the use of a highway for the purpose of transporting water to areas where it is needed, as in the instant case, would be the rejection of evolutionary change. See 5 Restatement of the Law, Property, Section 479. We therefore hold that the construction of water pipes in real property, for which an easement for highway purposes has been given, is not an added burden on such land, for which the owner must be compensated.Hofius v. Carnegie-Illinois Steel Corp.,
{¶ 18} "We are aware that the defendant is a private corporation for profit. However, the project sought to be enjoined was undertaken pursuant to an agreement with the board of county commissioners and is, therefore, presumed to be for the public purpose." Id., at 105-106,
{¶ 19} A particularly instructive part of the analysis inZiegler states: "since individuals could use the highway to transport water for their own use, a board of county commissioners could furnish water to the public collectively by installing water mains, all of which would be included within the scope of an existing easement of use for highway purposes." Id. at 103.
{¶ 20} The Ohio Supreme Court has also held that the stringing of cable television wires along the telephone poles in the electrical utility easement does not constitute any additional burden on the fee landholder's property. Centel Cable Television Co. of Ohio, Inc. v.Cook (1991),
{¶ 21} This Court itself applied Ziegler and found no added burden to the abutting landowner's property when a water line was placed in the 50-foot road easement along Struthers Road, in Mahoning County.Kallas v. Ohio Water Serv. Co. (1999),
{¶ 22} The Third District Court of Appeals held that there was no trespass when an underground cable television line was installed in a roadway right of way in Shelby County. Shaffer v. Video DisplayCorp. (1988),
{¶ 23} The Twelfth District Court of Appeals held that the installation of a sewer line did not constitute an added burden on property of the abutting landowner, relying on Ziegler. Speidel v.Warren County Commrs. (Jan 31, 1986), 12th Dist. No. CA85-10-078.
{¶ 24} Although Appellants acknowledge the holding ofZiegler, they contend that a case from this Court, The Whitacre-GreerFireproofing Co. v. M.B. Operating Co., Inc. (Feb. 23, 1983), 7th Dist No. 459, is dispositive. In Whitacre-Greer, a private company installed a gas pipeline along a township and county road in Carroll County without obtaining either permission or an easement from the abutting landowners. The defendant did obtain permission from the county commissioners to install the pipeline. The parties stipulated that the defendant "does not hold itself out to supply natural gas to the public." Id. at *1. We examined whether the pipeline added any additional burden to the abutting landowner's property under the holding of Ziegler. We concluded that Ziegler did not apply, "since the water line in that case was characterized as being for a public use." Id. at *2. The entire analysis in Whitacre-Greer is premised on the fact that the pipeline was being used for a private purpose.Whitacre-Greer is completely inapposite to the situation in the instant case because Appellee's pipeline is being used for a public purpose.
{¶ 25} Appellants are under the impression that the only method for Appellee to be able to legally install his gas pipeline in the roadway easement was if he qualified as a public utility under the definitions found in Ohio Revised Code Chapter
{¶ 26} Even if it were somehow relevant whether or not Appellee qualifies as a public utility, the only evidence in the record indicates that Appellee is a de facto natural gas public utility. Appellants provided no evidence on this issue.
{¶ 27} It should be noted that the water pipeline under review inZiegler — which was deemed to be an appropriate public use of the road right of way — served only two buildings: a school building, and the plaintiffs residence. In the instant case, there is undisputed evidence that Appellee's pipeline serves a number of residences on County Road 31. Appellants did not file any evidence to rebut Appellee's proof that his pipeline supplied gas to a number of properties. Appellant Janice J. Sandy, in her affidavit, does not dispute that Appellee's pipeline serves a number of residences.
{¶ 28} Appellants try to rely on a deposition allegedly taken of Mr. Rataiczak, but the deposition was not properly filed with the trial court, is not sworn or certified, and is not part of the official record. "Summary judgment shall be rendered forthwith if the pleadings,depositions, answers to interrogatories, written admissions, affidavits, transcripts of evidence, and written stipulations of fact, if any,timely filed in *Page 11 the action, show that there is no genuine issue as to any materialfact[.]" (Emphasis added.) Civ. R. 56(C); Civ. R. 30(F)(1); Dombelek v.Ohio Bur. of Workers' Comp.,
{¶ 29} Based on the evidence in the record, and the holding ofZiegler, Appellee's use of the road right of way does not constitute any added burden on Appellants' property, and thus, cannot constitute a trespass or entitle Appellants to damages for unjust enrichment. Appellants' assignments of error are overruled and the judgment of the trial court affirmed.
*Page 1Donofrio, J., concurs. Vukovich, J., concurs.