DocketNumber: No. 72071.
Judges: Porter, Patton, Rocco
Filed Date: 3/30/1998
Status: Precedential
Modified Date: 10/19/2024
[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 98 Plaintiff-appellant Thomas Steel, Inc. appeals from summary judgment entered in favor of defendants-appellees Wilson Bennett, Inc. and Safeco Insurance Company of America on their payment bond arising out of certain subcontract work performed by plaintiff at Cleveland Hopkins Airport. Plaintiff Thomas Steel claims that the trial court erred in barring its action by applying the incorrect statute of limitations and in not recognizing plaintiffs unjust enrichment claims. We find no error and affirm.
On June 9, 1992, Wilson Bennett, as general contractor, entered into a contract with the city of Cleveland to install certain improvements at Cleveland Hopkins International Airport. The project included construction of an Aircraft Rescue and Fire Fighters Station ("ARFF") and Relocation of Electric Vault ("EV-9") for the lump sum contract price of $6,841,000.
The contract obliged Wilson Bennett to obtain a payment and performance bond in the form set forth in C.C.O. ("Cleveland Codified Ordinance") 185.14. *Page 99 Wilson Bennett obtained the required bond from Safeco. The bond provided that Wilson Bennett as principal and Safeco as surety would jointly and severally indemnify and save harmless the city of Cleveland from all liens, charges, claims, demands, loss, costs, and damages, and "shall pay all lawful claims of subcontractors, materialmen and laborers for labor performed, and materials furnished" in performing the contract on the project.
On September 17, 1992, Wilson Bennett entered into a purchase order subcontract with Simms Steel Service Company to provide the structural steel and labor to erect the ARFF building and EV-9 building for the contract price of $385,000, subject to a ten-percent retainage.
Simms Steel's subcontract with Wilson Bennett was based on a purchase order agreement, dated May 12, 1992, with plaintiff Thomas Steel to supply the structural steel and other accessories needed to frame the ARFF building and EV-9 for the contract price of $207,000. Thomas Steel supplied the steel on the job and submitted periodic invoices to Simms Steel, totaling $208,450. Simms Steel withheld ten percent of the total contract price or $20,845 as retainage. Thomas Steel completed its work and sent its final invoice to Simms Steel, dated April 12, 1993.
Despite Thomas Steel's repeated demands upon completion of the project, Simms Steel and Wilson Bennett failed and refused to pay Thomas Steel the outstanding retainage of $20,845. Correspondence in the record suggests that Simms Steel was in bankruptcy. By letter dated April 3, 1995, Thomas Steel's counsel sent Wilson Bennett formal written notice that Thomas Steel had not been paid in full by Simms Steel. Thomas Steel advised Wilson Bennett that when the city issued final payment to Wilson Bennett, Thomas Steel claimed any money due Simms Steel.
On June 30, 1995, Wilson Bennett submitted its final request for payment to the city and stated under oath that all laborers, materialmen and/or subcontractors had been paid in full despite the notice of nonpayment from Thomas Steel.
On October 18, 1995, prior to the city's final payment to Wilson Bennett, counsel for Thomas Steel gave formal written notice to Safeco of its $20,845 bond claim. On December 15, 1995, the city determined that the project was completed and made a final payment of $40,300 to Wilson Bennett.
On January 5, 1996, Wilson Bennett's counsel sent. Thomas Steel formal written notice that Wilson Bennett and Safeco denied Thomas Steel's bond claim under the statute of limitations set forth in R.C.
On April 4, 1996, Thomas Steel commenced this action on the bond against Wilson Bennett and Safeco for $20,850. After discovery, all parties filed motions for summary judgment. The trial court granted summary judgment for defendants on statute-of-limitations grounds and denied Thomas Steel's motion for summary judgment. This timely appeal ensued.
We will address plaintiffs assignments of error in the order presented and together where the subject matter is appropriate.
"I. The trial court erred when it granted defendants-appellees' motion for summary judgment and dismissed plaintiff-appellant's complaint as time barred because the general bond statute, Ohio Revised Code §
"II. The trial court erred when it granted defendants-appellees' motion for summary judgment and dismissed plaintiff-appellant's complaint as time-barred because plaintiff-appellant filed suit within one year from the date of acceptance of the public improvement project by the city of Cleveland even if R.C. §
Under Civ.R. 56, summary judgment is proper when "(1) no genuine issue as to any material fact remains to be litigated; (2) the moving party is entitled to judgment as a matter of law; and (3) it appears from the evidence that reasonable minds can come to but one conclusion, and viewing such evidence most strongly in favor of the nonmoving party, that conclusion is adverse to the party against whom the motion for summary judgment is made." State ex rel. Parsons v. Fleming (1994),
It is well settled that the party seeking summary judgment bears the burden of showing that no genuine issue of material fact exists for trial. Celotex Corp. v. Catrett (1986),
However, the nonmoving party must produce evidence on any issue for which that party bears the burden of production at trial.Wing v. Anchor Media, Ltd. of Texas (1991),
In Dresher v. Burt (1996),
This court reviews the lower court's granting of summary judgment de novo. Brown v. Scioto Cty. Bd. of Commrs. (1993),
Thomas Steel contends that the trial court erred in finding that its action was time-barred by the provisions of R.C.
The bond in question was a payment and performance bond in the form required by C.C.O. 185.14. However, the parties agree that there is no Cleveland ordinance or charter provision specifying time for suit on the bond. For that reason, the defendants argued that the bond was furnished to a "political subdivision" for a "public improvement" as provided in R.C.
"(A) Each person bidding for a contract with the state or any political subdivision, district, institution, or other agency thereof, excluding therefrom the department of transportation, for any public improvement shall file with his bid a bid guaranty in the form of either: *Page 102
"(1) A bond in accordance with division (B) of this section for the full amount of the bid;
"(2) A certified check, cashier's check, or letter of credit pursuant to Chapter 1305 of the Revised Code, in accordance with division (C) of this section. * * *
"* * *
"(C) * * * If the bidder enters into the contract, the bidder shall, at the time he enters into the contract, file a bond for the amount of the contract to indemnify the state, political subdivision, district, institution, or agency against all damage suffered by failure to perform the contract according to its provisions and in accordance with the plans, details, specifications, and bills of material therefor and to pay all lawful claims of subcontractors, materialmen, and laborers for labor performed or material furnished in carrying forward, performing, or completing the contract; and agree and assent that this undertaking is for the benefit of any subcontractor, materialman, or laborer having a just claim, as well as for the state, political subdivision, district, institution, or agency.
"* * *
"(J) For the purposes of this section and sections
R.C.
A notice of claim and an action under the payment portion of the bond asserted by a subcontractor, materialman, or laborer, alleging that money is due for labor or work performed or material furnished in a public improvement contract must be timely presented within the limitations periods set forth in R.C.
"Any person to whom any money is due for labor or work performed or material furnished in a public improvement as provided in section
"A suit shall not be brought against sureties on the bond until after sixty days after the furnishing of the statement described in this section. If the indebtedness is not paid in full at the expiration of that sixty days, the person may bring an action in his own name upon the bond, as provided in section
Thus, R.C.
Thomas Steel completed its subcontract and submitted its final invoice to Simms Steel on April 12, 1993. The date of acceptance of the subject public improvement on which Thomas Steel supplied materials was December 14, 1993. Thomas Steel admitted in its response to Safeco's Request for Admission No. 1 that "the `Date of Acceptance' noted below, on the `Statement of Work Accepted' dated March 4, 1994 was December 14, 1993 * * *." This Statement of Work Accepted identified the: improvement accepted as "Relocation of Aircraft and Firefighting Station and Electrical Vault at Cleveland Hopkins International Airport, Phase I (ARFF Building) and III (Site Work)." The statement was signed by the Airport Commissioner and the Director of Port Control. Thomas Steel did not furnish Safeco with a statement of the amount due it until at least October 18, 1995. This was approximately twenty-two months after acceptance, rather than within the ninety-day time limit. Thomas Steel also did not file this action until April 4, 1996, over twenty-seven months after the acceptance, rather than within the one-year limitation period prescribed by R.C.
Defendant contends that the "date of acceptance" of the public improvement did not occur until December 15, 1995, when the city made final payment to Wilson Bennett and therefore its April 4, 1996 suit was within the one-year limitation of R.C.
Nevertheless, Thomas Steel vehemently argues that the bond was furnished pursuant to C.C.O. 185.14 and that since Cleveland is a charter or home rule municipality, the limitations specified in R.C.
The express wording of R.C.
It cannot be disputed that the Constitution of Ohio gives the city of Cleveland authority to adopt home rule powers of local self-government. Section
Considering these provisions which incorporate statutes as part of the contract documents, and in the absence of any provisions in the city's charter or *Page 105
municipal ordinances explicitly declaring an intent by the city to supersede or otherwise override these provisions, the application of R.C.
Assignments of Error I and II are overruled.
"III. The trial court erred when it granted defendants-appellees' motion for summary judgment and dismissed plaintiff-appellant's complaint as time barred where the one-year statute of limitations of R.C. §
Thomas Steel argues that the one year limitations period set forth in R.C.
Thomas Steel did not raise at the trial court level the issue of whether its claim for unjust enrichment (quantum meruit) was subject to the six-year limitations under R.C.
It is fundamental that a reviewing court need not consider any issues that could have been raised in the trial court, but were not. Schade v. Carnegie Body Co. (1982),
"Generally, an appellate court will not consider an issue which was not raised before the common pleas court. This holding is based upon the proposition that an appellate court should not reverse a decision on a ground which the common pleas court was never given the opportunity to consider." Andolsek v. WilloughbyHills Bd. of Zoning (Dec. 10, 1993), Lake App. No. 93-L-050, unreported, 1993 WL 548046.
Aithough Thomas Steel did timely raise in its summary judgment papers issues in favor of its unjust enrichment claim, its complaint (second cause of action) stated a claim on the only payment bond as follows:
"21. Thomas Steel incorporates by reference herein all of the allegations contained in paragraphs 1 through 20 of this Complaint as if fully rewritten herein.
"22. Wilson Bennett is the principal on the Bond.
"23. On or about January 5, 1996, Wilson Bennett, contrary to the terms of the bond, denied the claim of Thomas Steel on the Bond.
"24. As a direct and proximate result of Wilson Bennett's wrongful denial of Thomas Steel's claim on the Bond, Thomas Steel has been damaged in an amount not less than $20,845.00, exclusive of interest and costs."
This can be read only as a contract claim against Wilson Bennett on the payment bond rather than an unjust enrichment claim. Thomas Steel is in privity of contract with Wilson Bennett as a third-party beneficiary because the payment bond itself states: "We [Wilson Bennett and Safeco] hereby agreeing and consenting that this undertaking shall be for the benefit of any laborers or materialman having a just claim as aforesaid as for the City * * *."
In any event, we find that plaintiffs exclusive remedy against Wilson Bennett was on the bond, not on other common-law remedies. See Gen. Elec. Supply Corp. v. Wiley Elec. Co. (1933),
Plaintiff has called our attention to Cleveland City SchoolDist. Bd. of Edn. v. United Pacific Ins. Co. (June 28, 1991), Cuyahoga App. No. 60374, unreported, 1991 WL 117936, in which this court held that the performance bond of a general contractor and its surety was governed by the fifteen-year statute of limitations (R.C.
"It would be ludicrous and disastrous public policy to dismiss the liability of a surety on a bond in ten years, while holding the obligor liable on the written instrument for fifteen years.
"The Ohio Supreme Court has declined to interpret a surety's liability pursuant to a bond with a restrictive view; thus, the court stated in St. Paul Fire Marine Ins. Co. v. Indus. Comm.
(1987),
"A surety is primarily and jointly liable with the principal debtor. His obligation is created concurrently with that of the principal debtor. * * * (Citations omitted.)
"It is evident the bond issued by United Pacific Insurance as surety was intended to secure payment for breach of performance by Forepaugh occurring during the life of the bond." Id.
We likewise conclude that it would be poor public policy to bar the obligation of the surety Safeco under R.C.
Finally, we must take issue with Thomas Steel's contention that R.C.
"If a general provision conflicts with a special or local provision, they shall be construed, if possible, so that effect is given to both. If the conflict between the provisions is irreconcilable, the special or local provision prevails as an exception to the general provision, unless the general provision is the later adoption and :the manifest intent is that the general provision prevail."
In Andrianos v. Community Traction Co. (1951),
"A special statutory provision which relates to the specific subject matter involved in litigation is controlling over a general statutory provision which might otherwise be applicable."
The limitations provision under R.C.
Assignment of Error III is overruled.
Judgment affirmed.
PATTON and ROCCO, JJ., concur. *Page 109