DocketNumber: No. 08CA009433.
Citation Numbers: 182 Ohio App. 3d 39, 2009 Ohio 1910, 911 N.E.2d 356
Judges: Whitmore, Carr, Moore
Filed Date: 4/27/2009
Status: Precedential
Modified Date: 10/19/2024
[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 41 {¶ 1} Plaintiff-appellant, Building Industry Consultants, Inc. ("BIC"), appeals from the judgment of the Lorain County Court of Common Pleas granting summary judgment in favor of defendant-appellee, 3M Parkway, Inc. This court reverses.
{¶ 3} On July 10, 2006, 3M Parkway and NVR agreed to terminate their lot-purchase agreement because 3M Parkway was "unable to achieve the rezoning of the Property to allow the development contemplated by the Agreement." On July 27, 2006, BIC sent 3M Parkway an invoice. The invoice sought $28,000 from 3M Parkway "for construction management services to date." 3M Parkway refused to pay BIC the $28,000.
{¶ 4} On March 1, 2007, BIC brought suit against 3M Parkway for $28,000 on the basis of breach of contract, accounting, and quantum meruit. The parties conducted discovery, and 3M Parkway filed a motion for summary judgment on February 19, 2008. BIC responded in opposition on March 28, 2008. On June 13, 2008, the trial court granted 3M Parkway's motion for summary judgment. *Page 42
{¶ 5} BIC now appeals from the trial court's judgment and raises one assignment of error for our review.
{¶ 6} In its sole assignment of error, BIC argues that the trial court erred in granting 3M Parkway's motion for summary judgment on BIC's quantum meruit claim. Specifically, BIC argues that genuine issues of material fact exist as to its quantum meruit claim because (1) the parties did not have an enforceable contract that would bar recovery under a quantum meruit theory and (2) 3M Parkway received a benefit from BIC's services. We agree.
{¶ 7} This court reviews an award of summary judgment de novo. Grafton v. Ohio Edison Co. (1996),
{¶ 8} Pursuant to Civ. R. 56(C), summary judgment is proper if:
(1) No genuine issue as to any material fact remains to be litigated; (2) the moving party is entitled to judgment as a matter of law; and (3) it appears from the evidence that reasonable minds can come to but one conclusion, and viewing such evidence most strongly in favor of the party against whom the motion for summary judgment is made, that conclusion is adverse to that party.
Temple v. Wean United, Inc. (1977),
{¶ 9} In its motion for summary judgment, 3M Parkway simultaneously argued that it and BIC contractually agreed upon BIC's specific compensation, BIC *Page 43 could not recover under the contract because a condition precedent in the contract failed, and BIC could not recover under a quantum meruit theory because that theory does not apply when an express contract exists. In support of its motion, 3M Parkway relied upon the March 23, 2004 and March 19, 2005 letters BIC sent to 3M Parkway. The March 23, 2004 letter provided as follows:
In accordance with the request by * * * your counsel, * * * we have prepared preliminary budgets from September, 2003 to March, 2004. We also did preliminary investigative work for the project captioned above.
Per our discussion, [BIC] agreed to do this work at no cost to you, with the understanding that, if the project is determined feasible, [BIC] would become your Construction Manager. As of the writing of this letter, all costs incurred will be billable.
We will proceed with preliminary work, i.e., soil borings, wetlands, etc., in order to start this project and secure a building permit. We have agreed to hold our billing until the first construction draw, due to your current financial position.
If our understanding of this agreement is different * * *, please respond in writing in seven days from the date of this letter. * * *
The March 19, 2005 letter was comprised of a revised budget. 3M Parkway argued that these letters constituted the parties' agreement.
{¶ 10} In its motion in opposition to summary judgment, BIC argued that the parties never had an express contract regarding BIC's construction-management services. Instead, BIC argued that the parties had a quasicontractual relationship, which entitled BIC to equitable relief. In support of its motion in opposition, BIC pointed to the same evidence as 3M Parkway, as well as to Lynn's July 8, 2003 letter, which was printed on Prete Builders, Inc., letterhead. BIC noted that the parties never agreed upon a contract price because Lynn quoted 3M Parkway multiple price terms during the course of their relationship. Lynn initially quoted 3M Parkway a total cost of $2,301,570, later indicated in a related contract for brush hogging with 3M Parkway that the total cost of the project would be $2,704,420, and finally quoted a total cost of $3,297,188. Lynn's initial quote and final quote also contained different contingency fees. While Lynn's initial letter quoted a contingency fee of seven percent, his final letter quoted a contingency fee of eight percent. Moreover, BIC pointed to the deposition testimony of one of 3M Parkway's co-owners, Gary Mintz, who testified that (1) BIC was never 3M Parkway's construction manager (2) BIC merely sent 3M Parkway proposals for its fees and duties, followed by the March 2004 letter indicating that "until the approvals and the project was determined feasible, David Lynn would not be our construction manager," (3) the project's feasibility depended upon the city's rezoning the project area, which never occurred, and (4) because the rezoning never occurred, 3M Parkway never hired *Page 44 a construction-services manager.1 Mintz testified that BIC performed "some preparation work and miscellaneous stuff" for 3M Parkway, but did so only in "prepar[ation] to be construction manager."
{¶ 11} The trial court determined that the March 23, 2004 letter BIC sent to 3M Parkway constituted an express agreement between the parties. The trial court understood the above-quoted letter to mean that (1) BIC prepared preliminary budgets and performed investigative work for 3M Parkway for free, (2) BIC would charge 3M Parkway only "for the ``costs' incurred by [BIC] in performing the preliminary work," (3) BIC agreed to perform these services for 3M Parkway in consideration for being named construction manager, and (4) BIC's being named construction manager depended upon the condition of the project being "determined feasible." The trial court determined that 3M Parkway demonstrated that its project was infeasible because the city never agreed to rezone the project area. Accordingly, the trial court held that BIC could not recover under a contract theory because any contractual obligation terminated after the condition precedent of project feasibility failed.
{¶ 12} "This court will affirm a trial court's decision granting summary judgment on other grounds if the trial court's decision is legally correct." Fleck v. Hammer, 9th Dist. No. 23533,
{¶ 13} Apart from the fact that BIC conceded in its motion in opposition that it did not have an express contract with 3M Parkway, our review of BIC's March *Page 45 23, 2004 letter leads us to conclude that the trial court erred in determining that the letter constituted an express agreement. Lynn quoted 3M Parkway three different estimates and two different contingency fees over the course of their correspondence. Furthermore, Lynn sent his initial quote to 3M Parkway on letterhead from Prete Builders, Inc., a different company to which he belonged. The letter made no mention of BIC. BIC's March 23, 2004 letter also did not contain any starting or ending dates for BIC's performance. While BIC and 3M Parkway entered into a formal, written contract for the "brush hogging" work that BIC performed, the record is devoid of any evidence that 3M Parkway ever entered into a written contract for BIC's other services. 3M Parkway's co-owner, Gary Mintz, testified in his deposition that BIC performed work only in "prepar[ation] to be construction manager." He further testified as follows:
It's my understanding that 3M Parkway and [BIC] — at the time the approvals were obtained by the City of North Ridgeville, 3M Parkway and [BIC] would have entered into a construction management contract and the payment schedule and the terms and conditions would have been outlined specifically there, outlining the exact amount and when those payments would be made. It never happened because the approvals were never made, thus the fee is not due and owed.
Mintz referred to Lynn's letters as "proposals" and to Lynn's total cost estimates as "proposed budget[s]." Accordingly, by Mintz's own deposition testimony, even 3M Parkway did not understand the parties to have a contractual relationship.
{¶ 14} Based on the fact that the parties never assented to definite and certain terms of a contract and the fact that both parties indicated that they did not believe they had an express contract, the trial court erred in determining that BIC's March 23, 2004 letter constituted the agreement of the parties. Because the parties did not have a contract, however, the trial court correctly concluded that BIC could not recover pursuant to a contractual theory. Consequently, this portion of the trial court's opinion is correct, albeit on different legal grounds. Fleck,
{¶ 15} In its motion for summary judgment, 3M Parkway also argued that BIC could not recover $28,000 under an unjust-enrichment claim because that amount represented a "pro rata portion (12.5%) of [BIC's] construction management fee" under the parties' contract. Because an express agreement covered those services, 3M Parkway argued, the doctrine of quantum meruit could not apply. The trial court agreed with 3M Parkway's analysis and determined that BIC could not recover under a quantum meruit theory because "[t]he doctrines of unjust enrichment and quantum meruit are ``inapplicable if an express agreement [March 23, 2004 letter] existed concerning the services for which compensation is sought.' Pawlus v.Bartug [Bartrug] (1996),
{¶ 16} "The elements of unjust enrichment and quantum-meruit are identical." Coyne v. Hodge Const.,Inc., 9th Dist. No. 03CA0061-M,
{¶ 17} While it is true that a party may not recover for the same services under both a contractual claim and a claim for quantum meruit, a party is not barred from seeking alternative theories and recovering under a quantum meruit theory if his contractual claim fails. See Zeck v.Sokol, 9th Dist. No. 07CA0030-M,
Judgment reversed and cause remanded.
CARR, J., concurs.
MOORE, P.J., dissents.
Jochum v. Howard Hanna Co. , 2020 Ohio 6676 ( 2020 )
Mun. Servs. Corp. v. Hall Community Dev., L.L.C. , 2019 Ohio 3079 ( 2019 )
Fedex Corporate Serv., Inc. v. Heat Surge, L.L.C. , 2019 Ohio 217 ( 2019 )
Magnum Steel & Trading, L.L.C. v. Mink , 2013 Ohio 2431 ( 2013 )
J. Bowers Constr. Co., Inc. v. Gilbert , 2014 Ohio 3576 ( 2014 )
Carter v. Univ. Park Dev. Corp. , 2022 Ohio 3462 ( 2022 )