DocketNumber: 48203
Citation Numbers: 487 N.E.2d 329, 21 Ohio App. 3d 104
Judges: McManamon, Parrino, Markus
Filed Date: 12/17/1984
Status: Precedential
Modified Date: 11/12/2024
Appellant, James Ratner, acting as trustee for the owners of Parmatown Mall, submitted a dispute with appellee, Hellmuth, Obata and Kassabaum, architects ("HOK") to the American Arbitration Association pursuant to a contractual agreement previously entered into by the parties. On February 23, 1983 the arbitrators found in favor of appellant and against appellee on all claims and awarded $666,400 to appellant. HOK tendered a draft in that amount on May 25, 1983, which appellant accepted in partial satisfaction of the obligation excluding interest, which it claimed from the date of the award.
On October 13, 1983, appellant filed its application in the common pleas court for confirmation of the award as well as interest for the period of February 23 to May 25, at the statutory rate.
The trial court subsequently entered judgment on December 28, 1983 confirming the award, as well as interest in the sum of $17,445.52 on behalf of appellant. No appeal of this order was taken by appellee.
The docket reflects two additional entries by the court on January 6, 1984. In the first entry, the court stated "defendant's motion to confirm arbitration award [is] granted." The second entry orders "plaintiff's motion to strike and/or motion to deny request for interest on award is granted."1
On January 18, 1984 another entry was docketed in which the court sua sponte vacated its original confirmation award of December 28, 1983.
Ratner's motion for relief from this latter judgment was overruled on February 15, 1984. On the same day the court entered another confirmation award, this time allowing no interest to appellant.
Ratner presents a timely appeal from the court's entries of January 18, 1984 and the February 15, 1984 order of confirmation, raising one assignment of error:
"The trial court erred in denying defendant-appellant's request for interest on its arbitration award and ruling the Ohio Rev. Code §
For the reasons stated in this opinion the assignment of error is well-taken and we reverse the orders challenged by appellant.
R.C.
"(A) In cases other than those provided for in sections
The issue raised by appellant presents a case of first impression in the Ohio state courts.
Appellee argues that the cases upon which appellant relies are inapplicable because they interpret statutes that are inapposite to Ohio law.
In Columbine Valley Constr. Co. v. Bd. of Directors (Colo. 1981),
"As to interest, section
In Lundgren v. Freeman (C.A. 9, 1962),
"The Oregon general interest statute provides not only that interest is payable on moneys after they become ``due' (ORS § 82.010(1)(a)), and on money due upon the settlement of matured accounts ``from the day the balance is ascertained' (ORS § 82.010(1)(d)), but also provides that interest on judgment and decrees for the payment of money shall be from the date of their entry. Oregon Revised Statutes, § 82.010(1)(b). The last is true even if there is a subsequent appeal — if the judgment is affirmed. But if the judgment is modified on appeal, interest runs as of the date of modification. (Compton v. Hammond LumberCo., 1936,
"We think that, in the application of this policy, the Oregon courts would hold that interest runs from the date of the award. The parties selected arbitrators, rather than a court, as the body that would, in the first instance, determine the amount due. This they had a right to do; this the law encourages them to do. It should be the rule, rather than the exception, that when arbitrators hand down an award the parties will comply with it, without the necessity of court proceedings, just as it is (or should be) the normal or usual result that parties comply with a judgment, without the necessity of resort to process or appeal."
We find that both these cases involve statutes which closely resemble the law in Ohio and we adopt their application as well as their expressed policy concerns.
Although HOK urges that any order by the trial court granting interest would be tantamount to a failure to confirm the award as determined by the arbitrators, we find that this position is unsupported by legal authority. We note that the issue of whether interest should *Page 107 accrue from the date of the award was not a matter presented to the arbitrators.
In Braverman v. Spriggs (1980),
"* * * The running of interest is not delayed because the debtor denies owing the debt, but, rather, is delayed only where the amount is unliquidated, that is, the amount of the debt is uncertain. Where the amount of the debt is clear, but the only question raised is whether the plaintiff is entitled thereto, interest runs on the debt from the time that it was due and payable, as eventually found by the court. * * *"
Our conclusion is that the award of the arbitrators in the sum of $666,400 was a liquidated amount, due and payable on the date the award was rendered. We further find that such an award qualifies under the statute as an "instrument of writing * * * upon * * * [a] settlement between parties * * * for the payment of money arising out of tortious conduct or a contract or other transaction * * *." Consequently, the appellant is entitled to interest upon it from the inception of the award as provided by R.C.
We note that public policy considerations encourage effective conflict resolution and the statute provides the instrument to promote this end.
We find, as a matter of law, that the trial court properly confirmed the arbitrators' award and ordered the requested interest on December 28, 1983. However, subsequent to this order, the trial court journalized three additional entries in an apparent attempt to vacate the December 28th judgment as well as a fifth entry on February 15, 1984 which confirmed the award but denied interest. A trial court has no authority to vacate its orders sua sponte.2 Accordingly, the entries of January 6, 1984, which are in conflict with the court's original judgment, are nullities.
The orders appealed from are reversed.
Judgments reversed.
PARRINO, P.J., and MARKUS, J., concur.
Compton v. Hammond Lumber Co. , 154 Or. 650 ( 1936 )
north-drive-in-theatre-corporation-and-cross-appellee-v-park-in-theatres , 248 F.2d 232 ( 1957 )
Columbine Valley Construction Co. v. Board of Directors , 1981 Colo. LEXIS 651 ( 1981 )
York Plumbing & Heating Co. v. Groussman Investment Co. , 166 Colo. 382 ( 1968 )
T. & M. Transp. Co. v. S. W. Shattuck Chemical Co. , 158 F.2d 909 ( 1947 )
james-lundgren-dba-pacific-construction-company-v-claude-freeman-sydney , 307 F.2d 104 ( 1962 )