DocketNumber: Case Nos. 99CA16, 99CA17, 99CA18.
Citation Numbers: 740 N.E.2d 328, 138 Ohio App. 3d 57, 2000 Ohio App. LEXIS 2548
Judges: Kline, Abele, Grey
Filed Date: 6/6/2000
Status: Precedential
Modified Date: 10/19/2024
[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 59
[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 60
[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 61
[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 62
[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 63
Accordingly, we overrule each of Crane Hollow, Metro Parks, and the other landowners' assignments of error and we affirm the judgment of the trial court.
The FR-25 was used for the transportation of natural gas from 1916 until 1986, when its owner and Marathon's direct predecessor in interest, Columbia Gas Transmission Corporation, capped off portions of the FR-25 due to deterioration. When Marathon acquired the FR-25 easement from Columbia, it notified the landowners of its intent to replace the FR-25 with a modern pipeline capable of carrying liquid petroleum. Marathon further notified the landowners that it would remove all trees within seventy-five feet of the FR-25 in order to replace it, and that it would maintain a fifty-foot clearing for maintenance purposes.
The ensuing dispute prompted the parties to file three separate lawsuits in the trial court, each seeking injunctions or declaratory relief. The trial court consolidated the three actions and conducted a bench trial. *Page 65
At trial, the landowners presented evidence of numerous large trees growing within seventy-five feet of the FR-25. They also presented evidence that portions of the FR-25 had not been used since 1986, and that it had rust holes in it. Additionally, they presented evidence that Columbia executed an agreement with Metro Parks (the "Cooperative Agreement") that altered and limited the rights associated with the FR-25 on a few properties.
Marathon submitted historical evidence that large trees were used as forms for putting fire bends in pipes and as leverage anchors for moving heavy sections of pipe when the FR-25 was constructed. Large groups of men assisted by teams of oxen and horses constructed the FR-25. The construction process required a great deal of space to accommodate the men, animals, materials and equipment.
Austin Cramer, a former Columbia employee who was in charge of maintaining the northern portion of the FR-25 from 1979 through 1995, testified that he cleared small trees and brush in a fifty-foot wide strip surrounding the FR-25 on a regular basis. Cramer stated that he left large trees in place to avoid damaging the FR-25. Marathon submitted Cramer's detailed daily logbooks in which he recorded his clearing activities. Cramer also testified about his co-worker's clearing activities that occurred on the southern portion of the FR-25.
Finally, Marathon presented evidence that the Cooperative Agreement applied only to pipelines that are part of the Crawford Storage Field and that the FR-25, while in the vicinity of the Crawford Storage Field, is not part of the Crawford Storage Field.
The trial court found that Marathon established, based upon its predecessor's use and the landowners' acquiescence, that the easement is fifty feet wide. The trial court further found that the width of the construction easement was established at seventy-five feet based upon use and acquiescence. The trial court also found that Columbia did not abandon the easement when it took the FR-25 out of service. Finally, the trial court found that the Cooperative Agreement did not apply to the FR-25 pipeline.
The landowners appeal, asserting the following assignments of error:
*Page 66I. The trial court's decision that the width of the FR-25 easement was 50 feet based upon use and that the line was originally constructed in 1916 using 75 feet was against the manifest weight of the evidence.
II. The trial court abused its discretion by expanding the width of the easement established by historical use and acquiescence.
III. The trial court's decision that the FR-25 easement was not abandoned on the property of appellants Daniels, Pierce and Metro Parks was against the manifest weight of the evidence.
IV. It was plain error for the trial court to conclude that the cooperative agreement between Columbus and Franklin County Metropolitan Park District and Columbia Gas did not prohibit or restrict the proposed replacement of the FR-25 line with Clear Creek Metro Park and that the Cooperative Agreement had been surrendered.
A reviewing court will not reverse a judgment as being against the manifest weight of the evidence when the judgment is supported by some competent, credible evidence going to all the essential elements of the case. C.E. Morris Co. v. Foley Constr.Co. (1978),
An easement is an interest in the land of another, created by prescription or express or implied grant, that entitles the owner of the easement, the dominant estate, to a limited use of the land in which the interest exists, the servient estate.Alban v. R.K. Co. (1968),
The grant of an easement includes the grant of all things necessary for the dominant estate to use and enjoy the easement.Day, Williams Co. v. RR. Co. (1884),
An easement holder may not increase the burden upon the servient estate by engaging in a new and additional use of the easement. Lakewood Homes, Inc. v. BP Oil, Inc. (Aug. 26, 1999), Hancock App. No. 5-98-29, unreported, citing Centel CableTelevision Co. of Ohio, Inc. v. Cook (1991),
When the extent of the rights conveyed in an easement, such as the dimensions of the easement, are not apparent from the language of the grant, the dimensions may be established by use and acquiescence. Munchmeyer v. Burfield (March 26, 1996), Washington App. No. 95CA7, unreported, citing Bruce and Ely, Law of Easements and Licenses in Land (1988), Sections 7.02(2)(b) and 7.06. Once so established, the easement holder is *Page 68
estopped from asserting that different dimensions are reasonably necessary or convenient. Id. However, if the language of the grant clearly gives the easement holder a right in excess of the one actually used, such right still exists notwithstanding the easement holder's exercise of a lesser privilege. East OhioGas Co. v. James Bros. Coal Co. (1954), 53 Ohio Law. Abs. 438, 85 N.E.2d 816, 818; Panhandle Eastern PipelineCo. v. Tishner (In.App. 1998),
Several Ohio courts have construed language similar to that contained in the FR-25 grant and determined that a width of fifty feet is reasonably necessary and convenient for the maintenance of a pipeline. Columbia Gas Transm. Corp. v. Davis (S.D.Ohio 1998),
At trial, Marathon submitted evidence that workers actually used the large trees along the easement to assist in installing the original FR-25 pipeline. Specifically, Marathon submitted historical evidence that large trees were used as forms for putting fire bends in pipes and as leverage anchors for moving heavy sections of pipe. Bends and wrinkles in the FR-25 prove that these methods *Page 69 were used in its installation. Additionally, Marathon presented evidence that its predecessors maintained the FR-25 easement at fifty feet by bulldozing brush around the trees. A former Columbia maintenance employee testified that he intentionally did not cut down the large trees because doing so would have damaged the FR-25 pipeline. Thus, Marathon presented evidence that cutting down the trees actually would have been inconsistent with maintaining the pipeline.
While the record contains some unrebutted evidence of large trees growing on the easement, the record also contains some competent, credible evidence that the tree growth is not inconsistent with Marathon's use of the easement. The record shows that Marathon and its predecessors maintained the width of the easement by bulldozing brush, spraying herbicides, and leaving large trees standing. Therefore, we find that in this instance tree growth is related to Marathon's mode of use of the easement, not the width of the easement. Accordingly, we find that the record contains some competent, credible evidence that Marathon and its predecessors maintained the easement in question at a width of fifty feet.
Although Marathon and its predecessors did not remove trees from the easement in order to maintain it in the past, Marathon is entitled to vary the mode by which it uses the easement. SeeOhio Oil Gathering Co., supra. Aerial observation constitutes a modern invention that enables Marathon to more freely exercise its right to maintain the easement. We presume that the parties contemplated some normal developmental changes in the mode of use of the easement. See Ohio Oil Gathering Co., supra; Knox, supra. Therefore, even if the parties did not specifically foresee the possibility that the easement owner would use aerial observation to maintain the pipeline, aerial observation is permissible under the terms of the easement because it constitutes a mode of accomplishing the easement's purpose, i.e., maintaining the easement. *Page 70
A review of the record reveals that Marathon presented historical evidence of the methods available for constructing pipelines at the time the FR-25 was constructed. Curves and wrinkles in the FR-25 prove that the fire bends and brace and tackle type leverage anchors were used in its installation. These processes required large groups of men, teams of horses and oxen, and large trees. The evidence further reveals that these men and animals would have required a working and camping area approximately seventy-five feet wide.
We find that the foregoing constitutes some competent, credible evidence that the original construction easement for the FR-25 was approximately seventy-five feet wide. Competent, credible evidence also supports Marathon's contention that large trees in the easement area do not define the boundaries of the construction easement, because those trees were used in furtherance of the construction of the FR-25. Therefore, we find that the trial court's determination that the construction easement was established at seventy-five feet by use and acquiescence is not against the manifest weight of the evidence.
Because some competent, credible evidence supports the trial court's judgment, we find that the trial court did not err in defining the width of the maintenance and construction easements. Accordingly, we overrule the landowners' first assignment of error.
Marathon asserts that, although its predecessors failed to clear even young trees and brush in some areas, the record also contains some competent, credible evidence that Marathon's predecessors maintained a clearing more than seventy-five *Page 71 feet wide in other areas. Therefore, Marathon concludes that the trial court had the authority to weigh the parties' competing interests and equitably divide their property rights according to that which is reasonably necessary and convenient to serve the purpose for which the easement was granted.
When a party invokes the trial court's equitable jurisdiction, the trial court possesses discretionary authority to weigh the parties' competing interests and exact an equitable division of their property rights. Murray v. Lyon (1994),
A court of equity abuses its discretion when it alters an established easement or requires a party to accept an altered easement in substitution of the original. Munchmeyer, supra;Hollosy v. Gershkowitz (1951),
In this case, the landowners and Marathon invoked the trial court's equitable jurisdiction by seeking injunctions against each other. The record contains some competent, credible evidence that Marathon and its predecessors generally maintained the easement at a width of fifty feet, but that the maintained width varied between zero and seventy-five feet in some locations. Thus, the trial court's determination that the easement's width was not established in some locations was not against the manifest weight of the evidence. Consequently, the trial court possessed the discretionary authority to equitably divide the property rights by defining a consistent width for the easement.
The trial court based its equitable determination upon what is reasonably necessary and convenient to maintain the utility of the easement. We cannot say that the trial court's determination that fifty feet is an equitable width is arbitrary, unreasonable, or unconscionable. Therefore, the trial court did not abuse its discretion in defining the width of the easement as fifty feet in those areas where the width had not been established by use and acquiescence.
Accordingly, we overrule the landowners' second assignment of error. *Page 72
To demonstrate that a dominant estate has abandoned its easement, the servient estate must establish both (1) nonuse of the easement, and (2) an intent to abandon the easement. Snyderv. Monroe Twp. Trustees (1996),
The landowners presented evidence that Marathon's immediate predecessor in interest, Columbia, capped off a portion of the FR-25 in 1986 and transferred its natural gas customers from the FR-25 to another natural gas line. Additionally, the landowners presented evidence that after Columbia capped the line, it allowed it to deteriorate and rust. The landowners also produced a 1989 letter from a Columbia manager to the Metro Parks director, which states that Columbia has four pipelines that cross Metro Parks land: the E, the R-453, the SR-545 and the SR-580. In a similar letter written seven years earlier, before Columbia capped the FR-25, Columbia lists the FR-25 among its pipelines. Finally, a Marathon employee testified that he had heard of the FR-25 and was told that it was an abandoned line.
Austin Cramer, a Columbia employee, maintained the northern portion of the FR-25 from 1979 until his retirement in November 1995. Cramer testified that he made an effort to keep the FR-25 easement clear to a width of fifty feet even after he capped the line and diverted the customers to a newer, safer line. *Page 73 However, Cramer admitted that he did a better job maintaining the easement before he capped it. Cramer testified that he tried to keep the easement as clear as possible because he was told that Columbia planned to reopen or replace the FR-25. Marathon submitted Cramer's daily logbooks to support his testimony. Finally, Marathon showed that Columbia assigned the FR-25 easement to Marathon, thus evidencing Columbia's belief that it still possessed the easement and had not abandoned it.
We find that Cramer's testimony, combined with Columbia's assignment of the easement, constitutes some competent, credible evidence that Columbia did not intend to abandon the easement. Further, we find that the evidence that the landowners produced clearly demonstrates that Columbia stopped using a portion of the FR-25, but does not demonstrate that Columbia took unequivocal and decisive acts inconsistent with the continued use of the easement. Therefore, we find that the trial court's determination that Columbia did not abandon the easement is not against the manifest weight of the evidence.
Accordingly, we overrule the landowners' third assignment of error.
A court must interpret a contract so as to carry out the intent of the parties. Foster Wheeler Enviresponse, Inc. v.Franklin Cty. Convention Facilities Auth. (1997),
If the contract's terms are unambiguous, a court may not interpret the contract in a manner inconsistent with those terms.Alexander v. Buckeye Pipe Line Co. (1978),
If a contract is clear and unambiguous, then its interpretation is a matter of law that we review de novo.Nationwide Mut. Fire. Ins. Co. v. Guman Bros. Farm (1995),
In this case, the Cooperative Agreement is susceptible of two reasonable interpretations on its face. In some places the agreement purports to apply to those pipelines that are part of the Crawford Storage Field and to be "subject to" existing easements and pipelines located in the Crawford Storage Field area. In other places, the agreement refers to "all pipelines" depicted on the map. The map depicts Crawford Storage Field pipelines (those connected to storage wells) with a thick black line. Non-Crawford Storage Field pipelines are illustrated with a medium black line, and thin black lines show property boundaries. The map's legend does not reflect any distinction based upon the width of the black lines. Rather, it simply labels all black lines as completed Crawford Storage Field pipelines. The Cooperative Agreement could be reasonably interpreted to refer to either (1) all pipelines that were a part of the Crawford Storage Field or (2) all pipelines in the area of the Crawford Storage Field. We find that the trial court did not err in concluding that the Cooperative Agreement is ambiguous on its face.
The record in this case reveals that when the Cooperative Agreement was executed the FR-25 was an active field gathering line that crossed a portion of the Crawford Storage Field area. The FR-25 was not used for storage or linked to any storage well. Ralph Edwards, who executed the Cooperative Agreement in his capacity as Columbia's vice president of storage, possessed authority over storage pipelines, but not over field gathering pipelines such as the FR-25. *Page 75 Columbia's objective in entering into the Cooperative Agreement, as stated in the first paragraph of the Cooperative Agreement, was to facilitate the development of the Crawford Storage Field. We find these facts and circumstances constitute some competent, credible evidence that the parties intended that the Cooperative Agreement apply only to those pipelines that were part of the Crawford Storage Field. Therefore, the trial court did not err in finding that the Cooperative Agreement is inapplicable to the FR-25 easement. Because the Cooperative Agreement is inapplicable to the FR-25, we need not examine whether Columbia possessed the power to surrender the agreement with respect to the FR-25.
Accordingly, we overrule the landowners' final assignment of error.
Accordingly, we affirm the judgment of the trial court.
JUDGMENT AFFIRMED.