DocketNumber: No. WD-07-011.
Citation Numbers: 890 N.E.2d 356, 176 Ohio App. 3d 127, 2008 Ohio 1791
Judges: Pietkykowski, Skow, Osowik
Filed Date: 4/11/2008
Status: Precedential
Modified Date: 10/19/2024
[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 129
[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 130 {¶ 1} This case is before the court on appeal of the January 26, 2007 judgment of the Wood County Court of Common Pleas that granted in part appellants and cross-appellees' motion to dismiss appellees' complaint and to compel arbitration and stay the proceedings pending arbitration. For the reasons that follow, we reverse in part.
{¶ 2} A recitation of the relevant facts is as follows. In October 2002, appellees, Fadhil Hussein and Raya Ahmed, purchased two parcels of real estate on West River Road, in Perrysburg, Wood County, Ohio, from appellant Hafner Shugarman Enterprises, Inc. ("H S"). In consideration for a significant reduction in the purchase price, appellees agreed to use appellants (d.b.a. Hafner Crafted Homes) for any future construction of a single-family residence.
{¶ 3} Thereafter, on July 14, 2004, the parties contracted for the construction of an approximately 9,000-square-foot home, for an estimated contract price of $1,353,439. The construction contract contained the following arbitration clause: "In case any dispute or claim arises between the parties hereto under or growing out of this contract or the performance thereof, such dispute shall be resolved by arbitration by an arbitrator jointly selected by the parties from the Toledo Bar Association."
{¶ 4} At some point during the construction of the home, disputes arose regarding construction delays and defects, Perrysburg's refusal to issue an occupancy permit for the home due to these defects, and increased costs. The parties orally agreed to an additional penalty clause, which provided that if the home was not completed by May 31, 2006, H S would pay appellees $5,000 each additional week.
{¶ 5} Appellees moved into the home in July 2006; however, disputes remained regarding the condition of the home and the outstanding balance on the contract price. In a letter dated August 14, 2006, H S requested that the parties *Page 131 submit to arbitration. On August 21, 2006, appellees commenced the instant action against H S and David Hafner and Jeffrey Shugarman, individually.
{¶ 6} Appellees alleged the following causes of action: (1) fraud in the factum, (2) fraud, (3) breach of contract, (4) breach of express warranty, (5) breach of a novation, (6) unjust enrichment, (7) negligence, (8) violation of Ohio Consumer Sales Practices Act ("CSPA"), and (9) piercing the corporate veil. Appellees also sought a declaratory judgment with regard to certain outside work, including the sidewalks, the driveway, and the flood plain.
{¶ 7} On September 12, 2006, appellants filed a motion to dismiss or alternatively a motion to stay the proceedings and order arbitration. In their motion, appellants argued that the arbitration clause in the construction contract was broadly worded and that appellees' claims fell within the scope of the clause. Appellees opposed the motion, making specific arguments as to why the various claims were not subject to arbitration. First, appellees argued that the fraud-in-the-factum claim asserts that the entire contract is void ab initio. Next, appellees argued that because the CSPA claim seeks rescission and argues fraud in the inducement, it is not subject to arbitration. Appellees further argued that they alleged a novation, a later agreement that replaced the construction contract and did not contain an arbitration clause. Finally, appellees argued that if the court did order arbitration, it should stay, rather than dismiss, appellees' complaint.
{¶ 8} A hearing on the motion was held on January 22, 2007, and the following relevant evidence was presented. Appellee, Fadhil Hussein, testified on cross-examination that he had been looking at purchasing the subject property, two four-acre parcels, for quite a long time. The original asking price was $320,000 for each parcel, or $640,000. After lengthy negotiations, the price was reduced to $350,000. Hussein testified that the sale price was conditioned on giving Hafner Crafted Homes the opportunity to construct a residence on the land or recover half of the profit if the land was resold within three years.
{¶ 9} Hussein testified that he was represented by counsel when he signed the construction contract and that his attorney approved the contract. Specifically, Hussein stated that he freely agreed to the arbitration clause in the contract. Hussein stated that he presented Hafner with an additional agreement, prepared by his attorney, to motivate them to finish the job. Hussein agreed that the purpose of the agreement was not to change the terms of the original agreement. Hussein testified that he "felt like [he] was swindled long before [he] entered into [the construction] contract" and that is why he proceeded with the lawsuit rather than agreeing to submit to arbitration.
{¶ 10} Jeffrey Shugarman testified that he is the vice-president of Hafner Crafted Homes. Shugarman testified regarding the price changes of several *Page 132 items involved in the contract. Shugarman stated that some prices were increased while others were significantly lower than what was quoted.
{¶ 11} Cross-examination of Shugarman focused on appellees' fraud claims. Shugarman was questioned about the Ohio Department of Transportation ("ODOT") permit issued on October 25, 2000, allowing H S to construct a driveway with access from S.R. 65 to residential properties. The permit set forth the specifications for the driveway and stated that "[a]ny change in the use of the permitted access inconsistent with its terms and conditions will be considered a violation of this permit and cause for removal of the permitted installation at the permittee's cost."
{¶ 12} Shugarman was then questioned about a permit inspection certificate issued on July 17, 2002, which indicated that the work had not been completed in accordance with ODOT specifications. Shugarman testified that Hussein knew that the driveway was not complete prior to purchasing the lots; however, Hussein was not informed of the ODOT-deficiency letter. Shugarman stated that because the driveway was a "work in progress," he did not feel that Hussein needed to be informed.
{¶ 13} Shugarman was also questioned about the fact that the city of Perrysburg found that there was insufficient concrete poured for the foundation of the home. Shugarman testified that he would not inform an owner about such a problem if the problem was corrected and did not cost the owner anything. Shugarman testified that the foundation later cracked; he denied that he or his partner tried to hide it from appellees.
{¶ 14} Shugarman was further questioned about the October 2002 real-estate purchase contract, specifically, the provision representing that the seller had not received notice that the property was not in compliance with any "laws, orders, rules or regulations, ordinances and codes of any kind." Shugarman acknowledged that "[i]n the context of reviewing it, right now I can see that probably would have been a good thing to tell him."
{¶ 15} At the conclusion of the testimony, appellees introduced an affidavit from Trish Branam, Executive Director of the Toledo Bar Association. The affidavit stated that contrary to the arbitration clause, the Toledo Bar Association does not provide arbitrators or arbitration services.
{¶ 16} At the conclusion of the hearing, the trial court stated that the arbitration clause applied to the breach-of-contract claim; the court dismissed that claim alone. The court then stated that the majority of appellees' claims were related to fraud and misrepresentation and violations of the CSPA that "really are not arbitrable issues." In its January 26, 2007 judgment entry, the trial court clarified that appellees' breach-of-contract claim was dismissed without *Page 133 prejudice pending arbitration. The trial court did not stay the proceedings relative to the remaining claims pending arbitration. This appeal followed.
{¶ 17} Appellants now present the following two assignments of error:
{¶ 18} "I. First Assignment of Error. Once the trial court determined that the arbitration clause was a valid and enforceable provision of the parties' contract, the trial court erred by finding that the arbitration clause only applied to Appellees' claim for breach of contract.
{¶ 19} "II. Second Assignment of Error. Once the trial court determined that the arbitration clause was a valid and enforceable provision of the contract, the trial court erred in failing to stay the entire case until the issues subject to arbitration are resolved."
{¶ 20} Appellees and cross-appellants raise the following assignment of error:
{¶ 21} "[D]id the trial court err when it held that Plaintiffs' claim for breach of contract was arbitrable when in fact the entire Construction Contract was void ab initio?"
{¶ 22} Prior to addressing the merits of the parties' arguments, we must determine the appropriate standard of review. Appellants contend that a de novo standard of review is appropriate; conversely, appellees espouse that an abuse-of-discretion standard of review generally applies to decisions regarding the arbitrability of a dispute. Generally, Ohio courts have applied an abuse-of-discretion standard when reviewing a trial court's decision granting or denying a motion to stay proceedings and compel arbitration. Recently, the Supreme Court of Ohio held that a de novo standard of review applies in cases regarding the unconscionability of an arbitration clause. Taylor Bldg. Corp. of Am. v.Benfield,
{¶ 23} Based on the foregoing, we will review de novo the question of whether, as a matter of law, a particular claim is subject to arbitration. However, the trial court's factual findings will be accorded deference. The trial court conducted a hearing on the matter with the specific purpose of gaining information regarding the factual bases of the claims.
{¶ 24} Appellants argue in their first assignment of error that the trial court erred when it limited the enforceability of the arbitration clause to appellees' breach of contract claim. Conversely, appellees' assignment of error disputes the trial court's determination that their breach-of-contract claim was *Page 134
arbitrable. Initially, we note that arbitration is encouraged as a method of dispute resolution and a presumption favoring arbitration arises when the claim in dispute falls within the arbitration provision. Williams v. Aetna Fin. Co.
(1998),
{¶ 25} "A provision in any written contract, except as provided in division (B) of this section, to settle by arbitration a controversy that subsequently arises out of the contract, or out of the refusal to perform the whole or any part of the contract, or any agreement in writing between two or more persons to submit to arbitration any controversy existing between them at the time of the agreement to submit, or arising after the agreement to submit, from a relationship then existing between them or that they simultaneously create, shall be valid, irrevocable, and enforceable, except upon grounds that exist at law or in equity for the revocation of any contract."
{¶ 26} Appellants cite the Ohio Supreme Court case captioned Academy of Medicine of Cincinnati v. Aetna Health,Inc.,
{¶ 27} With the above guidelines in mind, we begin our analysis of the arbitrability of appellees' claims. Appellees' first and second claims for relief alleged fraud in the factum and fraud. Appellees' fraud-in-the-factum claim specifically refers to the construction contract. In the claim, appellees alleged that appellants misrepresented that the contract was a "time and materials contract" based upon actual costs.
{¶ 28} Appellees, in support of their assignment of error asserting that none of their claims should be subject to arbitration, cite Roberts v. Bank of Am. NT SA
(1995),
{¶ 29} In Roberts, the appellant argued that the absence of consideration prevented the formation of a legally binding agreement and should be considered fraud in the factum and nonarbitrable. Id. at 304,
{¶ 30} Appellees' fraud claim alleges that appellants made several material misrepresentations regarding cost increases and defects in construction. Appellees contend that they detrimentally relied upon the misrepresentations.
{¶ 31} At the motion hearing, testimony was presented regarding the alleged misrepresentations relative to the code violations and the foundation; much of the testimony related to events that predated the construction contract. Accordingly, because appellees' fraud claims are not presumed to be arbitrable and they allege acts that occurred prior to the execution of the construction contract, we cannot say that the trial court erred when it failed to order arbitration on these claims.
{¶ 32} Appellees' third claim is for breach of the construction contract. The trial court found this claim to be arbitrable. Appellees' claim falls squarely within the scope of the arbitration clause. Thus, we find that the court did not err.
{¶ 33} In appellees' fourth claim for relief, they argue that pursuant to the construction contract, appellants breached the express warranty that the work would "be performed in a good and craftsman-like manner per industry standards." Under the Fazio test, this claim specifically relates to the contract and is a proper subject for arbitration.
{¶ 34} Appellees next allege, in their fifth claim for relief, that a subsequent agreement between the parties replaced the construction contract; appellees contend that appellants breached the novation. Because this agreement did not contain an arbitration clause, the court did not err in finding that the parties did not agree to arbitrate this claim. Moreover, the court heard testimony that Hussein did not intend that the agreement would replace the construction contract; rather, the agreement was meant to supplement the original contract.
{¶ 35} In appellees' sixth claim for relief, they contend that appellants were unjustly enriched by failing to perform the promised services and retaining the payments tendered. Under the Fazio test, this claim also stems directly from the performance of the construction contract and is within the scope of the broadly worded arbitration clause. *Page 136
{¶ 36} Appellees' seventh claim for relief alleged that appellants breached their duty to construct appellees' home in a workmanlike manner. This claim clearly arises from the performance of the construction contract, Fazio, and is a proper subject for arbitration.
{¶ 37} Appellees' eighth claim for relief alleges that appellants violated the CPSA. The parties dispute whether appellees' CPSA claim is subject to arbitration. The parties each rely on cases from our court to support their arguments.
{¶ 38} Appellants rely on Karamol v.Continental Estates, Inc. (Sept. 22, 2000), 6th Dist. No. WD-00-021,
{¶ 39} Conversely, in Zalecki v. TerminixInternatl., Inc. (Feb. 23, 1996), 6th Dist. No. L-95-156,
{¶ 40} In the present case, in their CSPA claim, appellees allege that "[i]n the negotiation and implementation of the construction contract, Defendants knowingly committed deceptive and/or unconscionable sales practices * * * and/or committed acts or practices declared to violate the CSPA by judicial decisions archived in the public inspection file of the Ohio Attorney General's Office prior to the events in question." Accordingly, we find that the allegations raised by appellees are more analogous to the facts in Zalecki rather thanKaramol. Thus, we find that the trial court did not err by not ordering that the claim be arbitrated.
{¶ 41} We next address the effect, if any, of the apparent defect in the arbitration clause regarding the language that requires that the parties select an arbitrator "from the Toledo Bar Association." Appellees submitted an affidavit from the director of the Toledo Bar Association stating that "[t]he Toledo Bar Association does not provide any general arbitration services." Appellees argues that because the arbitration clause, as written, is not enforceable, it may be avoided. In support, appellees cite Kauffman v. Cugini CapocciaBuilders, *Page 137 Inc. (June 28, 2001), 10th Dist. No. 00AP-871,
{¶ 42} In the present case, it is apparent that appellants mistakenly believed that the Toledo Bar Association provided arbitration services. However, appellees have not demonstrated that they relied on this portion of the arbitration clause when approving the arbitration provision. Thus, we conclude that the mistake was not material and did not render the arbitration clause voidable.
{¶ 43} In summary, we conclude that the trial court did not err when it ordered the breach-of-contract claim to be arbitrated. However, we find that the court erred by not ordering that the breach-of-express-warranty, unjust-enrichment, and negligence claims be arbitrated as they clearly, underFazio, could not be maintained without reference to the construction contract. We further find that the court did not err when it failed to order that the fraud claims and the CSPA claim be arbitrated. Finally, we conclude that the error in the arbitration clause was not material and did not affect the enforceability of the provision.
{¶ 44} Accordingly, appellants' first assignment of error is well taken, in part. Appellees and cross-appellants' sole assignment of error is not well taken.
{¶ 45} Appellants' second assignment of error disputes the trial court's refusal to stay the proceedings pending arbitration. R.C.
{¶ 46} "If any action is brought upon any issue referable to arbitration under an agreement in writing for arbitration, the court in which the action is pending, upon being satisfied that the issue involved in the action is referable to arbitration under an agreement in writing for arbitration, shall on application of one of the parties staythe trial of the action until the arbitration of the issue hasbeen had in accordance with the agreement, provided the applicant for the stay is not in default in proceeding with arbitration." (Emphasis added.)
{¶ 47} In Cheney v. Sears, Roebuck Co., 10th Dist. No. 04AP-1354,
{¶ 48} On consideration whereof, we find that appellants were prevented from having a fair proceeding. The judgment of the Wood County Court of Common Pleas is reversed in part, and the matter is remanded for further proceedings consistent with this decision. Appellees are ordered to pay the costs of this appeal pursuant to App. R. 24. Judgment for the clerk's expense incurred in preparation of the record, fees allowed by law, and the fee for filing the appeal is awarded to Wood County.
Judgment reversed in part and cause remanded.
SKOW and OSOWIK, JJ., concur.
robert-fazio-v-lehman-brothers-inc-lehman-brothers-holdings-inc-sg , 340 F.3d 386 ( 2003 )
Dana Ltd. v. Sypris Technologies, Inc. , 2015 Ohio 5311 ( 2015 )
Khaledi v. Nickris Properties, Inc. , 2018 Ohio 3087 ( 2018 )
Toledo Fedn. of Teachers v. Bd. of Edn. of the Toledo City ... , 2019 Ohio 3025 ( 2019 )
Wetli v. Bugbee & Conkle, L.L.P. , 2015 Ohio 4213 ( 2015 )
Sterling Contracting, L.L.C. v. Main Event Entertainment, L.... , 2020 Ohio 184 ( 2020 )
Murray v. David Moore Builders, Inc. , 177 Ohio App. 3d 62 ( 2008 )
Rippe & Kingston Co., PSC v. Kruse , 2014 Ohio 2428 ( 2014 )
Marquez v. Koch , 2012 Ohio 5466 ( 2012 )
Zamora v. Lehman , 111 Cal. Rptr. 3d 335 ( 2010 )
Ranazzi v. Amazon.com, Inc. , 2015 Ohio 4411 ( 2015 )
Donnell v. Parkcliffe Alzheimer's Community , 2017 Ohio 7982 ( 2017 )