{¶ 1} Appellants, Gatliff Building Company and Randy Gatliff, appeal from a decision of the Medina County Court of Common Pleas, denying their motion to stay proceedings pending arbitration. We affirm.
{¶ 3} Appellants timely appealed, raising two assignments of error for our review. For ease of analysis, we will address the two assignments of error together.
II
Assignment of Error No. 1
Assignment of Error No. 2The trial court's denial, because the arbitration clause was allegedly substantively unconscionable, of appellants' motion to stay proceedings so the matter can be arbitrated under the American Arbitration Association rules was an abuse of discretion.
The trial court's denial, because the arbitration clause was procedurally unconscionable, of appellants' motion to stay proceedings so the matter can be arbitrated under the American Arbitration Association rules was an abuse of discretion.
{¶ 4} In their two assignments of error, appellants maintain that the trial court erred in determining that the arbitration clause in the construction contract between the parties was substantively and procedurally unconscionable. We disagree.
{¶ 5} Generally, appellate courts review a trial court's disposition of a motion to stay proceedings pending arbitration under an abuse-of-discretion *Page 847
standard. Reynolds v. Lapos Constr., Inc. (May 30, 2001), 9th Dist. No. 01CA007780,
{¶ 6} Ohio's public policy encourages arbitration as a method to settle disputes. Schaefer v. Allstate Ins. Co.
(1992),
{¶ 7} Procedural unconscionability concerns the formation of the agreement and occurs when no voluntary meeting of the minds is possible. Bushman v. MFC Drilling (July 19, 1995), 9th Dist. No. 2403-M,
{¶ 8} Substantive unconscionability refers to the actual terms of the agreement. Contract terms are unconscionable if they are unfair and commercially unreasonable. Bank One, N.A. v.Borovitz, 9th Dist. No. 21042, 2002-Ohio-5544,
{¶ 9} In order to determine whether a given contract provision is unconscionable, courts must examine the particular facts and circumstances surrounding the agreement. Lightning RodMut. Ins. Co. v. Saffle (Nov. 6, *Page 848
1991), 9th Dist. No. 15134,
Procedural Unconscionability
{¶ 10} At his May 18, 2004 deposition, Randy Gatliff, the president and owner of Gatliff Building Company, testified that since the company had been formed, each of its two standard construction contracts contained the arbitration clause that is at issue in this case. Gatliff also testified that he had never modified or removed the arbitration clause at the request of a customer and that if a customer was not willing to accept the language of the company's contract, he would instruct them to search for another home builder. Finally, Gatliff testified that he had not explained the arbitration clause to appellees and that he had not called their attention to the clause.
{¶ 11} Appellees each executed an affidavit and attached those affidavits to their brief opposing appellants' motion to stay proceedings. In those affidavits, appellees stated that they were not represented by counsel when they executed the construction contract and that this was their first experience with a construction contract. Appellees further stated that no employee of Gatliff Building Company had offered them any information on arbitration or discussed the clause with them. Lastly, appellees stated that at the time they executed the agreement, they did not know what arbitration meant.
{¶ 12} Randy Gatliff's own testimony characterizes the construction contract in general and the arbitration clause in particular as adhesive. Black's Law Dictionary (7th Ed. 1999) 318-319 defines an adhesion contract as a "standard-form contract prepared by one party, to be signed by the party in a weaker position, usu[ally] a consumer, who has little choice about the terms." As Gatliff testified in his deposition, he had never modified or removed the arbitration clause contained in his company's standard contract, and he would not do business with a consumer who would not accept the language of that clause. Furthermore, it is undisputed that Gatliff neither pointed out the arbitration clause nor explained its contents to appellees, that appellees were unrepresented by counsel when they executed the contract, and that this was the first construction contract that appellees had experience with.
{¶ 13} In light of all the foregoing facts and circumstances, we conclude that the arbitration clause in the construction contract between the parties is procedurally unconscionable.
Substantive Unconscionability
{¶ 14} The arbitration clause contained in the construction contract between the parties reads as follows: *Page 849
All claims and disputes relating to this contract shall be subject to arbitration at the option of either the buyer or the contractor in accordance with the Arbitration Rules of the American Arbitration Association for the construction industry in effect at the time of the arbitration located in Medina County, Ohio. Written notice of demand for arbitration shall be filed with the other party to the contract and with the American Arbitration Association, within a reasonable time after the dispute has arisen. The buyer shall have no rights to seek or obtain arbitration until such time as the contractor has certified substantial completion in accordance with this agreement. An award in arbitration may be enforced and entered in a court of competent jurisdiction in the county in which the lot is located. Arbitration shall be mandatory for buyers and constitutes the sole method of buyer in seeking to enforce the provisions of this agreement.
{¶ 15} The clause is skewed in favor of the contractor, imposing significant restrictions upon the buyer alone. First, the clause prohibits the buyer from initiating arbitration until the contractor has certified substantial completion. By forcing the buyer to wait to seek relief, this provision of the clause threatens to thwart the buyer's efforts to mitigate damages. Additionally, the clause provides that arbitration is the only method through which the buyer is permitted to enforce the contract provisions. Among other consequences, this provision increases the financial hurdle the buyer must surmount in order to pursue a claim.
{¶ 16} The clause does not disclose either the costs of arbitration or the fact that those costs are substantially higher than the costs associated with a regular court proceeding. While it makes clear that the rules of the American Arbitration Association ("AAA") govern any arbitration proceeding initiated by either party, the clause makes no reference to the fees required by that group.
{¶ 17} Appellees attached the AAA's published rules and procedures to their brief opposing appellants' motion to stay proceedings. Those rules reveal that the fees required to pursue a claim vary with the amount of damages alleged. In their complaint against appellants, appellees alleged damages of at least $165,000.1 According to the fee schedule published by the AAA, this alleged damages amount would require appellees to pay an initial fee of $2,750 upon filing their claims and an additional case-service fee of $1,250 if their case proceeded to an initial hearing. AAA Rule 50 does provide that the administrative fees may be deferred or reduced "in the event of extreme hardship on the part of any party." The rule makes clear, however, that such a deferral or reduction is entirely within *Page 850 the discretion of the AAA. Moreover, the rule does not provide for a waiver of the fees. Lastly, the initial filing fee of $2,750 and the case-service fee of $1,250 do not reflect additional costs that will be incurred by the parties during the course of arbitration. AAA Rule 51 explains that the parties are responsible for the expenses of the arbitrator, witnesses, and AAA representatives, as well as the arbitrator's compensation.
{¶ 18} In the affidavits attached to their brief opposing appellants' motion to stay proceedings, Appellees stated that they could not afford to pay the fees required in order to arbitrate their claims. Appellants have challenged this statement by pointing out that appellees had arranged for appellants to build a $297,000 home. The fact that appellees felt able to afford the construction of a $297,000 home does not, on its own, belie their sworn statements that they are unable to expend the fees associated with arbitration.
{¶ 19} In light of all the foregoing facts and circumstances, we conclude that the arbitration clause in the construction contract between the parties is substantively unconscionable.
{¶ 20} Given our determinations that the arbitration clause in the construction contract between the parties is both substantively and procedurally unconscionable, we conclude that the trial court did not err by determining that the clause was unconscionable, and both of appellants' assignments of error are overruled.
Judgment affirmed.
SLABY, P.J., concurs.
CARR, J., dissents.
Buyer v. Long, Unpublished Decision (2-3-2006) , 2006 Ohio 472 ( 2006 )
English v. Cornwell Quality Tools, Co., Unpublished ... , 2005 Ohio 6983 ( 2005 )
Corl v. Thomas King, Unpublished Decision (6-13-2006) , 2006 Ohio 2956 ( 2006 )
Post v. Procare Automotive Serv. Solutions, 87646 (5-3-2007) , 2007 Ohio 2106 ( 2007 )
Bayes v. Merle's Metro builders/blvd. Constr., 2007-L-067 (... , 2007 Ohio 7125 ( 2007 )
Peltz v. Moyer, 06 Be 11 (9-17-2007) , 2007 Ohio 4998 ( 2007 )
AJZ's Hauling, L.L.C. v. TruNorth Warranty Program of N. Am. , 2021 Ohio 1190 ( 2021 )
Ball v. Ohio State Home Services, Inc. , 2006 Ohio 4464 ( 2006 )
Taylor Building Corp. of America v. Benfield , 2006 Ohio 4428 ( 2006 )
Fry v. FCA US L.L.C. , 2017 Ohio 7005 ( 2017 )
Jamison v. LDA Builders, Inc. , 2013 Ohio 2037 ( 2013 )
C4 Polymers, Inc. v. Huntington Natl. Bank , 2015 Ohio 3475 ( 2015 )
Cook v. Richard T. Kiko Agency, Inc. , 2023 Ohio 552 ( 2023 )