DocketNumber: 16126
Citation Numbers: 245 P. 63, 114 Okla. 156, 1926 OK 136, 1926 Okla. LEXIS 974
Judges: Riley, Nicholson, Branson, Harrison, Mason, Phelps, Lester, Hunt, Claric
Filed Date: 2/9/1926
Status: Precedential
Modified Date: 10/19/2024
This action was commenced in the district court of Garfield county by plaintiff in error. The parties will be referred to as they appeared in the court below. The plaintiff alleged that on July 8, 1922, the defendants, J. G. Robins and Pete Lambros, executed and delivered to the plaintiff their 12 promissory notes, each in the sum of $100, and to secure the same executed and delivered their chattel mortgage to the plaintiff, mortgaging certain restaurant equipment, which equipment was purchased by the defendants and the notes issued in partial consideration thereof. Plaintiff pleaded a separate cause of action on an open account in the sum of $81.38, and prayed for judgment against defendants in the total sum of $1,281.38 with interest thereon, and for attorney fees in the amount of $240, as provided for in said notes.
The defendants filed an answer consisting of a general denial and counterclaim; the counterclaim being that the defendants purchased the equipment for their restaurant on April 15, 1922, alleging that the equipment purchased was to be installed in their restaurant at Enid, Okla., and that by the terms of their contract of purchase the said equipment was to be delivered to the defendants within three weeks from the date of purchase, which delivery date was by said defendants extended to June 1, 1922; they further allege that the city of Enid is located in a wheat country and that during June, July, and August there is an influx of laborers which creates good business, that plaintiff was made aware of this condition on entering the contract, and that because plaintiff failed to deliver the goods until August 20, 1922, they were damaged in the sum of $1,000 per month during the default in delivery.
Defendants filed an amendment to their answer, admitting the execution of the notes and mortgage sued upon, and alleged that at the time of the purchase they paid on account $475, and agreed to pay $300, when said goods were delivered; that they paid the $300, and delivered the notes and mortgage when they received their first and partial shipment, and that when they inspected said shipment they learned that it did not correspond to the goods ordered, but was of an inferior quality, and that because of necessity they were compelled to use same to their damage in the sum of $500.
Plaintiff filed its demurrer to the answer and counterclaim, which demurrer was overruled and exceptions saved.
The cause was submitted to the jury, and the jury rendered a verdict in favor of defendants, J. G. Robins and Pete Lambros, in the sum of $38.03, and thereafter the court rendered judgment in accordance with said verdict, to which plaintiff excepted, filed motion for new trial, and in due form perfected appeal to this court.
It is contended for reversal of the judgment that the court committed prejudicial error in giving instruction No. 3, which is as follows:
"You are further instructed that on May 8, 1922, the plaintiff by its telegram to the defendants agreed to ship the goods, wares and merchandise sold said defendants complete in approximately five or six weeks next after that date; and it became and was the duty of said plaintiff to ship said goods, wares and merchandise within approximately five or six weeks next after May 8, 1922, and in the event they failed to so do, then they would be liable to defendants for all the detriment proximately caused by their delay in shipping said goods at the time they agreed to ship the same or which in the ordinary course of things would be likely to result therefrom, provided you further find from the evidence that they failed, neglected, or refused to ship said property complete to defendants within approximately five to six weeks after said date, and in determining the damages, if any, for anticipated profits, you should include only such profits as are capable of being determined by you from the evidence with reasonable certainty."
Section 5976, Compiled Statutes 1921, provides as follows:
"For the breach of an obligation arising from contract, the measure of damages, except where otherwise expressly provided by this chapter, is the amount which will compensate the party aggrieved for all the detriment proximately caused thereby, of which, in the ordinary course of things would be likely to result therefrom. No damages can be recovered for a breach of contract which are not clearly ascertainable in both their nature and origin."
To be more specific, it is contended that instruction No. 3 is a departure from the statute, supra, in that its guide for damages, if any, is that the same be in reasonable *Page 158 certainty, whereas the statute contemplates that no damages shall be recovered which are not clearly ascertainable in boththeir nature and origin.
Under the holdings of this court, the text of the instruction did not constitute error, for in Muskogee v. Yahola Sand Co.,
"Prospective profits, proximately resulting from the breach of a contract, are recoverable in an action for damages, where the amount thereof is not contingent and speculative, but can be measured with reasonable certainty."
So far as the wording of the instruction is concerned in being a departure from the text of section 5976, supra, we think the contemplation of the statute, as construed, is that damages to be established must be with reasonable exactness as to origin and reasonably certain as to amount. A higher degree of accuracy is required in the former than in the latter, neither must be absolute in degree of proof. See Baker Strawn v. Miller Jones Bros.,
"The words 'clearly' and 'ascertainable', used in section 5976, Compiled Oklahoma Statutes 1921, taken together, mean without obscurity, obstruction, confusion, or uncertainty, and the damage claimed must be made reasonably certain. * * *"
In Lawton Refining Co. v. Hollister,
"Profits or gains prevented may be recovered in an action for breach of warranty where they can be rendered reasonably certain by evidence, and have naturally resulted from the breach."
See, also, First State Bank of Mannsville v. Howell,
The second and last contention of plaintiff's counsel is that the trial court erred in overruling the motion for a new trial, for the reason assigned that no sufficient evidence was had to support the judgment of damage in favor of defendants.
The undisputed evidence is that the goods received did not correspond to those ordered, and the testimony in this element of damages duly supports the prayer for a recovery of $500.
Much testimony was introduced showing a loss of anticipated profits, and after an examination of the record we cannot say that the verdict is not sustained by the testimony.
As held in Ft. Smith Western Ry. Co. v. Williams,
The judgment is affirmed.
NICHOLSON, C. J., BRANSON, V. C. J., and HARRISON, MASON, PHELPS, LESTER, HUNT, and CLARK, JJ., concur.
Baker & Strawn v. Miller & Jones Bros. , 109 Okla. 184 ( 1925 )
First State Bank of Mannsville v. Howell , 41 Okla. 216 ( 1913 )
Callahan Co. v. Chickasha Etc. Co. , 17 Okla. 544 ( 1906 )
Ft. Smith W. R. Co. v. Williams , 30 Okla. 726 ( 1912 )
Wellington v. Spencer , 37 Okla. 461 ( 1913 )