Citation Numbers: 237 P. 363, 115 Or. 250
Judges: BURNETT, J.
Filed Date: 3/24/1925
Status: Precedential
Modified Date: 1/13/2023
This is a suit to foreclose an alleged mechanic's lien, the foundation notice of which as filed in the office of the county clerk, reads as follows, so far as material to the questions involved:
"Know all men by these presents, that the undersigned, V.W. McCormack, hereinafter called `The claimant,' hereby claims a mechanic's lien upon that certain building or improvement known as a residence and the land upon which the same is located, in the County of Multnomah, State of Oregon, and described as follows: Lot 9, Block 76, Laurelhurst.
"The lien hereby claimed is for materials furnished and delivered at said premises to be used and which were used in the construction, alteration and repair of said building, and for labor performed upon said building at the instance and request of Portland Construction Company.
"At the time of commencing to furnish said materials and to perform said labor Dr. A. Bertschinger was the owner or reputed owner of said building, and Dr. A. Bertschinger is now the owner thereof. That *Page 265 Dr. A. Bertschinger is the owner of said land and had knowledge of the construction, alteration and repair of said building, and caused the same to be done.
"In the construction, alteration and repair of said building, Portland Construction Company was the contractor and agent of said Dr. A. Bertschinger.
"Said materials were furnished and said labor was performed between the dates of July 2nd, 1921, and July 17th, 1921, and the contract and reasonable price thereof was and is the sum of five hundred eighty-six and 40-100 dollars, lawful money of the United States, and the sum of five hundred eighty-six and 40-100 dollars is now due or to become due to the claimant and the following is a true and correct statement of said account and demand after deducting all just credits and off-sets:
"Mr. A. Bertschinger, "In account with "V.W. McCormack.
"To labor and material, being concrete work on residence located on Lot 9, Block 76, Laurelhurst ............................ $586.40
"It is the intention of the claimant to hold a lien upon the building hereinbefore described, for the amount of said claim, and not only upon said building, erections and superstructures, but also upon the land upon which the same are constructed, together with a convenient space about the same or so much as may be required for the convenient use and occupation thereof, to be determined by the judgment of the court at the time of the foreclosure of this lien."
The complaint avers, among other things:
"That heretofore and on and between the 2nd and 17th days of July, 1921, the above-named plaintiff performed work and labor in the construction, alteration and repair of a certain building, sidewalk, outhouses and driveway used in connection therewith and furnished material to be used therein, which said labor was performed upon, and which said material was used in the construction of the same. *Page 266
"That said building is a residence and is located upon Lot 9 of Block 76 in Laurelhurst Addition to the City of Portland.
"That said labor so performed and said material so furnished were both at the special instance and request of the Portland Construction Company, as independent contractor and the agent of the above-named defendant."
The answer:
"Admits that plaintiff attempted to perform certain construction work in connection with the residence located on Lot 9, Block 76, Laurelhurst. Admits that plaintiff filed a purported notice of lien with the County Clerk of Multnomah County, Oregon. Admits that plaintiff mailed to defendant a notice stating that he intended to commence suit."
Otherwise the whole complaint is traversed. The new matter in the answer has to do with alleged defects in the work said to have been done on the premises, all of which is put in issue by the reply. In the final decree the Circuit Court reduced the plaintiff's claim and ordered foreclosure for the remainder. The defendant has appealed.
Although the plaintiff has demanded a personal judgment against the defendant, yet as said by Mr. Justice RAND in Duby v.Hicks,
"A lien upon real or personal property, other than that of a judgment or decree, whether created by mortgage or otherwise, shall be foreclosed, and the property adjudged to be sold to satisfy the debt secured thereby by a suit. In such suit, in addition to the decree of foreclosure and sale, if it appear that a promissory note or other personal obligation for *Page 267 the payment of the debt has been given by the mortgagor or other lien debtor, or by any other person as principal or otherwise, the court shall also decree a recovery of the amount of such debt against such person or persons as the case may be, as in the case of an ordinary decree for the recovery of money."
It is not stated in the complaint or indicated in the testimony that any promissory note or other personal obligation had been given by anyone as a lien debtor. Hence the sole relief, if any, that can be awarded to the plaintiff is the foreclosure of his lien without any personal judgment.
It will be noted that by his notice above quoted plaintiff "claims a mechanic's lien upon that certain building or improvement known as a residence." He does not include any other structure or appurtenance. By his evidence he undertakes to prove under this notice, labor, not only performed on and material furnished for the residence, but also for adjacent walks, on a separate building called a garage, on a driveway leading to the garage, and on a retaining wall built along the boundary line between the lot mentioned and adjoining real property. It is suggested that if the plaintiff had agreed with the defendant to build on the premises in question a residence without saying more, the defendant could not be heard to resist payment for the residence, and say to the plaintiff:
"It is true you built a residence, but you did not construct a garage or driveway leading thereto, or lay any walks about the house or build a retaining wall on the line between me and my neighbor."
On the other hand, having declared for labor and material employed in constructing a certain building called a residence, the claimant cannot in his evidence include other structures any more than he could *Page 268 prove the sale of a cord of wood or a barrel of flour under a complaint to recover the sale price of a horse. By the statute, Or. L., Section 10191, for labor and materials furnished to erect a building, the claimant "shall have a lien upon the same" building and not upon another. Neither can another building be the basis of a lien upon the one named in the notice. So in this instance it is apparent that the only property involved here is "that certain building known as a residence," and that the plaintiff cannot include in his claim as stated other buildings or works.
In LaCrosse etc. R.R. Co. v. Vanderpool,
"`Building' as a noun, has a common well understood meaning, exclusive of structures of this character (a railroad bridge) and including only those which have a capacity to contain and are designed for the habitation of man or animals, or the sheltering of property."
See, also, Wheeler v. Pierce, 167 Pa. St. 416 (31 A. 649, 46 Am. St. Rep. 689).
Section 10191, Or. L., reads thus in part:
"Every mechanic, artisan, machinist, builder, contractor, lumber merchant, laborer, teamster, drayman and other persons performing labor upon or furnishing material, or transporting or hauling any material of any kind to be used in the construction, alteration or repair, either in whole or in any part of any building, * * fence, sidewalk, * * or any structure or superstructure, * * shall have a lien upon the same for the work or labor done or transportation of material furnished at the instance of the owner of the building or other improvement or his *Page 269 agent; and every contractor, sub-contractor, architect, builder or other person having charge of the construction, alteration or repair, in whole or in part, of any building or other improvement as aforesaid, shall be held to be the agent of the owner for the purpose of this act."
In declaring that the person named "shall have a lien upon the same" the statute did not mean to say that a person should have a lien upon a building so described in the notice, not only for material that went into that building but also for material used in the construction of adjacent buildings or other structures.
Unquestionably since Willamette Mills Co. v. Shea,
In Beach v. Stamper,
"The original contractor, King, was not in a position to claim a single lien upon the whole for any default that might have been made by the builder in the payments stipulated for. This would seem to follow from the principle announced that the contract must form a basis for a lien on the whole, but it is supported by authority as well. (Citing precedents.) But the exact question here involved — whether Stamper is entitled to the lien claimed by him — has been decided in Knauft v. Miller,
Otherwise discussing the matter, Mr. Justice WOLVERTON said:
"The contract is therefore the controlling feature that unites the several structures and enables the court to say that they are but one building within the spirit and reasonable intendment of the statute." *Page 271
Also in commenting upon the reason of the decision inWillamette Mills Co. v. Shea,
"The controlling feature which induced the decision was that the contract for construction was single, embracing all the buildings for a lump and inseparable sum or price, thus treating the property as a whole and inseverable."
In other words, the claimant not only is confined by his notice to one building and to the labor and material furnished for that building, but also he cannot have a lien on more than one building unless he shows an entire contract covering all the structures as a single unit. Such a contract is indispensable to the support of a lien on more than one building.
Moreover, the notice of lien must be complete within itself and cannot be aided by averment: Morrison v. Willard,
True, it is said in Section 10192, Or. L., —
"The land upon which any building or other improvement as aforesaid shall be constructed, together with a convenient space about the same, or so much as may be required for the convenient use and occupation thereof. * * shall also be subject to the liens created by this act,"
but where the lien claim is laid upon a certain building as in this instance, this statute only gives a lien on adjacent land for materials which went into *Page 272
the building mentioned. The law does not give a lien upon such a building for material and labor which went into other structures, although they were located within the curtilage of the dwelling. In the testimony, claim is made for labor and materials furnished, not only in the basement of the residence and steps adjacent thereto, but also for the retaining wall mentioned, the floor of the garage, sundry walks on the lot, and a driveway from the street to the garage. Our statute does not as in West Virginia — O'Neil v. Taylor,
The evidence does not disclose the terms of the agreement with the original contractor. Although it is said to have been in writing, the writing is not produced, but without dispute, even as stated by the plaintiff, the retaining wall mentioned in the evidence was not included in the original contract. It was by virtue of a separate agreement, as the plaintiff states, direct with the owner. It will not do to say that this was a modification of the former contract, for as already shown, the original contractor was one of the parties to that agreement and only for the purpose of supporting a lien was he by that contract made the agent of the defendant. He could not bind the defendant in any way beyond the terms of the original contract. Neither can the defendant nor the plaintiff change that contract without the consent of the contractor, he being a party personally bound by it; so that we have at best two contracts for separate pieces of work on the premises. There was no entire contract covering all these separate improvements, that being the essential laid down in Willamette Mills Co. v. Shea and Beach v. Stamper,supra.
The lien notice must be complete within itself and cannot be expanded beyond the building therein described so as to include other structures, although erected upon the same lot. Applicable to this feature it is said in Missouri Valley Cut Stone Wks. v.Brown,
"A retaining wall though it serves the purpose of a fence, and a driveway extending from the street up to the side of the residence are not such improvements that a mechanic's lien can be maintained for the material used in the construction thereof when contracted for separately from the building." *Page 274
In McDermott v. Palmer, 2 E.D. Smith (N.Y.), 675, it was said:
"The provisions of the Act passed April 20, 1830, authorizing a lien in favor of mechanics for work performed towards the erection, construction or finishing of buildings do not apply to the flagging of sidewalks, yards and areas of buildings in the process of erection."
By way of dictum it was said that perhaps under a later statute sanctioning a lien on buildings and appurtenances, a lien might have been established on adjoining structures, but under a statute like ours the rule was laid down as stated.
In Truesdell v. Gay, 13 Gray (Mass.), 311, it is said:
"A wall built around three sides of the stack of an iron furnace at the distance of a few feet from it in order to protect it from the possible sliding down of the earth from a hill at the foot of which it stands, is not a building within the meaning of St. 1851, C. 343, and including labor performed upon the wall, in a statement filed in the town clerk's office under that statute will defeat any lien for work done upon the furnaces."
In Title Guarantee Co. v. Wrenn,
In Harrisburg Lumber Co. v. Washburn,
"Had the claim contained a lumping charge of the amount demanded and there were no means of ascertaining from the notice itself the quantity and value of the lumber used in building the sidewalk the lien would be defeated."
It was also said in Kezartee v. Marks Co.,
"The liens under this statute are specific; that is, they extend to the particular structure, building, or erection in or upon which the particular materials were used, or the particular labor was performed. In this case Mr. Beardsley had a lien upon the fence for the materials furnished and used in its construction, and he had another lien upon the house for the materials used in its repairs and construction; but he had no lien upon the fence for materials used in the house, nor upon the house for materials used in the fence."
The court there excluded the claim of Beardsley. In theWillamette Mills Co. v. Shea case the court distinguished the case of Kezartee v. Marks Co., owing to the fact that in the Willamette Mills case there was a specific contract including all the buildings as one unit, but that feature is utterly wanting in the instant case. The result is that the lien here *Page 276 cannot be sustained for the reason that there is no omnibus contract grouping together several improvements. The forbidden scheme is to include in a lump charge against a specified building not only labor and materials entering into the construction of that building, but also labor and materials used in separate structures one at least of which was not included in the original contract under which the plaintiff claims.
Another reason is that the claim is made only upon the building, which does not include other than that, although erected on the same lot and under such a notice there could be no recovery except for what went into the building described.
There is yet another reason why this claim cannot be allowed. Section 10195, Or. L., says:
"It shall be the duty of every original contractor, within sixty days after the completion of his contract, and of every mechanic, * * or other person, save the original contractor, claiming the benefit of this act, within thirty days after the completion of the alteration or repair thereof, * * to file with the county clerk of the county in which such building or other improvement, or some part thereof, shall be situated, a claim containing a true statement of his demand, after deducting all just credits and offsets, with the name of the owner, or reputed owner, if known, and also the name of the person by whom he was employed or to whom he furnished the materials, * *."
In Rankin v. Malarkey,
"This notice of lien does not comply with the requirements of the statute, because it fails to state the name of the person to whom the materials were furnished. * * While no particular form is necessary, *Page 277 the notice on its face should show that the claimant, at the instance of the owner or his agent, had furnished certain materials to be used in the construction of a building upon which he claimed a lien, and for this purpose the statute has required the claimant to name in his notice the person to whom the materials were furnished. The plaintiff having failed to do this, or to connect the owner of the premises with the materials furnished his lien never attached to the land or building."
The same doctrine is reiterated on rehearing by Mr. Justice BEAN. Practically the same form of claim was in question inGetty v. Ames,
"This claim or notice of lien is clearly insufficient, because it does not state, either directly or by necessary inference, the name of the person to whom the claimants furnished material, or for whom they performed the labor for which they seek to enforce the lien, or, indeed, that they furnished any material or performed any labor whatever on the building of the defendants. Upon these questions the notice is entirely silent, and is, therefore, insufficient under the mechanic's lien law of this state."
The same doctrine is advanced in Dillon v. Hart,
As to the materials the notice says it is for materials furnished and for labor performed on said building, but to whom the materials were delivered is not stated. Again, the statement of claim is
"To labor and material being concrete work on residence located on Lot 9, Block 76 Laurelhurst."
On the other hand, the reply shows:
"That the material used in the construction of the driveway upon said premises was ordered by *Page 278 Fancher-McLean Co., and the successor to said Fancher-McLean Co., namely, the Portland Construction Co., and the same was of very poor quality, and by reason thereof the surface on the driveway became loose from the base thereof."
The original reply had it that this material used in the construction of the driveway was furnished by the Fancher-McLean Co. The proof expressly sustains the theory that it was furnished by that company. The statement, however, in the lien notice does not show what part of the material was furnished by the plaintiff, if any, and what by the contractor. Consequently, we have a clear case of a lumping charge of items that were not lienable under the claim as stated by the plaintiff in the notice which he filed. The retaining wall was not lienable under a claim against the building, for the reason that it was not included under the contract under which this plaintiff claims.
It is well settled, in the language employed by Mr. Justice EAKIN in Crane Company v. Erie Heating Co.,
"All authority to bind the owner on account of the building or buildings to be constructed must emanate from the original contract, which becomes the foundation law for the government of all subcontracts, as they must be let under it and by virtue of the contractor's authority obtained through it."
While the statute makes the original contractor the agent for the owner of the realty upon which the structure contracted for is to be erected, yet the scope of that agent's authority is measured and restricted by the terms of his contract. We are taught that where a notice of lien contains a lumping charge for labor or material, a part of which is lienable and part nonlienable, and the notice contains no itemized statement or other means by which it can *Page 279
be ascertained from the notice itself, and without the resort to oral testimony, what amount of the charge is lienable, the right to a lien for the total amount or any part thereof is lost:Kezartee v. Marks,
The deduction is, that no item is lienable on behalf of a subcontractor as such unless the same is included in the agreement had by the owner with the original contractor. If a subcontractor would urge a lien upon more than one structure he must be able to refer to an original contract covering as one undertaking all the structures involved. He cannot place his claim on a single building and prove under that claim labor and materials furnished in the construction of another edifice. In other words, the original contract, the claim of lien, and the proof must correspond in scope and meaning or the lien will not attach. The original contractor has no authority as a statutory agent to bind the property in favor of a subcontractor for anything not included in the original contract. No subordinate claim can rise above that source and sanction of its origin. It may well be that one who happens to be a subcontractor may make an independent agreement with the owner of the realty to perform labor upon structures situated upon that realty or even to make new structures thereon and for such services could file a lien as an original contractor by virtue of his independent agreement, but he must assert his claim in that capacity. He cannot put into his claim of lien as a subcontractor anything outside of the original contract under which he is such subcontractor. Independent items are not lienable in favor of a subcontractor *Page 280 claiming as such under the contract of his immediate superior.
The terms of the original contract in the instant case do not appear in evidence. It is indicated that it was in writing, but the document was not produced and we are utterly uninformed as to its terms. As said before, while it is competent by a single contract to include several buildings and other structures situated upon the same ground, yet the claim of lien must be so framed as to correspond with such a contract. The claim in this instance is for
"Labor and material, being concrete work on residence located on Lot 9, Block 76, Laurelhurst ............................ $886.40"
It is also declared by that notice to be the intention of the claimant "to hold a lien upon the building hereinbefore described," also upon the land together with the convenient space about the same, etc. Under such notice, confined as it is to a single structure, the claimant cannot import into his charge at the trial items for other buildings, although they might be within the curtilage of the residence, and that for the simple reasons that they are not included in his notice and that the notice does not refer to an omnibus contract covering all the structures. This is plainly a lumping charge not at all itemized so that it cannot, in the language of another, "be ascertained from the notice itself, and without resorting to oral testimony what amount of the charge is lienable" and what is not lienable.
The testimony discloses that at least part of the work for which the plaintiff claims was not at all within the contemplation of the original contract, yet the plaintiff is here claiming the right to tack it on to the lien which he claims upon the dwelling, *Page 281 as a subcontractor. In short, his testimony shows that under the guise of claiming a lien upon the single structure described as a residence he is seeking to include items which are not at all within the meaning of the word "residence," such as driveways, walks and a garage, covering them with a lumping charge, but also an item for a retaining wall which he himself says was not in anywise included in the terms of the original contract under which he is claiming as a subcontractor.
Under the uniform holdings hitherto of this court such a claim is void and constitutes no lien upon the premises. The decision of the Circuit Court should be reversed and the suit dismissed. I dissent from the conclusion of Mr. Justice RAND.
Chief Justice McBRIDE concurs in this dissent.