DocketNumber: 77-6-414; CA A30091
Citation Numbers: 70 Or. App. 358, 689 P.2d 1052
Judges: Newman, Richardson
Filed Date: 10/24/1984
Status: Precedential
Modified Date: 10/18/2024
This case is before us for the third time. In B & D Investment v. Petticord, 48 Or App 345, 617 P2d 276, rev den 290 Or 302 (1980), and B & D Investment Corp. v. Petticord, 61 Or App 585, 659 P2d 400, rev den 294 Or 792 (1983),
We instructed the trial court on our second remand to make findings that would determine whether plaintiff’s damages were properly measured in accordance with the formula the court applied at the second trial or should be measured in accordance with the formula of Restatement of Contracts, § 357(1) (1932), that we held in Welch v. Webb, 47 Or App 771, 615 P2d 391 (1980), is applicable in some situations when a plaintiff seeking quantum meruit damages has breached the parties’ contract. The trial court then made findings from which it necessarily followed that the latter formula is applicable here. However, the court awarded exactly the same amount of quantum meruit damages it had at the previous trial, where it used the different formula. The trial judge stated in his findings:
“The net benefit to defendants Petticord by reason of plaintiffs work and material is in the sum of $40,373.22, representing the reasonable value of the work and materials furnished but not including $21,677.84 additional cost incurred directly as a result of plaintiffs breach in changing plans without authorization. Defendant Petticord has paid plaintiff $19,936.96.”
In effect, the trial court computed damages — as it did
Pioneer and the Bank appeal from the trial court’s denial of attorney fees that they contend they are entitled to recover as the prevailing parties in plaintiffs underlying lien foreclosure action. Our remand in our second opinion in this case required the trial court to conduct further proceedings on Pioneer’s and the Bank’s claim for attorney fees. See 61 Or App at 593-94. We conclude from the record on remand that the trial court denied their claim because it found in accordance with plaintiffs objection that Pioneer and the Bank were
Plaintiffs cross-appeal from the denial of its claim for attorney fees is rendered premature by our disposition of defendants’ appeal, because it remains uncertain whether plaintiff is the prevailing party. We nevertheless choose to address the merits of the cross-appeal, in the hope of aborting some further use of the trial court’s resources and a further appeal in this already extravagantly litigated case. Plaintiff argues that, although it did not prevail on its lien foreclosure claim and is therefore not entitled to statutory attorney fees, the contract between plaintiff and defendants provides for attorney fees and plaintiffs complaint was predicated in part
“* * * on the theory that it was entitled to recover against Petticords in quantum meruit because Petticords wrongfully terminated the contract. A quantum meruit claim in such circumstances is treated as ‘arising out of the contract’ for purposes of an attorney fee award. * * *”
Plaintiff relies on American Petrofina v. D & L Oil Supply, 283 Or 183, 583 P2d 521 (1978). The court held there that, where a plaintiff seeks recovery on alternative contract and quasi-contract theories and the defendant “prevails” on the contract theory but the plaintiff is awarded quantum meruit damages, the defendant is not entitled to attorney fees under a contractual provision for their recovery by the prevailing party in litigation arising out of the contract. Assuming that plaintiff is correct in its extrapolation that the plaintiff in American Petrofina would have been entitled to attorney fees, plaintiff is not aided. This is not an action on a contract that provides for attorney fees; it is an action that was brought to foreclose a lien, and any right to quantum meruit damages plaintiff might ultimately enjoy is ancillary to the denial of foreclosure and does not arise from the contract. Quantum meruit damages awarded after the disallowance of a lien do not give rise to an award of statutory attorney fees under former ORS 87.060(4). Betz Construction v. Peterson, 47 Or App 333, 614 P2d 1184, rev den 289 Or 677 (1980). Plaintiff cannot avoid that consequence by recharacterizing this proceeding as a contract action.
Reversed and remanded for further proceedings not inconsistent with this opinion on the issue of plaintiffs damages; otherwise affirmed.
The facts are set forth in our earlier opinions, and restating them would serve no purpose.
Unless otherwise specified, the term “defendants” in this opinion refers to the Petticords.
The trial court found:
“The evidence fails to prove that the additional cost of completing the house over and above the contract price was caused by the plaintiffs breach. That is mere speculation.”
We cannot tell from that finding whether the trial judge considered that defendants’ evidence was insufficient to prove completion costs, or whether the court did not find in accordance with defendants’ evidence or whether, for some unspecified reason, the court regarded the proven costs to be legally unavailable as an offset. The finding should be clarified on remand. We do not agree that the evidence was insufficient, if that was the intended meaning of the finding.
We said in B & D Investment v. Petticord, supra, 48 Or App at 347, that plaintiff completed approximately 25 percent of its required performance under the contract. The contract price was $132,900. Under the “ratable proportion of the agreed compensation” limitation of section 357(1), plaintiffs recovery may not exceed 25 percent of the contract price, less amounts defendants have already paid. See comment g to section 357. We do not suggest that that ceiling on plaintiffs damages will become relevant in the calculation of the award, given the other evidence in the record.