DocketNumber: 87-1724-J-2, 87-1766-J-2, 86-1146-J-2, 86-1567-J-2, 86-2621-J-2, 87-1986-J-2; CA A73802
Citation Numbers: 120 Or. App. 203, 852 P.2d 844, 1993 Ore. App. LEXIS 699
Judges: Landau, Muniz, Rossman
Filed Date: 5/12/1993
Status: Precedential
Modified Date: 11/13/2024
Third-party plaintiffs Underwriters of Interest (Underwriters) appeal from a summary judgment in favor of third-party defendant Deltak Corporation (Deltak). We reverse and remand.
This case arises out of the same transaction that is described in Biomass One, L.P. v. S-P Construction (A68622), 120 Or App 194, 852 P2d 847 (1993). The relevant facts are set out in that opinion and are not repeated here. At issue in this case is the interpretation of an agreement between S-P Construction (S-P) and another subcontractor, Deltak, which required Deltak to provide boilers to S-P for the cogeneration power plant that S-P had agreed to construct for Biomass One, Ltd. Two provisions of that agreement are relevant. First, under the heading of “Warranty,” the agreement provides:
“Performance data on the performance sheet are predicted under the operating conditions given on the same sheet. Performance is guaranteed and so stated on the performance or guarantee page of this proposal and if the heating surface is undamaged and kept clean by the purchaser.”
Second, the “performance sheet,” entitled “Fired Boiler Data,” contains various specifications regarding the boilers Deltak was to provide, including:
“Steam generated (lb/hr) 175,00o[1 ]
“Fuel Wood
“Moisture 40”
The trial court concluded that, as a matter of law, those provisions require proof that the boilers actually were fired with fuel meeting the specifications on the performance sheet as a condition precedent to enforcement of the guarantee. When Underwriters, as subrogees of S-P, conceded that they could not establish precisely what type of fuel actually was used, Deltak moved for summary judgment, which the trial court granted. Underwriters argue that the trial court
Deltak argues that the agreement unambiguously provides that enforcement of the guarantee is contingent on proof that the boilers were fired with wood fuel with a moisture content of 40 percent. It emphasizes the existence of the fuel specifications in the performance sheet and the provision in the guarantee that performance as promised is “predicted under the operating conditions given on the same sheet.”
Underwriters argue that the agreement merely describes the capacity of the boilers, and that they are not required to establish that any particular fuel was burned to demonstrate that Deltak failed to supply boilers with the guaranteed capacity. They emphasize that the guarantee clause mentions nothing about fuel specifications as a condition to its enforcement; therefore, they should be allowed to prove through the testimony of experts that Deltak supplied boilers that failed to conform to the guarantee.
If anything, the language in this agreement is even less clear than the language at issue in Biomass One, L.P. v. S-P Construction (A68622), supra. Deltak’s argument that the agreement conditions enforcement of the guarantee on proof of actual fuel use may be a reasonable interpretation, but it is not the only reasonable one that may be drawn from the language alone. The language could have been intended to
Because we hold that the trial court erred in granting summary judgment for Deltak, we need not address Underwriters’ other assignments of error.
Reversed and remanded.
The Fired Boiler Data sheet originally specified a figure of 150,000. It later was changed to 175,000.
The agreement provides that California law governs its interpretation. However, because there is no apparent conflict between the relevant principles of California and Oregon law, we are free to apply the latter. Deerfield Commodities v. Nerco, Inc., 72 Or App 305, 316, 696 P2d 1096, rev den 299 Or 314 (1985).