DocketNumber: No. 219
Judges: McCollum, Mitchell, Paxson, Sterrett, Williams
Filed Date: 5/26/1890
Status: Precedential
Modified Date: 10/19/2024
The contract between Peters and the city of Philadelphia contained no stipulation as to the time within which the paving was to be completed, the space left for that purpose in the printed form of the contract not having been filled in. But when the contract was made the ordinance of May 11, 1872, was in force, which provided that all contracts for paving should contain a condition that the work should be completed in two years from their date, and in default thereof the contract should be void: Ord. 1872, p. 199. This ordinance was part of the city law, and in his agreement the contractor expressly stipulated to execute and finish his work in accordance with all the ordinances of the city relating to paving. The stipulation to finish the work within two years from the date, must therefore be considered as written into the contract. The work was not finished in two years, and therefore the contract became void in July, 1875. It appears by the case stated that part of Penn street was paved in 1873, and nothing further was then done under the contract until 1879. The city, of course, might have treated the contract as void, and refused it further recognition; but, on December 3, 1878, an ordinance was passed entitled “ An ordinance to repeal an ordinance in relation to contracts for street paving,” which repealed an ordinance of December 31, 1862, and then proceeded: “And all contracts for paving streets entered into by the department of highways, under which work has been done under resolution or ordinance authorizing the same, be and are hereby ratified and approved:” Ord. 1878, p. 213. The ordinance of 1862, thus repealed, provided only for the publication of notice, by the applicants for contracts to pave, of the time and place where property owners might appear and object, and had no relation to the time of completion of the work: Ord. 1862, p. 487. If the question were distinctly raised here, and were new, we might find some difficulty in holding this ordinance of December 3,1878, applicable to contracts made void by the ordinance of 1872, which has reference to an entirely different subject-
In the interval, however, from 1875 to 1878, while the contract was void, or at least dormant, the ordinance of April 24, 1877; Ord, 1877, p. 59, was passed, fixing the price of rubble pavement for all new paving after the passage of the ordinance at $1.10 per square yard. The price in Peters’ contract of 1873 was $1.50 per square yard.
It is beyond question that, in reviving and ratifying the contract, the city might have made an express condition that the work thereafter to be done under it should be done at the reduced price. Appellant’s counsel has argued strenuously against the power of the city to change the terms of contracts once made, and also against the power of courts to introduce new terms by construction. All this is fully conceded, but the argument overlooks the fact that the appellant’s contract had become void by his own default, and if it was revived as an act of grace by the city he must accept the revival upon such terms as the city imposed. The city, however, made no express conditions, and we have therefore to consider the effect of the omission to do so, and also the effect of the ordinance of 1877 upon the rights of the appellees.
Actions by a municipal corporation to the use of a contractor who has done the work, against the owner of property charged with the payment for it, are a species of tripartite contests, unknown to the common law, and presenting some difficulties in procedure under its forms. The general rule, even in Pennsylvania where equity is part of the common law, undoubtedly is that the rights of the legal plaintiff only can be regarded and must prevail, but the rule has as many exceptions as the principles of equity require for their enforcement. The authority of municipal corporations to impose the cost of paving upon
Nor is it reasonable to suppose that the councils intended to sanction any higher charge. The appellant’s contract was not revived by name or specifically in any way. It got its new life by coming within the general terms of the ordinance of December, 1878. When that ordinance was passed, councils knew that the legal charge had been fixed by the ordinance of April, 1877, and may well have supposed that all subsequent work done under revived contracts, as well as under new ones, would be done under the terms of that ordinance. Their right to have -made an express provision to that effect is beyond question, and it is a reasonable construction to imply that condition in the ordinance as actually passed.
The judgment of the court below, having been entered for an amount based on the price under the ordinance of 1877, was correct.
Judgment affirmed.
On June 4, 1890, a motion for a re-argument was refused..
It should be stated, to prevent confusion, that the opinion in this case, printed in 26 W. N. 150 and in 19 Atl. R. 947, was subsequently modified as printed in this report.