The learned judge below found the facts clearly and discussed and applied the law correctly, but owing to the wide range of the argument before him, at greater length and in more detail than is now necessary, as the essential facts are few and not really in dispute.
These are the material facts and they are not really in dispute. Subordinate issues were raised as to the construction by the railroad under requirement of an Act of April 26,1855, P. L. 302, of a guard wall to protect teams from running over the embankment: the effect of several indictments by the quarter sessions of Monroe county (formed in 1836, from Northampton and Pike), for failure to keep the road in repair; the agreement in 1868, between the railroad company and the supervisors of the township as to the repair and acceptance of the new road in place of the old, etc. None of these, however, are material to the present controversy. The act of 1855, was a requirement of a safety guard on the precipitous side of the road and had no bearing on the question of width; the indictments were all upon the condition and want of repair, and the agreement of the supervisors in 1868, had reference only to the same thing, that the new road was satisfactory as to condition and accepted as replacing the old in that respect. It did not profess to go any further, or to alter the rights of the township or the commonwealth as to the title or legal limits of the highway, and it could not have done so had it attempted to. The supervisors are subordinate agents and have no authority to give away the rights of the commonwealth: Furniss v. Furniss, 29 Pa. 15; Snow v. Deerfield Township, 78 Pa. 181.
The substantial question is upon the title of the common
On this state of facts the appellant bases its contention that the relocated or present road exists only by proscription and therefore occupies only the ground covered by the opened and traveled way. In substance this is the appellant’s whole case. Its buildings, except the chute, are outside of the traveled way but within the thirty-three and a half feet claimed by the commonwealth.
The argument rests on a fundamental misconception of the law and the burden of proof. The original road of 1803, was laid out by formal proceedings in the quarter sessions, with a legal width of thirty-three and a half feet. It was actually opened presumably only to the ordinary width, but it retained its capacity to be opened to its full legal width at any time in the future when- the public convenience should require it. This was its status, legal and actual, when the appellant took possession. It is conceded that the only authority for such taking was sec. 13 of the Act of February. 19, 1849, P. L. 79, which enacts that “ If any such railroad company, shall find it necessary to change the site of any portion of any turnpike or public road, they shall cause the same to be reconstructed forthwith at their own expense, upon the most favorable location, and in as perfect a manner as the original road.” What the railroad company does under this authority is not to give the commonwealth a new road with a new title and new attributes, but the old road reconstructed. The site is necessarily changed but in all other respects it is to be “ the same,” to wit: expressly upon the most favorable location and in as perfect a
If when it took the former location of the highway and relocated the latter in 1855, the railroad only substituted a way of the traveled width, then when a half century or more later the public needs should require a wider highway the township would be compelled to resort to new proceedings and pay for additional land. That would not be reconstructing “ the same ” as the statute requires. The suggestion answers itself. In contemplation of law the present road is the road that was opened by legal proceedings in 1803. Its course has been deflected at this point but its entity remains the same, with all its attributes unchanged in point of law. If in the course of years the change had gradually come about to avoid obstacles, improve grade, or other reason of such kind, the legal as well as the actual road would in time be that which the public used, though it was not in the place where the viewers originally located it, and though the supervisors never had at any time the authority to relocate it: Furniss v. Furniss, 29 Pa. 15; Com. v. Marshall, 137 Pa. 170.
Part of appellant’s argument that the present road exists only by prescription, is based on the absence of any evidence as to how the ground for it was acquired by the railroad company. But the burden of proof was on the appellant. Even in ordinary cases where a railroad takes land for a right of way the presumption is that it takes the full width of sixty feet authorized by statute: Jones v. Erie, etc., R. R. Co., 144 Pa. 629. And such presumption is not rebuttable where as in the present case the width of land, however acquired for the purpose, was not dependent on the judgment of the corporation but had to be adequate to the discharge of its statutory obligation to replace the public highway. It is not for the corporation to defend on the ground that it did not do its dutjn
The buildings were within the legal limits of the highway, the chute extending across it though above the surface was of course an obstruction, and the court found that the quarry was so operated as to be dangerous to public travel and a nuisance. The injunction was therefore properly issued.
Decree affirmed with costs.