DocketNumber: Appeal, No. 150
Citation Numbers: 272 Pa. 31, 115 A. 868, 1922 Pa. LEXIS 770
Judges: Moschzisker, Sadler, Schaefer, Simpson, Walling
Filed Date: 1/3/1922
Status: Precedential
Modified Date: 11/13/2024
Opinion by
Plaintiff agreed to build an addition to defendant’s house, the contract requiring that the work should be done under the direction and subject to the approval of defendant’s architects, that “all payments [therefor] shall be due when certificates for the same are issued” by the architects, and “that no certificate given or payment made under this contract, except the final certificate or final payment, shall be conclusive evidence of the performance of this contract, either wholly or in part, and that no payment shall be construed to be an acceptance of defective work or improper materials.”
When plaintiff had completed the work, as he alleged it was to be done, he filed a mechanic’s claim and then applied for and received from the architects a final
It is not necessary to consider the assignments of error in detail, since we are all of opinion the court below should have given binding instructions for plaintiff. There was no evidence offered or produced in any way affecting the certificate of the architects, which, on the contrary, defendant admitted was honestly given, and not as the result of fraud, collusion or caprice, and hence barred the defense he endeavored to make: Monongahela Navigation Co. v. Fenlon, 4 W. & S. 205; Hostetter v. City of Pittsburgh, 107 Pa. 419; Bowman Bros. v. Stewart, 165 Pa. 394; McCloskey v. Marks, 263 Pa. 441.
This conclusion is not affected by the last clause above quoted “that no payment shall be construed to be an acceptance of defective work or improper materials/’ not only because it specifically refers to a “payment” only, which, so far as the present claim is concerned, has not yet been made; but also because it can only relate to the partial payments, for under the immediately preceding clause of the same paragraph, which of course must be considered in determining the meaning of this one, “the final certificate or final payment shall be conclusive.evidence of the performance of this contract ”
The judgment of the court below is affirmed.