DocketNumber: Appeal, No. 408
Judges: Bell, Brien, Cohen, Eagen, Jones, Musmanno, Pee, Roberts
Filed Date: 4/18/1967
Status: Precedential
Modified Date: 11/13/2024
Opinion
Burke Brothers, Inc. entered into a contract with the Pennsylvania State Public School Building Authority for the general construction of a new secondary school in Clearfield County, Pennsylvania. Burke then entered into a sub-contract with Mesker Bros. Iron Company to furnish metal windows and window wall construction for the building at a cost of $19,950. Burke paid Mesker only $9,411.94, and Mesker sued for the balance of $10,538.06. Burke answered that Mesker had failed to deliver the windows at the times stipulated upon between them and that, as a result of such failure, Burke was required to enclose the building by erecting supports to which temporary window coverings were attached. Burke claimed, in addition, that he sustained further financial damage since the failure to deliver the windows on time delayed the course of construction for approximately 14 weeks and accordingly increased the cost of supervision. Thus, Burke claimed that Mesker was indebted to Burke in the sum of $3,800 over and above the $10,538.06 withheld.
Mesker’s contention has been that the failure to deliver the windows at the stipulated time was the fault of the architect for which it should not be held responsible.
By stipulation of counsel, the case was tried without a jury, and the court found in favor of Mesker in the sum of $10,538.06. Burke filed exceptions which were overruled; hence this appeal.
Under all these circumstances it cannot be said that the court below abused its discretion in finding that Mesker was not guilty of undue delay in obtaining the architect’s final approval. This conclusion leads to the necessary result that Mesker is not liable to Burke for the claimed increased costs and Burke is liable to Mesker for the balance due under its subcontract in the amount of $10,538.06.
Judgment affirmed.