DocketNumber: Appeal, No. 45
Judges: Frazer, Kephart, Moschzisker, Sadler, Schaffer, Simpson, Walling
Filed Date: 2/6/1922
Status: Precedential
Modified Date: 10/19/2024
Opinion by
The City of Philadelphia prepared plans for the building of a sewer on 52d Street, which passed along that highway beneath the tracks of the plaintiff’s railroad. Prospective bidders were advised thereby that the railroad company would protect its rails when the excavation made this necessary, the cost to be paid by the contractor, who was directed to include the estimated sum in his proposal. The specifications required that satisfactory arrangement for the necessary support of the right-of-way should be made by the successful bidder. Defendant was awarded the contract on December 17, 1914, and began the construction of the sewer. The railroad line was reached in August of 1915, and consent was secured by Perna to do a part of the work at the crossing, using his own men and materials. It has been found by the jury, under proper instructions, that he then agreed to indemnify the plaintiff for all outlays which it might make in inspecting the work, and guarding against accident, as well as for any other expense to which it was necessarily put by reason of the proposed excavation. Such an understanding was denied by defendant, who insisted his liability was limited to two items, amounting to $190, covering the cost of 'the removal of certain timbers, and the reballasting of the track, and he expressed a willingness to pay that sum alone. This action was then instituted to recover the full amount expended by the plaintiff, which right depended upon the existence of the agreement to reimburse, and the question of fact was found in its favor. Unless then some prejudicial error in the admission of testimony, or in the charge of the court, can be pointed out, the judgment should be sustained.
A number of assignments have been filed, which, in effect, make three complaints. It is insisted, first, that it
Again, the receipt of evidence to show the cost of the necessary inspection and guarding of the tracks, during the sewer construction, is complained of. This objection, suggested in assignments four to seven, is untenable, in
One matter appears upon the record which requires correction. At the time of the excavation, six tracks were upon the ground. Later, a siding was built by the railroad. As to the shoring of this, the cost was assumed by the plaintiff, in an agreement with the city. The verdict rendered includes a charge of $17.11 for work at this point, and this sum is not properly chargeable to defendant. The erroneous inclusion of this item does not make necessary a retrial, for substantial justice can be done by directing a reduction of the judgment accordingly : Gandy v. Klaw, 269 Pa. 820. To this, we understand, the appellee consents.
The assignments of error are overruled, and the judgment is modified, and is here entered for $1,661.86, with interest from April 23,1921, and as so modified it is affirmed.