delivered the opinion of the court,
Peter H. Quin filed this bill against the City of Philadeljfiiia, Peter A. B. Widener, city treasurer, Samuel L. Smedley, chief engineer and surveyor, and A. B. Burton. Three days thereafter, the bill was so amended as to make Samuel P. Hancock a party defendant. On the final hearing, the bill as to Widener was dismissed with costs; but it was adjudged and decreed that the City of Philadelphia, Smedley, Burton and Hancock should each pay to Quin the sum of $4601.22, together with costs of suit. From that decree, the City, Smedley and Hancock severally appealed, and they were argued together.
On the 30th June 1873, Burton entered into a contract with the City of Philadelphia to furnish the materials and construct a bridge over the Philadelphia and West Chester Railroad at Darby road. Payments were made by the city on the monthly estimates, as the work progressed; in all to the amount of $10,000. This left due on the final estimate the sum of $6881.45. The contention arises in regard to the claim of Quin to this money paid by the city on the final estimate.
It appears that Quin was surety for the fulfilment of Burton’s contract, and by writing bearing date the 1st of July 1873, Burton assigned to Quin all his (Burton’s) interest in the contract, “ except the item of superstructure.”
We will first consider the question whether the city, although notified of this assignment, was so far bound thereby as to be liable to Quin for having thereafter paid the money due on the last estimate to Burton. The assignment was not on the contract, but on a separate piece of paper. It was not noted on the contract, nor was it ever filed in the ofiice of the controller. In all five estimates W'ere made and five warrants drawn. All the estimates were made to Burton as contractor. The four preceding warrants in payment of the estimates, as well as the last, were all drawn in favor of Bui-ton. Although Quin, by himself and agents, assisted in the construction of the work, yet it does not appear that the city ever admitted any liability to him or assumed to pay him. It will be observed that the assignment is not of the whole contract, nor of all the money to become due thereon. It is an assignment of a part only. The obligation which the city assumed with Burton was an entire contract. That which the latter assigned to Quin
Having reached this conclusion in regard to the city, it necessarily removes the main grounds of complaint against Smedley. The assignment being invalid as against the city, no mere notice of it to him could make him liable to Quin. Smedley was the engineer and surveyor; his duties were limited; he had no power to change the contract, nor to ratify the assignment. Prior to the final estimate he was not authorized to draw a warrant. He made up the estimates of work done and certified them to the Commissioner of Highways. The appropriation was made to that depart
Then as to the appellant Hancock. Inasmuch as notice to the city or to Smedley of the assignment made to the appellee, was insufficient to prevent the issuing of the warrant to Burton, it necessarily follows that notice to Smedley was not notice to the appellant, and any knowledge he may have had of that assignment furnished no valid reason for withholding his approval.
Two other questions remain to be considered as affecting the liability of the appellant. The one, whether he had such an interest in the warrant itself as' in law to prevent his approving and countersigning it; the other, whether, in case he illegally received a part of the proceeds thereof, the appellee has not a full and adequate remedy at law against him.
The master found the appellant “ had a direct interest in the warrant in violation of law,” and submitted a decree that he should pay to the appellee the sum due to him from Burton. In adopting the decree the court appears to have rested it on the ground that the appellant was interested in the sum due on the estimate, and was to receive a portion thereof, contrary to the ordinance of 20th February 1856. Whether these conclusions are correct depends on the proper construction of the Acts of Assembly and ordinance relating to the duties of the controller.
Section 12 of the Act of 2d February 1854, Pamph. L. 21, declares the controller “shall countersign all warrants on the city treasurer, and shall not suffer any appropriation made by the city councils to be overdrawn, and shall perform all the duties now enjoined by law on the county auditors.” Section 51 declares if any
The ordinance of 20th February 1856 declares, “ no department shall issue any warrant until the bill containing such claim shall be presented by said department to the controller. The controller shall audit such bill with the view to ascertain whether the supplies have been purchased or the services performed, and the sum charged therefor is proper ; and he shall inquire and ascertain if any member of the councils, member or officer of such board, officer of any department or officer or agent of the city corporation is interested in the sum due therefor or is to receive any portion thereof, or has received any commission, consideration or gratuity relating thereto ; and if any party is so interested, he shall refuse to countersign said bill and.report the same to councils.”
The evidence on which it is claimed these statutes and this ordinance impair the validity of the controller’s action is substantially this : From time to time, during the progress of the work, he advanced or loaned money to Burton. He testified, and the evidence appears uncontradicted, that he did it out of compassion for Bur ton and for the benefit of the city ; that the original appropriation was exhausted and he was informed the bridge was not fit for travel; that this money was lent to be used in doing the work, paying the men and paying for the materials. He took Burton’s due-bills therefor, some of which stated they were payable out of the money for the completion of the bridge, and others for sums-payable on demand. It does not appear that Burton made any assignment to him of the fund. When the warrant was presented for the appellant to countersign by Burton, a certified copy of the
The master thought the facts brought the case within the forbidden clause of the Act of 12th February 1854. We think it very doubtful whether a contract for building a bridge comes within the meaning or spirit of “ any sale to or contract for supplies.” The rule for construing statutes of this penal character will hardly justify designating this contract as one “ for supplies furnished the city.” It would seem that the word “ supplies” was designed to apply to property of a personal character. Whether this be the correct, construction is unnecessary now to decide. The proceeding against the appellant is not to impeach him and to remove him from office; nor is it to enjoin him against approving and countersigning the warrant. He had done these acts before these proceedings were commenced. This is merely the claim of one individual against another for the money paid on a warrant which Burton was justly entitled to receive. How did the act of the appellant in countersigning it injure the appellee ? If it had not been signed he could not have attached the debt in the hands of the city: City of Erie v. Knapp, 5 Casey 173; nor could he have compelled the issuing of the warrant to him.
The effect intended to be produced by a literal compliance with the Act of 29th May 1856 is to delay the issuing of the warrant until it shall be specially authorized by city councils. The issuing of this warrant had already been so specially authorized and ordered. No action of the appellant could have procured from the councils more specific authority than that which he held in his hands when he signed the warrant. The warrant stated on its face all the statute required. Its truthfulness was verified by the certified ordinance. He had no right to divert that money from the sole purpose for which it was appropriated. There is no allegation that the contract with Burton was not fairly and honestly made; nor that the estimate was not just and correct. The warrant was drawn for the precise sum specifically appropriated, and for the purpose named in the ordinance. The object of the act had thus been accomplished. The issuing of the warrant was specially authorized by councils.
Then as to the ordinance of 20th February 1856. This manifestly refers to those cases in which “ a bill” must be submitted to the controller before a warrant shall be drawn. It makes no reference to warrants. It provides he “shall audit such bill” for the purpose of ascertaining if any of the objections in the ordinance stated exist. If so found, he shall refuse to countersign “said
It cannot be doubted that the same power which directed the general action of the controller in the cases coming within the ordinance of 20th February 1856, could, by ordinance of 8th June 1874, provide otherwise for the payment of a sum expressly appropriated to a specific object. In this case no “bill” was submitted to the controller in regard to which he could have inquired whether an official was “ interested in the sum due therefor or was to receive any portion thereof.” It is true he knew that he expected to receive from Burton, after the latter had received the warrant, the sums which he had advanced and for which he held due-bills; but the amount due him was in no manner affected by the sum Burton might receive from the city. It was not to be increased nor diminished thereby. It is not claimed that the appellant was interested in the contract when made, nor that he was to receive any share of the money to be paid thereon, “nor that he was to receive, or did receive, any commission, consideration or gratuity relating thereto.” This ordinance of the 20th of February 1856 is a just and salutary one. It should be invoked whenever necessary to secure or protect the city against any collusion, combination or fraudulent conduct of any of its officials prejudicial to its interest. It should not by a forced construction be applied to the settlement of disputes to which the city is not a party, and in which it has no pecuniary interest. The city makes no complaint that the appellant did not refuse to countersign and did not report the reasons for his refusal to the councils. Had he reported to the councils that Burton was to pay him out of the money he was to receive, for the advances made during the progress of the work, the councils could well have replied, “no bill has been submitted for you to examine and audit. This is the case of a final estimate of the chief engineer and surveyor, made on a written contract. By ordinance, duly approved this day by the mayor, we have appropriated the precise sum to pay the estimate, and ordered a warrant to be drawn therefor. If our ordinance of 20th February 1856 would have required you to examine this claim, our ordinance of to-day relieves you therefrom. The claim is just. The debt is due. Burton is entitled to the warrant. You will therefore countersign and deliver it to him.”
The fact must not be overlooked that the appellant had not only countersigned the warrant, but had actually received the money seven days before he was made a party to this bill. Thus, in advance of any proceedings against him, he had actually received the money. If the appellee is justly entitled to that money he has a full and adequate remedy at law : Patterson v. Lane, 11 Casey 275. As
And now, to wit, 6th May 1878, the decree against each of the three several appellants is reversed and set aside, and the bill as to each of them is dismissed without prejudice to the rights of the appellee against Hancock. It is further ordered that the appellee pay the costs of appeal, and in the court below.