DocketNumber: Appeal, No. 138
Citation Numbers: 231 Pa. 208, 80 A. 62, 1911 Pa. LEXIS 817
Judges: Brown, Elkin, Fell, Mestrezat, Moschzisker, Potter
Filed Date: 4/10/1911
Status: Precedential
Modified Date: 10/19/2024
Opinion by
On December 11, 1907, the firm of Lynch Brothers contracted to erect a schoolhouse for the city of Philadelphia, to be finished by August 1, 1908. A percentage of the contract price was to be retained by the city until the acceptance of the building, and the sum of $3,723.58 for a period of twelve months after completion, as a guarantee for the sufficiency of the work. The Fidelity and Deposit Company of Maryland, the defendant, became surety on a bond given by the contractors under the city ordi
The appellant contends that the extensions of time granted by the use plaintiffs to the contractors, without notice to or consent from the surety, released the latter from its liability on the bond. This would be true if the bond were an ordinary contract of suretyship with an individual as surety. But, as we said in the recent case of Young v. American Bonding Company, 228 Pa. 373:
Here the bond was for the protection of subcontractors and others in the construction of a public building. It differs from the ordinary suretyship, in that it is not an obligation for the performance of any particular contract. It was given for the benefit of all persons who might furnish labor or material in the course of the work, whether the contracts for such labor and material were in existence at the time the bond was executed or not, and without regard to the terms of purchase, whether for cash or on credit. In its nature the obligation was more of a contract of insurance than of suretyship; so long as the extensions of credit did not go beyond the two year limit for suit fixed in the bond, and in the absence of fraud or unfair dealing on the part of the subcontractors to the prejudice of the surety, or of material harm actually suffered, the surety was not released. The surety does not aver any of these elements, but relies upon a presumption of injury because the moneys retained by the city were paid over before the expiration of the extensions. These moneys were not retained for the benefit of the surety, but, in the words of the contract, “as a guarantee that . . . .
We find no direct averment in the affidavits of defense that the surety was actually harmed by the extensions granted to the contractors, and the facts as stated therein are not sufficient in themselves to raise such a presumption. For all that appears, the contractor may have paid every cent of the cash received to other material men or mechanics who did work upon the building. In a case of this kind, there is no presumption that the surety company is harmed, the prejudice must be made to appear, and the suggestion of mere contingencies or possibilities is not enough.
The assignments of error are overruled and the judgment is affirmed.
South Phila. State Bank v. National Surety Co. , 288 Pa. 300 ( 1926 )
Watters v. Fisher , 291 Pa. 311 ( 1927 )
City of Montpelier v. National Surety Co. , 97 Vt. 111 ( 1923 )
Grinnell Realty Co. v. General Casualty & Surety Co. , 253 Mich. 16 ( 1931 )
Laurentide Finance Corporation of America v. Capitol ... , 392 F.2d 444 ( 1968 )
Chowning v. First State Bank , 102 Okla. 4 ( 1924 )
Evatt v. Dulaney , 51 Okla. 81 ( 1915 )
Thomas Holme Building & Loan Ass'n v. New Amsterdam ... , 124 Pa. Super. 187 ( 1936 )
Pennsylvania Supply Co. v. National Casualty Co. , 152 Pa. Super. 217 ( 1943 )