DocketNumber: Appeal, No. 187
Judges: Brown, Dean, Fell, McCollum, Mestrezat, Mitchell, Mitciielu, Potter
Filed Date: 2/24/1902
Status: Precedential
Modified Date: 10/19/2024
Opinion by
McManus, the appellant, on April 17, 1894, made a written contract with the city to build a police and fire patrol station on Fairmount avenue for the round price of $27,980. It was to be built according to plans and specifications which were appended to and made part of the contract. Then appears this clause in the contract:
“ It is further understood and agreed that this contract is entered into under and subject to the provisions of the act of assembly .... entitled ‘ An act to provide for the better government of cities of the first class in this commonwealth approved the first day of June, 1885.’ ”
There was also this stipulation:
“ It is further distinctly understood and agreed, that the total amount to be expended for the work to be done under this contract, shall in no event exceed the sum of twenty-seven thousand nine hundred and eighty dollars.”
It was further agreed that all the work done and materials furnished should be subject to the inspection and approval of the director of the department of public works for the city.
During the progress of the work, it is alleged, by McManus, that it was discovered, the specifications in some particulars violated the city building regulations, and these were changed at considerable expense to him, under the directions of the city architect so as to conform to them. Another of the speci
The city paid to the contractor the entire contract price, less the sum of $416, which it claimed the right to deduct because an item of tile work, estimated at $1,800, in the contract, had only cost the contractor $1,884. The changes, substitutions and additions to the specifications made by the contractor amounted to $2,811, for which he demanded payment; the city denied, (1) that such changes had been authorized by its subordinate officers, the architect and his assistants ; (2) it denied any authority on the part of these officers to permit such changes, even if they had been permitted by them. Thereupon McManus brought this suit. The issue was referred to George W. Harkins, Esq., to find the facts and decide the law, under the act of May 14, 1874. After a full hearing of the testimony, he awarded to plaintiff the sum of $2,972, very nearly including balance due on contract, the amount of his claim. The city filed exceptions to the referee’s report in the court below; all of them were sustained, except the one to the allowance of $416, the balance of the contract price, and judgment was entered for this amount with interest, making $569.92. From the decree of the court sustaining the exceptions to all charges, for additions and alterations, McManus brings this appeal, alleging the decree to be erroneous.
The gist of plaintiff’s case is very clearly set forth by the referee in his report. The evidence was contradictory, but from the weight of it, the referee finds that all the changes and additions made by the contractor were made by the directions of the city architect and his assistants and that they were properly made. Therefore, we assume the facts to be with the appellant. The question then, that confronts us is, under the contract and the law, is the city under a legal obligation to pay for the'changes? We start with the express stipulation in the contract, “ The work to be done under this contract shall in no event exceed the sum of twenty-seven thousand nine hundred and eighty dollars.” This being the round sum at which Mc-Manus agreed to erect the building. But suppose the city,
The referee in declining to follow the cases cited undertakes to distinguish them from the one before us on their facts, but in this he fails. True they do not present throughout the same facts, but on the main fact there is no difference; in each, except in the case of Filbert and Porter v. Phila., supra, the contractor sought to enforce a liability of the city on parol directions, outside the contract, from subordinate officers of the city; the latter in each case successfully invoked the act of 1885 and defeated recovery on the parol modifications of the written contract. A recovery in the Filbert and Porter case was allowed,
“ But in view of the great injustice that would follow its application under the peculiar circumstances of the present case, such a most inequitable decision should be avoided, if justly it can be. These changes were not made by the contractor of his own motion, he did not voluntarily depart from the prescribed conditions of his contract, and is not responsible for the departure from them. They were the outcome either of the errors and mistakes of the department itself, or of unforeseen happenings, or of exigencies that developed in the progress of the work. They were made with the approval of the officers of the department and he has borne the expense thereof out of his own pocket. The city has had, and now is enjoying the advantage of them, and there is no just reason why she should not pay for them. Swift and vigorous condemnation would follow repudiation of such a liability by a private individual, and it is difficult to understand why a different code of ethics should prevail in the case of the city.”
The reason why the same code does not apply in the case of a municipality is, that it is not the law. The very reason too, of the law is, that municipal corporations should not be made answerable for money, on sentiment, but only for contract liability under the law. A strict adherence to this rule is. the only protection which such corporations can invoke.
The decree of the court below overruling exception to the award to plaintiff, $569.92 is affirmed and the decree sustaining exceptions of city to balance of award is affirmed.