DocketNumber: Appeal, No. 195
Judges: Brown, McCollum, Mestbezat, Mitchell, Potter
Filed Date: 3/11/1901
Status: Precedential
Modified Date: 10/19/2024
Opinion by
By a contract dated September 12,1898, Flanagan and O’Horo agreed with the borough of Olyphant, in Lackawanna county, to construct a sewer in the first sewer district of said borough, in accordance with the provisions of an ordinance approved July 28,1898, and in conformity with the terms of said contract. The work was to be completed before December 1,1898. The compensation to the contractors was to be $1.75 per lineal foot, payable from moneys collected by virtue of assessments upon the properties benefited, except such portions as might be finally assessed upon the borough by the viewers appointed for the purpose of assessing the costs of said sewer. The agreement contained the following provision: “ This contract is let subject to the proceedings for the assessment of the cost of said sewer now pending, and in case the project should be abandoned by the borough before any work is done or the proceeding should be set aside by a legal process, then there shall be no liability upon the part of the said borough, by virtue of the entering into this contract. ” The construction of the sewer was completed, as found by the court, in November, 1898.
The plaintiff is the owner of real estate in Olyphant borough, and a nonresident taxpayer of said borough. He filed this bill on March 30,1899. lie avers, inter alia, that the ordinance authorizing the contract for the construction of the sewer and the contract itself are illegal and void for the reasons therein set forth, among which is that the ordinance and contract will increase the indebtedness of the borough beyond the constitutional limit. The bill prays for an injunction restraining (1) the defendants from further proceeding with the construction of the sewer, and (2) the defendant borough from issuing any warrants and making any payments to the contractors on account of the construction of the sewer.
The answer denied that the ordinance and contract wore illegal and void, and admitted the assessment upon the borough, but denied that it was an illegal increase of the indebtedness of the borough, and averred that the contractors had constructed the sewer in its entirety in accordance with the terms and provisions of the ordinance and contract. It was further alleged that the plaintiff knew of the contemplated erection of the sewer, that the contract had been let for its construction and made no effort to restrain the defendants from constructing it until it had been fully completed, and that the contractors had expended a large sum of money in constructing the sewer, and that, therefore, the plaintiff was estopped from restraining the payment of the amounts due the contractors by reason of his conduct. The answer also denied that the plaintiff had a legal right to maintain the bill, and averred that he had an adequate remedy at law.
The court below refused the injunction and dismissed the bill on the ground that the plaintiff was guilty of laches and was therefore not entitled to relief in a court of equity.
The learned trial judge says in his opinion “ that many of the irregularities complained of in the bill exist in this case,” and then proceeds to find the following facts:
2. The contract to build the sewer was let to Flanagan and O’Horo, September 12, 1898. The resolution awarding the contract was not transcribed in the ordinance book. The ordinance provided that the advertisements for bids should not be made before the report of the viewers was approved by the court. This provision was not regarded by the council. The viewers’ report was confirmed nisi March 18,1899. The plaintiff in this case filed exceptions to the report. These exceptions have not yet been disposed of. The contract was let “ subject to the report of viewers.”
3. By admission of counsel for defendants it appears that the indebtedness of the borough in 1898, exceeded two per cent of the assessed valuation. The borough’s share of the cost of building the sewer is $2,603.53.
It is apparent the first prayer of the bill, that the defendants be restrained from further proceeding with the construction of the sewer, cannot be granted for the all-sufficient reason that the sewer had been entirely constructed before the bill was filed. The remaining question for consideration arises on the second prayer, that the borough be restrained from making any further payments to the contractors on account of the money due them for the erection of the sewer in pursuance of their contract. The learned trial judge refused the relief asked for in this prayer, and on the ground of laches, denied the right of the plaintiff to invoke the aid of a court of equity to enjoin the borough from making full payment of the money due the contractors.
From the evidence in the case and the facts found by the
Aside from the many “ irregularities ” found by the court below to exist in the action of the municipal authorities, participated in at least to a certain extent by the contractors, is a clear and distinct violation of the constitution of the commonwealth. Article 9, section 8 of that instrument is as follows: “ The debt of any borough .... shall never exceed seven per centum upon the assessed value of the taxable property therein, nor shall any such municipality or district incur any new debt, or increase its indebtedness, to an amount exceeding two per centum upon such assessed valuation of property, without the assent of the electors thereof, at a public election in such manner as shall be provided by law.” It is conceded by the defendants that at the time the ordinance was adopted and the contract was entered into for the construction of the sewer, the indebtedness of the borough exceeded the constitutional limitation. It is not pretended that the assent of the electors of the borough to an additional indebtedness such as this contract creates was obtained at a public election or otherwise. Unless, therefore, the plaintiff is by his laches estopped from invoking the constitutional mandate for his protection, which likewise is the protection of every other taxpayer of the borough, the second prayer of the bill must be granted, and the municipal authorities be restrained from a further application of the funds of the borough to this indebtedness.
In order to determine the question of the plaintiff’s laches in filing his bill, we must ascertain and recur to the facts. The trial judge, while holding the plaintiff guilty of laches, has not found all the facts disclosed by the testimony in the case.
The parties disagree as to when the plaintiff first knew of the proposed improvement. The plaintiff alleges it was in November, 1898, the month in which the sewer was completed. The defendants claim that it was in the summer or fall of 1898, and that, therefore, it was at the time the contract was made, or prior thereto. This is the inference the defendants draw from the plaintiff’s own testimony. But we do not agree that such is the import of the language used by him on the witness stand. While it is somewhat indefinite, yet we think it shows that he did not see the work during its progress, and did not learn of the intention to construct the sewer until about the time of its completion.
Now if we assume, as claimed by the defendants, that the plaintiff, prior to the making of the contract and commencement of the work, was cognizant of the intention to erect a sewer, yet we are unable to see why he would be compelled to file his bill at that time or otherwise to rest under the imputation of laches. The information he would receive by an investigation at that time would be such as he might obtain from the
In another view, which is supported by the facts in the case, the plaintiff did not know of the intended improvement until about the time of its completion. This was in November, 1898. His bill was filed the following March. It has not been shown, and it does not appear, that in this interim conditions were changed, or that any act was done by which the defendants were injured in any way. Since the plaintiff first learned of the improvement, there has been no change in the status of the parties or in the affairs of the borough to affect injuriously the defendants. Hence the plaintiff’s “ standing by for four months
We do not think that any laches can be imputed to the plaintiff until at least the date of filing the report in court, which was March 18,1899. Until that time, he certainly had no right to presume that the provisions of the ordinance requiring the expenses of the improvements to be paid by the benefits assessed against the property owner would not be carried out, or to assume that the viewers would make an assessment against the borough and thereby increase its indebtedness beyond the constitutional limit. A knowledge of the construction of the sewer would not of itself, under the provisions of the ordinance and contract, have justified the conclusion that any liability would be imposed on the borough by the action of the viewers. The plaintiff, therefore, was not compelled to anticipate such a result and file his bill before the viewers had so determined and filed their report.
As the bill was filed in seventeen days after the report of viewers was presented to the court, it was done with sufficient promptness to repel any charge of laches.
The view we take of the case, therefore, determines it on the facts which, under well settled rules, relieve the plaintiff from the charge of undue delay in bringing his bill.
Many authorities have been cited by counsel on either side to support their contention as to what constitutes such laches as will estop a party from asserting his rights in a court of equity. It will be observed that they are all to the same effect, and that the only difference is that which arises in their application to the facts of the case under consideration. Under the facts of the case in hand, we think the appellee’s construction of the numerous authorities cited by them does not sustain their contention. The efficacy of the rule established
The learned counsel for the appellees seems to think that the only objections that have been made to the proceedings in this case are of an extremely technical nature, and so long delayed that they are not entitled to consideration in a court of equity. From the reckless manner in which the proceedings were conducted by the borough officials, we think it is evident that their views fully coincide with those of their counsel. We have referred to, but have not discussed, what are termed “ irregularities ” in the proceedings. Our decision rests upon a plain and palpable violation of a provision of the constitution of the commonwealth by the municipal authorities. This, we regret to say, is too frequently regarded as nothing beyond a technical objection to the illegal action of the officers of many of the municipalities of the state. It is therefore incumbent upon the courts, when the opportunity is presented, to enforce the constitution in a manner that will impress upon officials and citizens alike the necessity of a strict observance of that instrument as the supreme law of the commonwealth. In the case in hand, it works no hardship to the contractors. To their allegation that they had no way of ascertaining the indebtedness of the borough, the answer is that it was their duty to ascertain it in some way, or to refuse to enter into the contract until the borough officials had satisfied them that the proposed additional indebtedness would be within the constitutional limit. Without taking this precaution, they acted at their peril. It is a general and fundamental principle of law that all persons contracting with a municipal corporation must at their peril inquire into the power of the corporation or of its officers to make the contract; and a contract beyond the scope of the corporate power is void, although it be under the seal of the corporation : 1 Dillon on Municipal Corporations, sec. 447.
But it is apparent from the contract itself that neither the officials acting for the borough nor the contractors, were certain of the legality of the proceedings under which the improvement 'was to be made. It is there stipulated, as we have seen, that there should be no liability on the part of the borough, if the proceedings should be declared illegal. Any interpretation that may reasonably be given to this clause of the agreement is con
The answer alleges that the plaintiff has an adequate remedy at law and that, therefore, a court of equity has no jurisdiction. The question thus raised was not discussed or determined by the trial judge of the court below, who ruled the case solely on the ground of the plaintiff’s laches. The counsel for neither party has discussed the right of the plaintiff to maintain the bill, and we shall not do so. Under the facts of this case, we think the plaintiff is entitled to have his right to the relief he seeks determined in a court of equity.
The decree of the court below is reversed, and it is now, March .11,1901, ordered, adjudged and decreed that the bill be reinstated, and that an injunction be issued by the court below restraining the burgess, town council and treasurer of the borough of Olyphant from issuing any warrants and making payments to Flanagan and O’Horo or their assigns for or on account of the construction of said sewer. It is further ordered that the costs of the proceeding, including the costs of this appeal, be paid in equal proportions by the borough of Olyphant and Flanagan and O’Horo.