DocketNumber: Appeal, 305
Judges: Frazer, Walling, Simpson, Kephart, Schaefer, Maxey, Drew
Filed Date: 12/1/1931
Status: Precedential
Modified Date: 11/13/2024
Argued December 1, 1931. The basic question in this case is whether or not the bond in suit is one of guaranty or indemnity. The action is assumpsit on a completion bond; the lower court held it to be a guaranty, and the measure of damage thereon to be the cost of completion. These rulings were excepted to, and after judgment was entered on the verdict, they were assigned as error, and defendants appealed. *Page 292
The facts are almost determinative of the issue, and are as follows: The plaintiff, Mrs. Elizabeth Purdy, sold to one Valentine Kulp, a straw man for Isaac Wood Massey, defendant, a piece of land in Philadelphia for $85,000; she received $25,000 in cash and a purchase-money mortgage, with bond, for the balance of $60,000. Massey intended to build a garage on the lot, and to finance the undertaking he induced plaintiff to subordinate her mortgage to another mortgage equal in amount to the cost of construction. She agreed to do so provided the building was completed or she received a bond guaranteeing completion. This arrangement was effected. Plaintiff subordinated her mortgage to a first mortgage placed with the Home Life Insurance Company for the contract price of the building, $80,000, after defendants, Massey as principal and Indemnity Insurance Company of North America as surety, had given their bond for $60,000, the amount of her mortgage. This bond, after reciting the facts, provided that if Massey should "complete the building mentioned free and clear of mechanics' liens or claims, then this obligation shall be void; otherwise to be and remain in full force and effect."
The garage was never built. Some neighbors objected to a public garage at that place, filed a bill in equity, and secured an injunction restraining Massey and Kulp "from using or operating or permitting to be used or operated as a public garage or automobile sales and service station . . . . . . any . . . . . . building . . . . . . erected on said lot." Massey and Kulp then refused to erect the building. The defendants were immediately notified and demand made upon them to perform the obligation of their bond. They declined to do so, the Home Life Insurance Company foreclosed its mortgage on account of nonpayment of interest, a sale was had, and the plaintiff's second mortgage was wiped out. She has received nothing on account of interest or principal due her on the mortgage given by Kulp, and the judgment which plaintiff has entered against him on the bond which the *Page 293 mortgage was given to secure is worthless, and nothing can be recovered thereon. Unless plaintiff can recover on this bond she will have received $25,000 for the property which she sold for $85,000, and she will have suffered a loss of $60,000 and interest thereon through no fault of her own. She no longer has her property or her mortgage, and she has now brought suit against defendants on their bond.
Is this bond one of guaranty or merely an indemnity against loss? "The distinction between the two agreements is simply that between an affirmative covenant for a specific thing, and one of indemnity against damage by reason of the nonperformance of the thing specified": Weightman v. Union Trust Co.,
This bond is to be construed most strictly in favor of the plaintiff. The obligor, Indemnity Insurance Company of North America, is a paid surety engaged in the business of furnishing bonds for profit; we have frequently held that in cases of corporate sureties, the bond is to be strictly construed in favor of the obligee: Young *Page 294
v. American Bonding Co.,
The condition of the bond is performance of a specific thing — completion of the building provided for in plans and specifications made a part of the bond — and the only alternative for performance is the bond itself. It is obvious, being clearly expressed by the words of the bond and the circumstances surrounding the transaction, that the intent of all concerned was to give plaintiff in lieu of her first mortgage the enhanced value of the real estate by the addition of the building, or failing that, its equivalent in money — not to exceed the face value of the bond. It can readily be seen that such an arrangement was a sound business transaction, and as events happened, a wise precaution for and by the plaintiff. In giving up her first lien on the property to help finance the building, she could not have protected herself in any better way.
That this is a guaranty bond, an affirmative covenant to complete the building in event of default by the principal, is firmly established by our cases: Janes v. Scott,
In regard to the measure of damage, the court below required the plaintiff to show the cost of erecting the building contemplated in the contract. The estimates of the witnesses ranged from $45,000 to $70,000, and the court instructed the jury that if they found the fair cost to be more than $60,000, they could not give a verdict in excess of that sum because such was the amount of the bond. The verdict was for $60,000 with interest. In fixing compensation for damage resulting from breach of a contract the general rule is that the injured party should be placed in the same position as if there had been no breach. The object of the law is to place such party in as good position as if the contract had been kept. In the instant case the bond guaranteed the completion of the building; if there had not been a breach of the obligation of the bond, the building would have been erected. Since this was not done, the plaintiff can only be put in as good position as if the contract had been carried out by giving her the cost of construction, not exceeding, of course, the amount of the bond. The measure of damage on a bond guaranteeing completion is the cost of completion: Equitable Trust Co. v. National Surety Co., supra; Mechanics Trust Co. v. Fidelity Casualty Co., supra; Board of Education v. Maryland Casualty Co.,
Defendants contend that the injunction issued against Kulp and Massey was a sufficient legal excuse and justification for their failure to erect the building. It is their only excuse, and it is neither legal nor sufficient. An examination of the decree shows that they were restrained only from operating a public garage on the *Page 296
premises; not one word was said against the construction of this or any other building on the property. They could have erected any kind of building, the decree only prohibited them from using whatever building might be erected as a public garage. The precise question was passed upon in Penniman v. Hoffman,
It is also contended by defendants that the plaintiff has no interest in the present cause of action, and is therefore not entitled to recover. At the trial an offer was made to show that plaintiff has no financial interest in the property or in the mortgage. An objection to this offer was sustained by the court, which action is assigned as error. The offer was properly refused; it was not within the issues framed under the pleadings, not having been pleaded as a defense: Ruth-Hastings Glass Tube Co. v. Slattery,
The assignments of error are overruled and the judgment of the court below is affirmed.
South Phila. State Bank v. National Surety Co. ( 1926 )
Mechanics Trust Co. v. Fidelity & Casualty Co. ( 1931 )
Berks County ex rel. School District v. Levan ( 1878 )
Union Trust Co. v. Citizens' Trust & Surety Co. ( 1898 )
Weightman v. Union Trust Co. ( 1904 )
American Manufacturing Co. v. S. Morgan Smith Co. ( 1904 )
C. H. Hardy Auto Co. v. Posey ( 1912 )
Guaranty Trust & Safe Deposit Co. v. Powell ( 1892 )
Equitable Trust Co. v. National Surety Co. ( 1906 )
Borough v. Pittsburg & Beaver Street Railway Co. ( 1912 )
Young v. American Bonding Co. ( 1910 )
Folz v. Tradesmen's Trust & Saving Fund Co. ( 1902 )
Shaw v. New Amsterdam Casualty Co. ( 1932 )
League Island Community Building & Loan Ass'n v. Doyle ( 1936 )
Proudley v. Fidelity & Guaranty Fire Corp. ( 1942 )
Poole v. Great American Insurance ( 1962 )
Pennsylvania Turnpike Commission v. Andrews & Andrews ( 1946 )
Westville Land Co. v. Handle ( 1934 )
Manufacturers & Merchants Building & Loan Ass'n v. Willey ( 1936 )
Pennsylvania Co. v. Lebanon Building & Loan Ass'n ( 1939 )
Hess v. Merion Title & Trust Co. of Ardmore ( 1935 )
Front & Huntingdon Building & Loan Ass'n v. Berzinski ( 1937 )
Harman Et Ux. v. Chambers ( 1948 )
E. P. Wilbur Trust Co. v. Eberts ( 1939 )
Trainor Co. v. Aetna Casualty & Surety Co. ( 1933 )
Bill Curphy Co. v. Elliott ( 1953 )
Provident Trust Co. v. Metropolitan Casualty Ins. Co. ( 1945 )
Brier Hill Coal Co. v. Hartford Steam Boiler Inspection & ... ( 1941 )