DocketNumber: 19 MAP 2005
Judges: Cappy, Castille, Nigro, Newman, Saylor, Eakin, Baer, Former
Filed Date: 11/21/2006
Status: Precedential
Modified Date: 10/19/2024
OPINION
The issue on appeal is whether a demonstration of public need for water alone is sufficient to require a water company to extend its water lines and service without receiving customer contribution, in an instance where the cost of the extension project would exceed the company’s expected revenue from the extension. Because we find that the Public Utility Commission’s (“PUC’s”) line extension regulations, which authorize a utility to require customer contribution in an instance such as this, are a proper application of statutory authority, we affirm.
On May 3, 2001, Cindy Parks filed a complaint with the PUC alleging that the town of Hickory in Mount Pleasant Township, Washington County, lacked public water that residents and property owners both needed and wanted.
On June 14, 2001, the Office of Consumer Advocate (“OCA”) filed a Motion of Intervention and Public Statement, stating that it intended to assist Parks and other Township residents to obtain public water at the lowest reasonable cost. After a pre-hearing conference, by letter dated January 25, 2002, the OCA requested an indefinite suspension of the litigation schedule because of an agreement between the parties that the PAWC would apply for a Penn Vest loan. Penn Vest
On August 21, 2002, the OCA filed a complaint against the PAWC, alleging that the Township had an inadequate quantity and quality of water. The OCA requested that the PAWC be required, at the PAWC’s sole expense, to extend its water service into the Township and alleged that the PAWC was in violation of Section 1501 of the Public Utility Code, 66 Pa.C.S. § 101 et seq., which requires public utilities to extend water lines “as shall be necessary ... for the accommodation, convenience and safety of its patrons, employees, and the public.” Id. § 1501. On September 12, 2002, the PAWC filed an answer denying the claims made by the OCA, and asserting that it would extend service to bona fide service applicants if the terms of its Tariff were satisfied. Pursuant to that Tariff (and the PUC regulations it tracked), the PAWC claimed that it was obliged to expend $6200 per bona fide service applicant for the extension of water service, but the remainder of the cost of the project would have to be borne by the service applicants or some other entity on behalf of the applicants.
ALJ Larry Gesoff held evidentiary hearings on September 9, 2002 and December 3, 2002. Local residents, landowners and community leaders testified regarding the inadequate water supply and poor and unsafe quality of their water. Residents testified to problems they had encountered in accessing water, the costs they had expended in installing and maintaining equipment used to obtain, store and render potable their water supplies, and other costs attributable to having to turn elsewhere for water or water-related services (such as clothes laundering). Residents also testified to the danger posed in the event of a fire, as water for fighting fires must be
The parties disputed the question of whether the line extension project was one that would require customer contribution under the Commission’s line extension regulations and the PAWC’s Rule 27. The PAWC argued that the cost of the project would exceed its required investment, and thus it was entitled to request customer contribution as a condition of undertaking the project, while the OCA argued that the PAWC’s required investment would be substantially more than the cost of the project, and thus, no customer contribution would be required. To understand the competing calculations requires some understanding of the operation of the regulations. The regulations provide a method for determining the investment required of the utility for each “bona fide service applicant.” That per-applicant investment is then multiplied by the number of bona fide service applicants; the total dollar figure represents the utility’s required investment. The utility’s investment amount is then measured against the estimated cost of the project. If the utility investment exceeds the cost, no customer contribution is required. If the required utility investment is less than the project cost, however, contribution may be requested of bona fide service applicants, whose individual obligation is determined by simply dividing the cost difference by the number of applicants.
The PAWC produced evidence that the main line water extension project in the Township (as proposed by the OCA) would involve in excess of 83,000 feet of water mains and a one-million gallon storage tank, and would cost $6,290,499. Calculating its investment obligation, the PAWC assumed 744 new customers as bona fide service applicants.
In a comprehensive, 89-page decision and order filed on April 16, 2003, ALJ Gesoff dismissed the complaints. Relevant to the issue before this Court, the ALJ found that the Township was in need of a dependable water source due to the diminishing quantity and quality of the water available, but that the need for water alone did not oblige the PAWC to extend its service without customer contribution. Instead, the ALJ found that the application of the PUC line extension regulations, and the PAWC’s tariff, were reasonable, and that application of those regulations would require customer contribution. In reaching this conclusion, the ALJ accepted the PAWC’s weighted cost of debt and its estimated cost of the project. PUC Initial Decision, at 56-70.
The OCA filed exceptions to the ALJ’s order with the PUC and the PAWC filed reply exceptions. In an opinion and order entered on August 8, 2003, the PUC denied the OCA’s exceptions, adopted the ALJ’s Initial Decision to the extent it was consistent with the PUC’s opinion and order, and dismissed the complaints. The PUC rejected the OCA’s argument that the demonstration of public need alone requires the extension of water lines at the utility’s expense, noting that it had already considered and rejected that argument in previous cases, including a challenge brought by the OCA to the PAWC’s adoption of its Tariff Rule 27. Opinion and Order at 5, citing Popowsky v. Pennsylvania-American Water Co., Docket No. R-00943155C001, 1997 Pa. PUC LEXIS 142 (order entered June 9, 1997). In the prior decision, the PUC had noted that, although the OCA’s suggestion of such a duty upon the part of the utility “is an interesting social program,” neither the Commission nor the courts had required it, and
The PUC also dismissed the OCA’s claim that the PUC should waive the regulations upon a showing of compelling need. The PUC acknowledged that it had the authority to waive a requirement in its regulations, but only if the waiver would not adversely affect the substantive right of a party. Id. at 7. The PUC then went on to explain at some length why the waiver/exception posed by the OCA was neither required nor acceptable:
[The PUC’s line extension] regulations were approved by the Commission’s Order entered on October 7, 1996.... Following approval by the Independent Regulatory Review Commission (IRRC) and the applicable committees of the Pennsylvania House and Senate, the regulations and the Commission's] October 7, 1996 Order were published at 27 Pennsylvania Bulletin 799 et seq. (February 15, 1997). The final line extension regulations were three years in the making and reflect the Commission’s definitive statement of how requests for main extensions by “Bona Fide Service Applicants” are to be resolved.
We also note that ignoring the existence of our line extension regulations, as advocated by the OCA, would open the door to a pattern of burdensome, case-by-case litigation of requests for line extensions. As the Commission made clear in its October 7, 1996 Order, our line extension regulations were adopted for the express purpose of supplanting case-by-case adjudications, which experience had shown to be unacceptable. (27 Pa. Bull. at 800.) Yet the broad “exception” urged by the OCA in this proceeding, i.e., a “public need” exception, would make virtually all line extensions subject to such burdensome case-by-case litigation. Therefore, we find that this case is governed by our regulations on line extensions and that the presiding ALJ applied the appropriate standard of review.
Id. In response to additional objections from the OCA, the PUC further upheld the ALJ’s determinations that, inter alia: (1) under the regulatory definition of the term, there were no
The OCA then appealed to the Commonwealth Court, which affirmed in a divided, published, en banc decision. Popowsky v. Pennsylvania Public Utility Comm’n, 853 A.2d 1097 (Pa.Cmwlth.2004) (en banc). The panel majority, per the Honorable Mary Hannah Leavitt, summarized the issues as follows: (1) whether the PUC’s application of its line extension regulations violated Pennsylvania case law holding that a utility must bear the capital expense of extending service where there is a public need for that service; (2) whether the PUC’S acceptance of the PAWC’s interpretation of Rule 27 of its Tariff “nullified” the PUC’s duty to adjudicate complaints pursuant to the Public Utility Code; and (3) whether the PUC’s decision was supported by substantial evidence.
Respecting the first question, the majority noted that it was undisputed that the PUC’s regulations were adopted in compliance with the requirements of the Commonwealth Documents Law, 45 Pa.C.S. § 1102 et seq., the Commonwealth Attorneys Act, 71 Pa.C.S. § 732-204(b), and the Regulatory Review Act, 71 P.S. §§ 745.1-745.15. The OCA argued, however, that the regulations as so adopted conflicted with a duty every utility has under Section 1501 the Public Utility Code to provide service to the public where a need for such service is established. In the OCA’s view, the PUC was obliged to allow for an exemption from customer contributions on a case-by-case basis in “public need” instances where such an exemption would not cause the utility “material, economic harm.”
Before analyzing the OCA’s public need claim, the majority outlined the history and purpose of the PUC’s regulations. The majority began by citing Section 1501 of the Code, which expressly authorizes a utility, with the approval of the PUC, to adopt “reasonable rules and regulations governing the conditions under which it shall be required to render service.” 66
With this background in mind, the majority turned to the OCA’s public need argument, noting that the OCA principally relied upon Ridley Township v. Pennsylvania Public Utility Comm’n, 172 Pa.Super. 472, 94 A.2d 168 (1953), which it cited for the proposition that public utilities must provide service without customer contribution unless the utility can demonstrate “material economic harm to the utility or undue burden upon existing customers.” The majority disagreed with the OCA’s reading of Ridley Township, concluding that, in fact, that case recognized that the PUC has discretion to determine when customer contribution is appropriately required for a line extension project, and noting that subsequent appellate cases support this reading of the case. 853 A.2d at 1105-06, citing Colonial Products Co. v. Pennsylvania Public Utility Comm’n, 188 Pa.Super. 163, 146 A.2d 657 (1958) and Lynch v.
The majority went on to note that Section 1504 of the Public Utility Code provides the PUC with the express power to prescribe by regulation “just and reasonable standards ... to be furnished, imposed, observed and followed by any and all public utilities.” 66 Pa.C.S. § 1504(1). The majority further noted that, in its order adopting the line extension regulations, the PUC stated its belief that the regulations were consistent with Ridley Township because “a negative equity return is a material handicap.” 853 A.2d at 1106. The majority then explained that Rule 27 of the PAWC’s tariff was approved by the PUC because it satisfied the standards outlined in the regulations.
Turning to the effect of the regulations, the majority noted that agency regulations are binding on the court so long as they are in accord with the power delegated to the agency, are enacted with proper procedures, and are reasonable; and an agency’s interpretation of its own regulations will be deemed controlling unless it is plainly erroneous or inconsistent with the regulation. 853 A.2d at 1106, citing Moyer v. Berks County Bd. of Assessment Appeals, 803 A.2d 833, 842 (Pa.Cmwlth.2002). In the case sub judice, the majority found, the PUC’s interpretation of the regulations was not clearly erroneous and the regulations themselves were consistent with the judicial interpretation of Section 1501, as found in Ridley Township and its progeny. Accepting the OCA’s “public need” exception, the majority reasoned, would vitiate the line extension regulations and would mean that all line extension disputes would be subject to “ponderous and protracted case-by-case litigation,” which was precisely the result the regulations were designed to avoid. Thus, the majority concluded, the PUC did not err in applying its regulations in this case, and the complaints were properly dismissed.
The fact that the PUC has established standards that give meaning to the requirement in Section 1501 that a utility establish “reasonable conditions” for extending service is not an abdication of responsibility. To the contrary, giving precision to what otherwise may be characterized as an open-ended statute is a proper exercise of the PUC’s responsibility.
853 A.2d at 1107-08 (footnote omitted).
Finally, the majority discussed at some length, and ultimately rejected, the OCA’s fact-bound claim that the order of the PUC was not supported by substantial evidence. Since the propriety of that determination was not challenged in the allocatur petition in this matter, see discussion infra, the specifics of the claim, and the court’s reasoning, are of no moment here.
Judge Smith-Ribner authored a dissenting opinion, which President Judge Colins joined. The dissent confined itself to the OCA’s public need argument. The dissent noted that the “break-even” formula adopted in the PUC’s regulations determines a utility’s financial obligation for service extension by looking only to “costs and revenue, without separate regard for the degree of public need for the service extension.” In the dissent’s view, the PUC’s “categorical” exclusion of public need as an independent factor in determining whether customer contributions should be required “contravenes” Section 1501’s “mandate ... that a public utility ‘shall make all such ... extensions ... as shall be necessary or proper for the accommodation, convenience, and safety of its patrons, employees, and the public.’ ” Popowsky, 853 A.2d at 1111
The OCA petitioned this Court for further review, raising three questions which, in actuality, were all permutations of a basic claim concerning whether the Commonwealth Court and the administrative tribunals erred in determining that a demonstrated public need for water alone is not enough to require a water utility to extend service without customer contribution under Section 1501. We granted review.
The core of the dispute centers on the meaning of Section 1501 of the Code, and the congruence of the PUC’s regulations with that provision. Section 1501 provides as follows:
Every public utility shall furnish and maintain adequate, efficient, safe, and reasonable service and facilities, and shall make all such repairs, changes, alterations, substitutions, extensions, and improvements in or to such service facilities as shall be necessary or proper for the accommodation, convenience, and safety of its patrons, employees, and the public. Such service also shall be reasonably continuous and without unreasonable interruptions or delay. Such service and facilities shall be in conformity with the regulations and orders of the commission. Subject to the provisions of this part and the regulations and orders of the commission, every public utility may have reasonable rules and regulations governing the conditions under which it*623 shall be required to render service. Any public utility beyond its corporate limits shall be subject to regulation and control by the commission as to service and extensions, with the same force and in like manner as if such service were rendered by a public utility. The commission shall have sole and exclusive jurisdiction to promulgate rules and regulations for the allocation of natural or artificial gas supply by a public utility.
66 Pa.C.S. § 1501. The PUC has adopted regulations that address the instances in which a public utility company is required to extend its services. 52 Pa.Code §§ 65.1-65.23. Section 65.21, entitled “Duty of public utility to make line extensions,” addresses when customer contributions (advances) may (or may not) be required of bona fide service applicants, adopting what is indeed essentially a “break-even” analysis:
Each public utility shall file with the Commission, as part of its tariff, a rule setting forth the conditions under which facilities will be extended to supply service to an applicant within its service area. Upon request by a bona fide service applicant, a utility shall construct line extensions within its franchised territory consistent with the following directives:
(1) Line extensions to bona fide service applicants shall be funded without customer advance if the annual revenue from the line extension will equal or exceed the utility’s annual line extension costs.
(2) If the annual revenue from the line extension will not equal or exceed the utility’s annual line extension costs, a bona fide service applicant may be required to provide a customer advance to the utility’s cost of construction for the line extension. The utility’s investment for the line extension shall be the portion of the total construction costs which generate annual line extension costs equal to annual revenue from the line extension. The customer advance amount shall be determined by subtracting the utility’s investment for the line extension from the total construction costs.
The parties track the positions they established in the proceedings below. The OCA focuses on the language in Section 1501 providing that utilities shall make all extensions “as shall be necessary or proper for the ... safety of its patrons, employees and the public.” The OCA construes the statute as dictating that utilities are required to provide line extensions upon a showing of public need alone, and thus the PUC’s regulations must account for public need. The OCA argues that there clearly was a showing of public need for water service in the case sub judice and the Commonwealth Court majority ignored the statutory mandate that that need be considered.
In support of its position, the OCA relies upon Ridley Township and a 1992 policy statement from the PUC declaring that the holding in Ridley Township was the policy of the Commission.
The OCA further argues that the PUC’s interpretation and application of the statute and the line extension regulations in this case is inconsistent with the meaning and intent of Section 1501 and is unreasonable. The OCA contends that the PUC failed to implement the plain language of Section 1501, neglected to give effect to all of the Code’s provisions, and ignored its responsibility to consider public interest over private concerns. Thus, the OCA contends, even though the PUC had the authority to promulgate the line extension regulations and did so in a procedurally proper manner, the regulations should be overturned because their application and interpretation produced an unlawful result here.
Finally, the OCA argues that requiring the utility to extend service without new customer contribution would not result in an ultimate loss to the utility because the utility would benefit from the revenue generated by new customers. Traditionally, it argues, rates are determined by averaging all costs associated with a particular customer class; thus, utilities do not charge individual customers for the costs of repairs to their specific lines. Such principles, the OCA contends, should also be considered in line extension cases. The OCA suggests that
The PAWC and the PUC have filed separate briefs, each arguing that the Commonwealth Court’s decision was consistent with the Public Utility Code, the line extension regulations, and applicable Pennsylvania case law. They contend that the regulations were a proper exercise of the PUC’s rulemaking authority and provide a uniform standard under which customers may be required to pay a portion of initial construction costs, but in instances where the annual revenue expected from the line extension does not equal or exceed the annual line extension costs.
The PAWC notes that the current regulations were established in response to a massive amount of litigation arising from a prior policy of case-specific review for all disputed line extension cases. The problems with the prior policy also led to the rescinding of the 1992 policy statement relied upon by the OCA. In response to the claim that the regulations ignore public need, the PAWC explains that, when a bona fide service applicant applies for the extension of service, the PUC’s regulations presume the existence of public need, as demonstrated by the distinction the regulations draw between developers and bona fide service applicants.
The PAWC further disputes the OCA’s argument that the plain language of Section 1501 requires the PAWC to bear the cost of line extension upon a showing of public need. Citing this Court’s decision in Rohrbaugh, the PAWC argues that Section 1504 confers on the PUC the authority to adopt regulations regarding a utility’s obligation arising from Section 1501. It further contends that the plain language of Section 1501 provides for the establishment of regulations and that these legislative regulations must be shown deference by the courts as they fairly balance the interests of utilities, existing customers, and prospective customers. The PAWC also claims that because new customers will receive a refund if additional customers attach to the extended main, the utility does not profit at all on line extensions funded in part by customer contributions.
The PAWC also notes that Section 1501 applies to all aspects of utility service and that if a utility’s service obligation were as absolute as the OCA contends, the PUC would be precluded from adopting regulations that condition any aspect of utility service, including the requirement that customers pay rates. The PAWC contends that a plain reading of Section 1501 can reasonably allow for both rates and customer contribution to line extension and that the regulations at issue here do not relieve the PAWC of its obligation to extend its service lines, they just require bona fide service applicants to contribute to such extensions in instances where the utility otherwise would not break even on the extension investment.
The PAWC emphasizes that the regulations were established by the PUC and the PUC has special expertise regarding utility law. The criteria set forth in the regulations, the PAWC contends, represent an exercise of the PUC’s ratemak
In its brief, the PUC notes that it explained the purpose and meaning of its regulations in the order which adopted the regulations. That order indicated that the PUC recognized that it was required to balance the interests of potential customers, existing customers, and the utilities, and had concluded that there is no obligation for a utility to make line extensions “which are uneconomic or unreasonable.” OCA Brief, at 16 (citing 27 Pa. Bull. 799, 800). The PUC suggests that the purpose of the formula in the regulations (which sets forth the utility’s required contribution) is to allow the utility to avoid an out-of-pocket loss that ultimately would be passed on to existing customers. Citing Lynch, 594 A.2d at 818, the PUC argues that customers may be required to contribute to line extension costs unless they can show that there is a public necessity for the extension and that the extension will yield a positive return of investment for the utility. The PUC also contends that the OCA’s reliance on Ridley Township is an attempt to re-litigate an issue that was considered by the PUC during the enactment of the regulations and was rejected in the final version of those regulations.
The PUC does not dispute that utilities may be required to extend service upon a showing of public need, but it emphasizes that, contrary to the OCA’s argument, utilities are not always required to do so at their sole cost. Instead, customer contribution may be required where the utility’s annual line extension costs will exceed the annual return on the service extension. The PUC argues that the OCA fails to recognize the language in Section 1501 which empowers the PUC to establish regulations “governing the conditions under which [utilities] may be required to render service.” 66 Pa.C.S. § 1501. The PUC argues that, when read in its entirety, Section 1501 clearly bestows upon the PUC the power to
Finally, the PUC argues that an agency’s interpretation of its regulations are entitled to deference as long as the interpretation is consistent with the statute and the legislative intent, and are narrowly construed. The PUC claims that in this case, it lawfully applied the line extension regulations. The PUC also contends that the regulations are binding on the courts because they are within the scope of the delegated power, were properly enacted, and are reasonable. Likewise, the PUC claims that the PAWC’s tariff, and the PUC’s interpretation of it, is binding on the courts because it is not discriminatory or unreasonable.
When this Court reviews an administrative agency’s interpretation of its own regulations, we must follow a two step analysis. “First, ‘[i]n construing administrative regulations, the ultimate criterion is the administrative interpretation, which becomes of controlling weight unless it is plainly erroneous or inconsistent -with the regulation____’ Second, the regulations ‘must be consistent with the statute under which they were promulgated.’ ” Commonwealth of Pennsylvania, Dept. of Public Welfare v. Forbes Health System, 492 Pa. 77, 422 A.2d 480, 482 (1980) (citations omitted).
Here, the administrative agency — the PUC — interpreted its line extension regulations as authorizing a utility to require contributions from bona fide service applicants if the cost of the extension project to the utility will exceed the expected return on the extension. This interpretation is wholly consistent with the plain language of the regulations. Indeed, the regulations include an algebraic equation used to determine the amount of utility (and ultimately customer) contribution. Therefore, we find that the PUC’s interpretation of the regulation was correct and consistent with the regulation itself.
Turning to the question of whether the regulation itself is consistent with the statutory delegation of authority, we first note the importance of considering the type of regula
In the Girard School District case, this Court noted the very different review accorded when a mere interpretive rule is at issue:
“An interpretative rule on the other hand depends for its validity not upon a Law-making grant of power, but rather upon the willingness of a reviewing court to say that it in fact tracks the meaning of the statute it interprets. While*631 courts traditionally accord the interpretation of the agency charged with administration of the act some deference, the meaning of a statute is essentially a question of law for the court, and, when convinced that the interpretative regulation adopted by an administrative agency is unwise or violative of legislative intent, courts disregard the regulation. See, e.g., United States v. Cartwright, 411 U.S. 546, 93 S.Ct. 1713, 36 L.Ed.2d 528 (1973); Skidmore v. Swift & Co., 323 U.S. 134, 65 S.Ct. 161, 89 L.Ed. 124 (1944).”
392 A.2d at 263 (quoting Uniontown Area School Dist. v. Pennsylvania Human Relations Comm’n, 455 Pa. 52, 313 A.2d 156, 169 (1973)).
Here, the line extension regulations were adopted pursuant to 66 Pa.C.S. § 1504(1), which vests broad powers in the PUC:
The commission may, after reasonable notice and hearing, upon its own motion or upon complaint:
(1) Prescribe as to service and facilities, including the crossing of facilities, just and reasonable standards, classifications, regulations and practices to be furnished, imposed, observed and followed by any or all public utilities.
In Rohrbaugh, this Court recognized that the rule-making power conferred by this provision is legislative in nature. 727 A.2d at 1085.
The OCA concedes that the PUC was authorized to establish the line extension regulations. The OCA also concedes that the regulations were adopted in a procedurally lawful manner. The OCA disputes, however, whether the regulations were (1) within the delegated power and (2) rea
With respect to substance, in its final order adopting the regulations, the PUC discussed existing appellate cases that had recognized that a utility’s duty to provide line extensions is not unlimited. See 27 Pa. Bull. at 799. It also discussed the need to balance the rights of the utility, existing customers, and individuals seeking main line extensions. Id. Further, the PUC stated that the purpose behind the regulations at issue was to “create a fair, reasonable and predictable economic standard.” Id. Ultimately, in the PUC’s considered view, it was reasonable to require a utility to absorb the entire initial cost of a line extension, but only if the utility could expect that the annual revenue resulting from the extension would equal or exceed the annual cost of the project. If the project would
The PUC’s exercise of its delegated power in this instance reveals no evidence of bad faith, unreasonableness or arbitrariness. In undertaking its evaluation, the PUC did not write upon a blank slate, but with the benefit of years of experience in such matters, including experience with what it deemed an unworkable, burdensome case-by-case approach to extension requests. Moreover, the Commission, though not obliged to adopt regulations consistent with the (intermediate appellate) judicial interpretations that existed in the absence of explicit regulations, Elite Industries, 832 A.2d at 431-32, nevertheless demonstrated an awareness of the existing case law and did not act inconsistently with it. See e.g., Huntingdon, Inc. v. Pennsylvania Public Utility Comm’n, 76 Pa.Cmwlth. 387, 464 A.2d 601, 603 (1983); Lynch, 594 A.2d at 818; Colonial Products Co. v. Pennsylvania Public Utility Comm’n, 188 Pa.Super. 163, 146 A.2d 657, 662 (1958); Ridley Township, 172 Pa.Super. 472, 94 A.2d 168. These cases recognize that, generally, water utilities are required to fund main line extension requests made by bona fide service applicants, but only so long as the project would not burden existing customers nor cause material economic harm to the companies. Although the OCA might prefer that a heavier burden be placed upon the utility,
For the foregoing reasons, we affirm the order of the Commonwealth Court.
. Pursuant to Rule 1952(b) of the Rules of Appellate Procedure, the PUC has filed a certified list of documents in lieu of an official record. Where necessary, we will rely upon the reproduced record supplied by the parties.
. A “bona fide service applicant” is defined in the PUC’s regulations as: "[a] person or entity applying for water service to an existing or proposed structure within the utility's certificated service territory for which a valid occupancy or building permit has been issued if the structure is either a primary residence of the applicant or a place of business.” 52 Pa.Code § 65.1.
. A tariff is defined in the Public Utility Code as "[a]ll schedules of rates, all rules, regulations, practices, or contracts involving any rate or rates, including contracts for interchange of service, and, in the case of a common carrier, schedules showing the method of distribution of the facilities of such common carrier.” 66 Pa.C.S. § 102.
. In 1999, the PAWC filed its Tariff with the PUC pursuant to Section 1501 of the Public Utility Code, 66 Pa.C.S § 101 et seq. Section 1501 provides in pertinent part that, "every public utility may have reasonable rules and regulations governing the conditions under which it shall be required to render service." 66 Pa.C.S. § 1501. Consistently with Section 65.21 of the PUC's regulations, Rule 27 delineates, among other things, the circumstances under which an extension of service will occur, the formula by which the PAWC's required contribution will be calculated, the formula for calculating customer contribution when the costs of the extension exceed the company's contribution, the manner in which customer contributions must be forwarded, and financing for customer contributions.
. The PAWC’s number of 744 potential bona fide service applicants was calculated by taking the total possible customers (701) in the Township and adjusting for the 17 non-residential customers included in that figure. The 17 non-residential customers were deemed to be the equivalent of 60 residential customers. The PAWC thus used the following equation: 701-17 + 60 = 744. Supplemental Testimony of Jay Lucas, at 6.
. Section 65.21(3) provides as follows:
The utility's investment for the line extension shall be based on the following formula, where X equals the utility's investment attributed to each bona fide applicant:
X = [AR-OM] divided by [I + D]; and,
AR = the utility's annual revenue
OM = the utility's operating and maintenance costs
I = the utility’s current debt ratio multiplied by the utility’s weighted long-term debt cost rate
D = the utility’s current depreciation accrual rate
52 Pa.Code § 65.21.
The PAWC calculated its obligation per bona fide service applicant as follows:
Average Annual Revenue: $ 424
Less: Operating and Maintenance Expense: _$ 104
Subtotal: $ 320
Divided by:
Depreciation Rate for 8" mains: 1.08%
Plus: Weighted Cost of Debt: 4.08%
Composite Rate: 0.0516
Company Investment: $6,200
. New water customers would be able to finance their contribution by paying the utility a one-third down payment and then paying the
. The OCA’s number of potential bona fide service applicants was based upon the results of a survey of 701 residents. Of the 530 residents who responded to the survey, 430 (or 81%) stated that they would connect to the public water system so long as customer contribution was not required. The OCA "extrapolated” from this response the inclinations of those who had not responded and then estimated a total of 568 (81% of 701) prospective customers in the Township.
. The OCA calculated PAWC’s obligation per bona fide service applicant as follows:
Average Annual Revenue: $ 424
Less: Operating and Maintenance Expense: $ 104
Subtotal: $ 320
Divided by:
Depreciation Rate for 8” mains: 1.08%
Plus: Weighted Cost of Debt: 1.387%
Composite Rate: 0.02467
Company Investment: $12,971
. Given the limited nature of the issues properly before us, see note 12 infra, the reasons for the ALJ’s crediting PAWC's position in this regard are of no moment.
. The OCA’s petition for allowance of appeal contained the following questions:
1. Whether the Commonwealth Court erred by failing to require a utility to forward the costs of line extension without customer contribution upon a showing of public need?
2. Whether the Commonwealth Court erred in its determination that the line extension regulations were consistent with Section 1501 of the Public Utility Code?
3. Whether the Commonwealth Court erred in finding that the PUC did not abuse its discretion when it required customer contributions even though there had been a demonstration of public need?
In its appellate brief, however, the OCA lists these two additional questions:
4. Whether the PUC's decision that the project was uneconomical was supported by substantial evidence?
5. Whether the PUC erred by dismissing the complaints on the grounds that there were no bona fide applicants?
Brief for Appellant, at 7. The OCA fails to acknowledge that it did not seek review of these questions in its allocatur petition, much less does it explain why it believes it is entitled to consideration of them. Because the additional questions were not the subject of our grant of review, we
We also note that the OCA confuses matters further because its argument is divided into 12 parts with no attempt to relate the dozen parts back to any particular question. Again, we will consider only those points arguably encompassed in the allocatur grant and argued with relevance and specificity in the appellate brief. We caution the OCA that this lack of order and focus alone could warrant dismissal of the appeal as improvidently granted.
. There is no dispute that safe water implicates public safety. See Pa. Const. Art. 1, § 27 ("The people have a right to clean air, pure water ...”); 35 P.S. § 721.2(a)(1) ("An adequate supply of safe, pure, drinking water is essential to the public health, safety and welfare ..."); Hatfield Township v. Lansdale Mun. Auth., 403 Pa. 113, 168 A.2d 333 (1961) (recognizing direct connection between adequate supply of safe water and public health, safety and general welfare).
. The 1992 policy statement was adopted at a public meeting held on August 20, 1992 and published in The Pennsylvania Bulletin on September 19, 1993.
. Section 65.1 of the PUC's regulations provides that a person will not be deemed a bona fide service applicant if any of the following apply:
(i) The applicant is requesting water service to a building lot, subdivision or secondary residence.
(ii) The request for service is part of a plan for the development of a residential dwelling or subdivision.
(iii) The applicant is requesting special utility service.
52 Pa.Code § 65.1. The PAWC contends that utility investment is only required when a bona fide service applicant is requesting an extension of service. If anyone else requests an extension, the utility is not required to contribute to the costs of constructing the lines because there is no public need for service. PAWC Brief, at 17.
. The OCA claims that the PUC obtains its authority to promulgate the regulations from 66 Pa.C.S. § 501. The Commonwealth Court found that the PUC gleaned its authority from Section 1501 of the Public Utility Code. Popowsky 853 A.2d at 1103-04. Although Sections 501 and 1501 certainly support that the PUC has the authority to adopt regulations, the source of this authority comes from Section 1504(a). Rohrbaugh, 727 A.2d at 1084.
. We reject the argument in the dissenting opinion below that the regulations are contrary to the legislative grant because they categorically eliminate public need from the equation. As the PAWC has explained, the distinction the regulations draw between bona fide service applicants and other applicants — i.e., requiring utility investment only when the request is made by a bona fide service applicant, as opposed to a developer, or a secondary home owner, or an applicant requesting special service, 52 Pa.Code § 65.1 — show that public need is
. We agree with the Commonwealth Court that Ridley Township, properly read, does not require utilities to extend service, even if it is not profitable, so long as they receive an overall return on its entire operations. Rather, Ridley Township is one of the many intermediate appellate cases that generally posited that utility companies were obliged to provide the initial capital required for line extensions unless doing so would subject the company to "unreasonable expenditures” or would “unduly burden the public.” Ridley Township, 94 A.2d at 171. Furthermore, Ridley Township was decided prior to the promulgation of the line extension regulations, which now control. If the regulations are valid, Ridley Township is no basis upon which to upset them.
. We also are unpersuaded by the OCA’s argument that the revenue the PAWC could expect in future rate increases should require it to forward the entire cost of mandated line extension projects. In addition to the fact that this is a policy argument which does not prove the unreasonableness of the agency’s regulatory scheme, the argument confuses two separate costs to utilities: costs associated with line extension and costs associated with regular service. The PAWC is subject to separate regulations for the establishment and increases of its rates. See 52 Pa.Code § 53.1 et seq. These requirements are separate and apart from the line extension regulations. Rates are intended to compensate the utility for its ongoing service, i.e., providing regular water service, and are not required to be viewed as containing a component which compensates the provider for unrelated projects or expenditures, such as line extensions for the benefit of new customers.