DocketNumber: Appeal, No. 2835 C.D. 1980
Judges: Blatt, MacPhail, Mencer, Palladino
Filed Date: 12/16/1981
Status: Precedential
Modified Date: 10/18/2024
Opinion by
Brockway Glass Company (Brockway) appeals here from an order of the Pennsylvania Public Utility Commission (PUC) entered October 15, 1980, which adopted the Initial Decision and Ruling on Exceptions of the Administrative Law Judge (ALJ) and dismissed the petitioner’s complaint against West Penn Power Company (West Penn). We affirm.
Brockway, an industrial customer of West Penn at several locations, has been taking electric service at its Plant No. 11 in Washington, Pennsylvania since acquisition of that plant in 1964, at which time it succeeded to the then-existing electric service agreement for that plant. Brockway and West Penn subsequently executed three new agreements: on October 10, 1965, September 8,1967 and May 3,1974, each of which was based upon a different West Penn rate schedule
On or about September 18, 1979,
Our scope of review in rate making cases is limited to a determination of whether or not constitutional rights have been violated, or if an error of law has been committed, or whether or not the findings, determinations or order of the PUC are supported by substantial evidence. Zucker v. Pennsylvania Public Utility Commission, 43 Pa. Commonwealth Ct. 207, 401 A. 2d 1377 (1979).
Broekway contends that Section 1303 of the Public Utility Code (Code), 66 Pa. C. S. §1303, requires a customer, whose service requirements have changed subsequent to execution of a service agreement and who has given notice to the utility of the changed conditions, to have its future billings computed at the rate most advantageous to the customer’s realigned service requirements. Broekway’s reliance on this Section of the Code, however, is misplaced.
Section 1303 of the Code provides:
No public utility shall, directly or indirectly, by any device whatsoever, or in anywise, demand or receive from any person, corporation,*242 or municipal corporation a greater or less rate for any service rendered or to be rendered by sncb public utility than that specified in the tariffs of such public utility applicable thereto. The rates specified in such tariffs shall be the lawful rates of such public utility until changed, as provided in this part. Any public utility, having more than one rate applicable to service rendered to a patron, shall, after notice of service conditions, compute bills under the rate most advantageous to the patron. (Emphasis added.)
Tariffs, of course, can include schedules of rates, and all rules, regulations, practices or contracts involving rates and have the force of law and are binding on both the utility and its customer. Behrend v. Bell Telephone Company, 242 Pa. Superior Ct. 47, 363 A.2d 1152 (1976). And, in Bell Telephone Co. v. Pennsylvania Public Utility Commission, 53 Pa. Commonwealth Ct. 241, 244, 417 A.2d 827, 828-29 (1980), this Court construed Section 1303 of the Code and stated that.“[t]here can be no lawful rate except the last tariff published as provided by law.... Further, it is well established that in the absence of an exception by the Commission, a public utility may not charge any rate for services other than that lawfully tariffed. ...” (Citations omitted, emphasis in original.) It is well-settled in Pennsylvania that:
Contracts for the service of utilities are presumed to have been made subject to the police power of the state ..., and it is beyond the power of the contracting parties to fix rates or provide for service permanently. . . . [T]he Public Utility Law supplant[s] any agreement in so far as rates are involved between the consumer and the utility. (Citations omitted, emphasis added.)
Brockway asserts that the requirement of a one-year notice of cancellation in addition to a four-year initial term of service operated as an unlawful penalty, and, further, that the said requirement was a term of adhesion. Public utility rates, of course, are required to be just and reasonable, 66 Pa. C. S. §1301, and, where a customer is heard to complain concerning a proposed change in rate, the burden of proof is upon the public utility to show that the proposed rate is just and reasonable. Where the complaint involves an existing rate, however, the burden then falls upon the customer to prove that the charge is no longer reasonable. ZucJcer. Brockway did not meet its burden here. The record indicates that in each of its successive agreements Brockway obtained a new and different rate schedule which was economically compatible with its then-current electric service requirements. In 1974 it opted for Rate Schedule 47 with its one-year notice of cancellation provision to apply after expiration of the intial four-year term and it continued under that schedule without complaint until it curtailed its operations at Plant No. 11 in 1980. Brockway submitted virtually no evidence at the hearing as to the unreasonableness of the cancellation provision per se, but ad
Tariff limitations have been upheld by our courts, which have recognized “the power vested in the PUC to evaluate the reasonableness of tariffs or regulations filed with it and to determine whether the provisions therein are compatible with the code and policies of the commission and consistent with its regulatory scheme.” Behrend, 242 Pa. Superior Ct. at 74-75, 363 A.2d at 1166. Rate Schedule 47 had met the test of reasonableness at rate proceedings on at least two previous occasions when it had been submitted by West Penn as a proposed rate, and Brockway has now failed to meet its burden of demonstrating that Rate Schedule 47 is now unreasonable.
Brockway does contend, and rightly, that the PUC was incorrect when it stated that “[w]here there is an outstanding contract, based on reasonable tariff provisions, it is the time of the contract that governs the application of Section 1303, and not the time of use.” (Emphasis in original.)
Order
And Now, this 16th day of December, 1981, the order of the Pennsylvania Public Utility Commission in the above-captioned matter is affirmed.
The record indicates that Thomas L. Anderson, Jr., the author oí the September 18, 1979 letter from Broekway, succeeded in recalling the letter from West Penn pending Brockway’s public announcement on October 1, 1979 of its intention to terminate operations at Plant No. 11. Anderson, by letter of October 1, 1979, then reconfirmed Brockway’s intention ,to shut down Plant No. 11 as of January 1, 1980. The Administrative Law Judge found September 18, 1979 to be the controlling date.
Reproduced Record at p. 112a.