DocketNumber: 2110 C.D. 1993
Judges: Doyle and Smith, Jj., and Kelton, Senior Judge
Filed Date: 11/5/1993
Status: Precedential
Modified Date: 10/19/2024
Lower Paxton Township, West Hanover Township, members of the townships’ Boards of Supervisors, and Waste Management of Central Pennsylvania, a division of Waste Management of Pennsylvania, Inc., (Waste Management) (collectively Appellants) appeal from the August 31, 1993 final order of the Dauphin County Court of Common Pleas denying Appellants’ post-trial motions and confirming the trial court’s July 27, 1993 decree nisi permanently enjoining the townships from executing a five-year waste hauling contract entered into with Waste Management. The broad question raised for this Court’s review is whether the trial court erred in ruling that the townships improperly rejected a disappointed bidder’s public contract bid for failure to comply with bidding require
I.
In March 1993, the townships agreed to jointly seek bids for a waste hauling and recycling contract for a five-year period to commence July 2, 1993. Prior to a finalized drafting of the invitation to bid, the townships held two pre-bid conferences with potential bidders to discuss the requirements for bids. The finalized invitation to bid was officially advertised in March 1993 and sent to interested bidders. Among the requirements of the invitation to bid was a provision that all bids be submitted by 4:00 p.m. on April 19,1993. Representatives of both townships were to open the bids that evening to initially determine the amounts of each bid.
As of the deadline, the townships received eight bids for the contract. Upon bid opening, the townships determined that the three lowest bidders were, in succession, Wayne-Pike Sanitation Company (Wayne-Pike), York Waste Disposal, Inc. (York Waste), and Waste Management. Following the reading of the bids, the townships, through the efforts of the staff attorney for Lower Paxton Township, began to review the bids in detail to ascertain if the bidders had complied with mandatory requirements of the invitation to bid. Review of the Wayne-Pike bid revealed several defects which led to rejection of that bid and no subsequent action by Wayne-Pike. The York Waste bid was $8,605,740 for the five-year term and Waste Management’s was $9,110,244.
Upon review of the York Waste bid, it was determined that York Waste failed to comply with the mandatory requirements of Section 3.1 of the invitation to bid, which required the bidder to furnish a letter from a recycling center certifying the center’s capability to accept and market all recyclables over the full term of the contract. York Waste’s bid provided only that the designated recycling facility had the capability to accept and market recyclables from the townships and did not certify that it could do so for the full term of the contract.
Following the townships’ opening and review of the bids, the vice president for York Waste became aware of the missing assets page and informed staff counsel that he would fax the missing information for consideration. Staff counsel responded that this information could not be considered since the bids had already been opened. York Waste nevertheless faxed the page in question. Upon review of Waste Management’s bid, it was determined that the bid was responsive in all respects, and this determination has not been challenged in the present action.
On May 12, 1993, staff counsel sent his findings to the Board of Supervisors for both townships detailing the proposed amounts of the bids, along with counsel’s conclusions regarding rejection of the Wayne-Pike and York Waste bids and recommendation for acceptance of the Waste Management bid. The Lower Paxton Township Board of Supervisors ultimately voted three to one to award the contract to Waste Management. The Board of Supervisors of West Hanover Township similarly decided, by a vote of three to one, to approve awarding the contract to Waste Management. The townships thereafter notified Waste Management that it had been awarded the contract.
On May 19, 1993, Robert I. Kimmel filed an action in equity with the trial court along with a motion for a preliminary injunction, and William Hornung was permitted to intervene without opposition on June 2, 1993 (Kimmel and Hornung, collectively Appellees). Following a June 2, 1993 hearing, the trial court issued a preliminary injunction against the townships enjoining execution of the contract with Waste Management. On June 22, 1993, the trial court entered an order
II.
On appeal from an order granting permanent injunctive relief, the standard of review is whether the trial court, in entering the final decree, abused its discretion or committed an error of law; the test is not whether there are any reasonable grounds for the action of the court below, as is the case in the review of preliminary injunctive relief. Sparkes v. Wright, 377 Pa.Superior Ct. 374, 547 A.2d 415 (1988). In reviewing the townships’ actions, the trial court was limited to a determination of whether there was a manifest abuse of discretion or a purely arbitrary execution of the agency’s duties or functions, American Totalisator Co. v. Seligman, 489 Pa. 568, 414 A.2d 1037 (1980); and the court could grant the extraordinary relief of permanent injunction only where the rights of the plaintiff were clear and free from doubt and the harm which the plaintiff sought to be remedied is great and irreparable. Mann-Hoff v. Boyer, 413 Pa.Superior Ct. 1, 604 A.2d 703, appeal denied, 531 Pa. 655, 613 A.2d 560 (1992), Courts will not review the action of governmental bodies or administrative tribunals involving acts of discretion in the absence of bad faith, fraud, capricious action, or abuse of power. Karp v. Redevelopment Authority of the City of Philadelphia, 129 Pa.Commonwealth Ct. 619, 566 A.2d 649 (1989), appeals denied, 527 Pa. 619, 620, 590 A.2d 760 (1990).
The trial court held that the townships’ stated reasons for rejecting York’s bid were “extremely technical,” and that the townships have discretion to determine only whether a bidder is responsible and may only reject a bid for “material discrepancies.” In reaching this conclusion, the trial court
The trial court also erroneously relied upon Metropolitan Messenger Service v. Commonwealth, 12 Pa.Commonwealth Ct. 609, 317 A.2d 346 (1974). In that case, Metropolitan Messenger, which was the second-lowest bidder, sought to have a contract award to Purolator Courier Corporation declared invalid. The invitation to bid required companies to submit a lump sum total bid and a calculation of the underlying per-stop price for check delivery services. Purolator complied with the bidding requirements by submitting the mandatory financial information, and submitted the lowest bid, despite Metropolitan’s allegation that Purolator’s method of computing the bid failed to comply with the bid requirements. In sustaining Purolator’s preliminary objections, this Court held that the critical issue is not the form of the calculation, but that the required information was in the bid. Since Purolator’s bid provided the requisite cost data, and since
Despite Appellees’ assertions to the contrary, Metropolitan Messenger in no way requires that municipalities waive technical variations from bid specifications, and indeed no support can be found for the trial court’s or Appellees’ distinction between technical and material defects. In Metropolitan Messenger, the parties’ bids complied with the bid requirements and the agency appropriately awarded the contract to the lowest bidder, a situation not present here. Moreover, Metropolitan Messenger neither addresses nor condones post-bid opening submissions.
The township supervisors also properly refused to accept York Waste’s attempt to cure its bidding defects after the bids were opened. The law is clear that a defective bid cannot be remedied once the bids have been opened. Canteen Co.; Nielson. There is no dispute that York Waste faxed the missing assets page to the townships after the bids were opened. Therefore, the township supervisors were without authority to consider the faxed information as being part of the original bid package. In Nielson, this Court held that memos supplied by a contractor after bids were opened could not be considered in an attempt to cure a deficiency in the bid proposal.
A further error was the trial court’s determination that the townships had discretion to waive York Waste’s “technical” bid deficiencies and should have exercised that discretion.
York Waste’s bid also failed to comply with the bid requirements regarding recycling certification. The invitation to bid required all bidders to supply a letter certifying a recycling center’s capability to accept and market recyclables from the townships over the full term of the contract. In its bid, York Waste’s recycling letter failed to certify its access to a recycling center capable of accepting and marketing such waste and failed to specify that it could do so for the full term of the contract. The trial court excused this lack of compliance based, in part, on its finding that staff counsel had independent knowledge that York Waste owned its own recycling facility and also knew that York Waste’s bid package was for the full five-year term of the contract. In so holding, the trial court clearly disregarded the mandate that bids must strictly follow bidding requirements. See Nielson.
III.
In the alternative, Appellees contend that the conduct of H. Michael Liptak, chairman of the Board of Supervisors of Lower Paxton Township, and Richard N. Koch, a member of that board, provides an additional and independent basis for this Court to affirm the trial court’s opinion. The trial court found that Liptak was the owner and CEO of Highway-Equipment Supply Company (HESCO), a company in the business of selling heavy construction equipment; at the time of the bidding process at issue, HESCO sold and/or leased equipment to Waste Management; and during board meetings, Liptak did not inform the other supervisors of his business relationship with Waste Management. Liptak however did not vote when the Board of Supervisors voted to award the contract to Waste Management. The court further found that Koch was employed as an engineer for Gannett Fleming, a consulting firm doing business with Waste Management.
Appellees argue that Liptak’s and Koch’s conduct was in violation of Section 802(f) of the Code, 53 P.S. § 65802(f), and that their being subject to civil and criminal penalties provides a basis for invalidating the award of the contract to Waste Management. Section 802(f) provides only that any township official who has direct or indirect interest in a township contract must so inform the other supervisors and refrain from voting on the expenditures. In the event of any violation, the remedies include damages, ouster from office, and fines, all of which are directed at the individual involved, not at the underlying contract. In addition, Appellees cite no authority for the contention that violation of Section 802(f) is grounds for invalidation of the contract.
The trial court properly found no evidence of collusion or ulterior motive on the part of either Liptak or Koch in awarding the contract to Waste Management. In rejecting arguments that a township’s supervisors’ acceptance of a
Because the trial court committed an error of law, its decision must be reversed and the award of the contract to Waste Management reinstated.
ORDER
AND NOW, this 5th day of November, 1993, the order of the Court of Common Pleas of Dauphin County is reversed and the award of the waste-hauling contract to Waste Management is reinstated.
. Staff counsel also noted other defects in the York Waste bid, including an incomplete equipment statement, obliterations on its route map, and a failure to affix a corporate seal. However, counsel concluded that it was not necessary to address these other defects because of the significance of the missing assets page and recycling certification defects.
. An obvious purpose of the competitive bidding process is to also guard against favoritism, extravagance, fraud and corruption in the awarding of municipal contracts. Conduit & Foundation Corp. v. City of Philadelphia, 41 Pa.Commonwealth Ct. 641, 401 A.2d 376 (1979).
. Section 1.5 of the invitation to bid required each bidder to furnish with the bid and in the same sealed envelope a full and complete sworn financial statement showing the bidders' assets and liabilities as of the end of 1992. Section 1.18 of the invitation to bid further provides that "[b]ids or proposals which contain erasures, alterations, conditional bids, omissions or irregularities of any kind may be rejected by the Townships at their option as not complying with the bidding documents."
. This Court similarly rejects Appellees' contention, relying upon Kratz, that a low bid for a public contract cannot be rejected unless the municipality has made an actual investigation into the bidder's financial capacity and has, if necessary, afforded the bidder opportunity to provide evidence or information to aid in a determination of responsibility. Besides not being a case in which the bid failed to comply with bidding requirements, Kratz held that such an investigation was necessary where the city declined to award the contract to the lowest bidder because of unfounded and unsupported concerns over the quality of materials and the difficulty of performance of the contract. This is clearly not the present situation.
. Section 1.19 of the invitation to bid states that the townships may waive technical defects if, in their judgment, the best interests of the townships shall so require. Even were this Court to validate the trial court’s distinctions, its decision nonetheless cannot be upheld. The term "technical” implies something that is immaterial, not affecting substantial rights, or without substance. Black’s Law Dictionary, 4th Ed. (1968). Neither the failure to comply with mandatory requirements regarding financial data nor to provide a full-term recycling certification can be considered "technical” defects in York Waste’s bid.
. In Canteen Co., the invitation to bid directed that bids "offer to pay a guaranteed annual fee or 20% of the gross revenue derived from the concession [five-year vending machine concession at the Philadelphia International Airport] whichever sum shall be greater.” The appellant’s bid was rejected as invalid because it included language excepting the bidder from the guaranteed fee in the event of sales restrictions due to strike, act of God or war or riot.