Judges: Friedman, McGinley, Silvestri
Filed Date: 4/20/1994
Status: Precedential
Modified Date: 11/13/2024
Somerset Rural Electric, Inc. (Somerset) appeals an order of the Pennsylvania Public Utility Commission (PUC) which granted summary judgment in favor of the Pennsylvania Electric Company (Penelec), dismissed Somerset’s exceptions from the initial decision of an administrative law judge (ALJ) and ordered that Somerset be prohibited from providing electric service in the Borough of Jennerstown (Jennerstown), Somerset County.
On May 9,1991, Penelec filed a petition for declaratory order (petition) with the PUC seeking an order declaring its exclusive right to furnish retail electrical service in Jenners-town and directing that Penelec be exclusively authorized to furnish electric service to the Jennerstown Speedway (Speedway).
In its petition, Penelec made the following averments of fact. Pursuant to a certificate of public convenience dated September 8, 1930 and an ordinance enacted by Jenners-town on June 13,1930, Penelec has furnished retail electric service to various customers in Jennerstown. It has furnished retail electrical service to Speedway since May of 1968. On June 19, 1990, Speedway requested additional retail electrical service from Penelec to its facility. On July 12, 1990, Penelec gave Speedway a cost estimate of approximately $12,000 to $14,000 for the additional service.
Penelec averred that Somerset, a “rural electric cooperative corporation,” which furnishes retail electric service to its members in portions of Somerset County, began providing retail electrical service for the first time in Jennerstown to Speedway in 1990.
On June 3, 1991, Somerset filed a motion to dismiss Penelec’s petition arguing that the PUC lacked jurisdiction over it. The PUC denied Somerset’s motion to dismiss on August 29, 1991, and ordered that Penelee’s petition be assigned to an ALJ.
Thereafter, Penelec filed a motion for summary judgment with the ALJ again asserting the arguments made in its petition and asserting that, as a matter of law, it was entitled to judgment. Somerset, in its answer to Penelec’s summary judgment motion, again asserted the PUC’s lack of jurisdiction over the matter.
On April 17,1992, the ALJ issued its initial decision granting Penelec’s motion for summary judgment.
On appeal,
As previously noted, Somerset, as an electric cooperative, is subject to the Cooperative Law. Somerset cites several provisions of the Cooperative Law as support for its assertion that the PUC lacks jurisdiction over it. Section 7334, 15 Pa.C.S. § 7334, provides:
Except as provided in Subchapter C (relating to unincorporated area certified territory), all electric cooperative corporations subject to this chapter shall be exempt in*1252 any and all respects from the jurisdiction and control of the Pennsylvania Public Utility Commission.
Subchapter C contains nine sections, 15 Pa. C.S. §§ 7351-7359, the first of which, § 7351, provides as follows:
(a) General rule. — This subchapter shall apply only to the establishment of boundaries of certified territory between retail electric suppliers where one supplier is an electric cooperative corporation and the other supplier is subject to the jurisdiction of the Pennsylvania Public Utility Commission for rates, terms and conditions for electric service.
Somerset argues that the PUC only has jurisdiction over electrical cooperatives where Subchapter C applies. Somerset asserts that Subchapter C does not apply here because Subchapter C applies only to the PUC’s drawing boundary lines within certified territories and Jennerstown is not within a certified territory.
The PUC looked to Section 7358 of Sub-chapter C of the Cooperative Law as providing authority for its exercise of jurisdiction in this matter. Section 7358 provides as follows:
Upon proceedings brought by an interested person or by action of the Pennsylvania Public Utility Commission, the commission shall have the jurisdiction to enforce compliance with this subehapter and shall have jurisdiction to prohibit the furnishing of retail electric service by any retail electric supplier19 1 except in its certified territory or territories or where lawfully serving and, in connection with the enforcement and prohibition, to exercise all powers granted by this subehapter or otherwise to the commission.
Specifically, the PUC relied upon Section 7358 granting it, in addition to jurisdiction to enforce Subchapter C, “jurisdiction to prohibit the furnishing of retail electric service by any retail electric supplier [here Somerset] except in its certified territory or territories or where lawfully serving.” (Emphasis added).
As noted, the PUC’s determination was based upon its conclusion that neither Speedway, nor any other entity within Jennerstown was eligible for membership in Somerset and that because Somerset, as an electrical cooperative, could only provide service to its members that its service to Speedway was improper.
Section 7321(a)(1) of the Cooperative Law clearly provides that “[e]ach electric cooperative corporation shall have power ... to furnish ... electric energy to its members only-” (Emphasis added). Section 7324 of the Cooperative Law, entitled, “Qualifications of members” provides:
All persons in rural areas proposed to be served by an electric cooperative corporation, who are not receiving central station service, shall be eligible for membership in the corporation....
Here, the ALJ specifically found, as accepted by the PUC, that Speedway was receiving “central station service” from Penelec. Al
The term “central station service” is used in the REA Act, see e.g. 7 U.S.C. § 902, to describe electric service from a central generation facility that serves numerous consumers. This is distinguished from, for example, electricity available only from small-scale, single-farm generators.
See ALJ’s Initial Decision at R.R. 160a. Based upon said review, the ALJ thus concluded, as noted herein above, that Penelec’s service within Jennerstown was “central station service” as set forth in the Cooperative Law and that pursuant to Section 7324, Somerset could not lawfully serve within Jenners-town.
Our review of the entire record in this matter, in accordance with our scope of review, reveals that the PUC’s did not violate constitutional rights, err as a matter of law or issue findings that were not supported by substantial evidence.
Because we conclude that the PUC’s determination that Somerset was not lawfully providing service within Jennerstown was correct, we hold that its exercise of jurisdiction was proper as specified in Section 7358 of the Cooperative Law. Accordingly, we will affirm the PUC’s order.
ORDER
AND NOW, this 20th day of April, 1994, the order of the Pennsylvania Public Utility Commission dated December 21, 1992 is affirmed.
. Subsequent to receiving Penelec’s cost estimate for its expanded service, Speedway went to Somerset, which, in turn agreed to provide Speedway with electrical service.
. There is no dispute over whether the Borough
. Although the ALJ granted Penelec’s motion for summary judgment and prohibited Somerset from providing service in Jennerstown, the ALJ declined to declare that Penelec had the exclusive right to provide service in Jennerstown as requested by Penelec. (ALJ's Initial Decision, R.R. 169a).
. § 7321(a)(1) provides, in relevant part:
(a) General rule. — Each electric cooperative corporation shall have power;
(1) To generate, manufacture, purchase, acquire and accumulate electric energy and to transmit, distribute, sell, furnish and dispose of such electric energy to its members only....
. § 7324 of the Cooperative Law, entitled "Qualifications of members, provides in part:
AH persons in rural areas proposed to be served by an electric cooperative corporation, who are not receiving central station service, shall be eligible for membership in the corporation. ...
. The ALJ made the following relevant conclusions of law;
3. The term “central station service” in the Cooperative Law means "service from a central generation facility that serves numerous consumers.”
4. The inhabitants of the Borough of Jenners-town have been receiving "central station service” from Pennsylvania Electric Company since 1949.
(R.R. 170a).
. Our scope of review is limited to determining if a party's constitutional rights have been violated or if an error of law was committed and to ascertaining that all necessary findings of fact are supported by substantial evidence. Valley Rural Cooperative, Inc. v. Pennsylvania Public Utility Commission, 143 Pa.Commonwealth Ct. 131, 598 A.2d 627 (1991).
. There is no dispute here that Jennerstown is not within a certified territory.
. The term "retail electric supplier” is defined in Subchapter C, Section 7352, as follows:
Any person, exclusive of a municipal corporation, engaged in the furnishing of retail electric service. The term shall apply only to a retail electric supplier which is an electric cooperative corporation and to a retail electric supplier which is subject to the jurisdiction of the commission for rates, terms and conditions for electric service and has a mutual boundary in an unincorporated area with an electric cooperative corporation.
.As noted hereinabove, we are not dealing with the whether Somerset is attempting to provide service within a "certified territory” as it is undisputed that Jennerstown is not within such a territory.