DocketNumber: Appeal, No. 34
Citation Numbers: 57 Pa. Super. 418, 1914 Pa. Super. LEXIS 214
Judges: Head, Henderson, Kephart, Orlady, Porter, Rice, Trexler
Filed Date: 7/15/1914
Status: Precedential
Modified Date: 10/19/2024
Opinion by
This action is scire facias sur mechanic’s lien. The plaintiff recovered a verdict and judgment in the court below for the full amount of his claim, and the defendant appeals. The opinion of the learned judge of the court below, in overruling the motion of the defendant for judgment non obstante veredicto, which will appear in the report of the case, renders extended discussion of the questions unnecessary. The only question of fact
The first specification avers that the court erred in the admission in evidence of plaintiff’s books of original entry. No objection was made to the admission of the books in evidence at the time they were offered, and after some discussion counsel for the defendant said: “With the exception of the heading, and with the privilege of auditing the account later, I have no objection to its going in in that way, to shorten it up.” The books were made the subject of extended examination and cross-examination. No objection was made to them because of the manner in which they were kept. The only objection made to the books at the trial was that the heading of the account, when first opened had been “George J. Painter, North Main Street, Van Luven Building.” After a time the charges were made against the “Bohemian Theatre.” The oral testimony explained that the building had first had no distinct name and was known as the “Van Luven Building”; that later it was given the name of the “Bohemian Theatre,” and. after the building had been thus named the charges
The claim filed averred that the materials were furnished and the work done under an oral contract between the plaintiff and George 14. Painter, who was averred to be the authorized agent of the defendant, 'providing that the claimant should furnish labor, materials, electrical supplies, etc., for the complete electrical equipment of said building and for the electrical work and equipment actually used in the construction and erection thereof for the price or sum of $475; that under this contract labor, material and equipment to the amount of $441.68 had actually been furnished in the erection and construction of said building, and that defendant was entitled to credits amounting to $65.80, leaving a balance of $375.88. Attached to the claim was a bill of particulars giving in detail the items of material and labor furnished, with the date and value of each. The claim thus showed upon its face that it was alleged to be founded on an oral contract requiring the plaintiff to furnish all the labor and material for the electrical equipment of the building for a fixed sum, viz., $475; it also showed that the plaintiff had furnished labor and material,, under the contract, to the value of only $441.68. The defendant ignored this ambiguity on the face of the lien, did not move to .strike off the claim, and proceeded to a trial on the merits. The plaintiff testified that he furnished all the
The fourth specification of error refers to the refusal of the court to strike out certain evidence. No exception was taken to that ruling and the specification of error must for that reason be overruled. If the jury believed the testimony of the plaintiff the defendant was liable on the oral agreement to pay $475 for the electrical work upon the building, the work had been almost completed when Painter left and the defendant changed his purposes with regard to the building; the defendant accepted the work which had been done, retained and has used it, and the difference between the $441.68, which plaintiff asserts he ought to have for the work done, and $475, the amount which plaintiff would have been entitled to receive if the work had been completed, fairly represents the value of the work omitted. The defendant distinctly testified that the fixtures on the top floor, the only work omitted, were
The judgment is affirmed.