DocketNumber: Appeal, No. 105
Citation Numbers: 73 Pa. Super. 19, 1919 Pa. Super. LEXIS 166
Judges: Head, Henderson, Keller, Orlady, Porter, Trexler, Williams
Filed Date: 10/13/1919
Status: Precedential
Modified Date: 11/14/2024
Opinion by
The plaintiffs in this action seek to recover a balance alleged to be due upon a contract for the erection of a building, for additional work in erecting shelving and counters in one of the storerooms of the building and for work done upon other buildings of the defendant. The contract for the erection of the building was in writing and required the building to be finished by June 1, 1907. The principal question in controversy at the trial arose under the following covenant, viz: “Should the contractors fail to finish the work at or before the time agreed upon, they shall pay to or allow the proprietor, by way of liquidated damages, the sum of ten dollars per diem for each and every day thereafter the said work shall remain incomplete.” It is admitted on behalf of the plaintiffs that, in view of the character and extent of the building operations, the amount thus stipulated to be paid in case the contractors failed to finish the building at the time
The court in that portion of the charge which is the subject of the second specification of error charged the jury as follows: “The plaintiff, having entered into this contract, would be required to finish and complete the structure on or before the date named in it, provided there was not any permission given him to delay the work by the defendant or by his agent, namely, the architect, or through weather conditions which would make it absolutely impossible for him to do the work.” If the limitation upon the liability of the plaintiff for delay, as thus stated, had been confined to that part of the instruction which referred to such delay as resulted from the action of the defendant or his agent, the architect, the instruction would not have been so clearly erroneous as to warrant a reversal, for the jury would probably then have understood that the plaintiff was only to have the benefit of such delay as resulted from the action of the defendant or his agent. It would, however, have guarded against misunderstanding by the jury if the court had instructed them that, even if the defendant had to some extent delayed the operation the plaintiff was only entitled to the delay which resulted from that cause. “For the fact 'that plaintiff was obstructed by defendant in strict performance did not absolve it from further effort to speedily perform. When the cause for the delay, the conduct of the defendant, ceased, the obligation to speedily finish was at once reimposed with all its force on plaintiff, and failure then to perform within a reasonable
The instruction complained of in the first specification of error certainly tended to leave upon the minds of the jury the impression that the plaintiff was only to be held answerable for such delay as resulted from his negligence or carelessness. He had covenanted that in case of delay he would pay at a certain rate per diem. The appliances and the number of men which he would employ in the undertaking were for him to determine; if there was delay he must respond according to his contract, unless that delay was caused by the defendant or his agent. The first specification of error is sustained.
The contract contained a covenant that nothing done under the contract was to be considered as extras unless agreed upon in writing and signed by the owner and contractor and certified to by the architect. The appellant
The judgment is reversed and a venire facias ide novo awarded.