DocketNumber: Appeal, No. 27
Citation Numbers: 70 Pa. Super. 42, 1918 Pa. Super. LEXIS 164
Judges: Head, Henderson, Kephart, Orlady, Porter, Trexler, Williams
Filed Date: 7/10/1918
Status: Precedential
Modified Date: 11/14/2024
Opinion by
Plaintiff agreed to deliver within six weeks 96,000 feet of white oak .plank to be used in replacing the floor of a county bridge. Three carloads were delivered within the time specified, eight thereafter, and there remained a deficit of 8,000 feet which defendant had to purchase elsewhere. Defendant claims that by reason of the delay in furnishing the plank and the failure to provide the entire amount contracted for he suffered damages. The lumber had been resold to one Pettit who- had the contract for putting the floor on the bridge and the vendor knew that such was the case and that defendant was under bond to the county commissioners to see that Pettit would complete the job according to contract. Time was of the essence of the contract. Special damages were claimed in the affidavit of defense. The jury gave the defendant a certificate and the question before us is whether the items of set-off presented by the defendant were properly admitted.
The defendant and Pettit partially settled their differences by the allowance of $200 to Pettit as compensation for nondelivery of the plank according to contract. The
The defendant presents a bill of $100 by way of set-off for expenses incurred in going to Williamsport, Scranton and other lumber centres in Pennsylvania in the attempt to find out where he could get plank to take the place of those which the plaintiff had failed to furnish. The tardiness of the plaintiff was continually met by requests on the part of the defendant to hurry up the delivery of the plank. The time of delivery expired on November 20th, when only three carloads had been delivered. On January 4,1913, defendant wrote to plaintiff telling him that if he did not hear from him by next mail with definite information he would go into the market and buy the plank and charge him with the difference. January 18th he asked the plaintiff the question, “Shall we go into the open market and buy the balance of the oak at once?” January 28th he again wrote plaintiff that if he did not hear from him by return mail he would tell the contractor to go ahead and do what he thought was best under the circumstances and on February 5th, he definitely cancelled the order. In the interval between the expiration of the time fixed by the contractor and the final cancellation of the order, eight additional oars had been shipped and accepted by the defendant. All these trips above referred to were taken before the cancellation and during the time when the defendant, was still urging the plaintiff to supply the balance of
The judgment is reversed and a venire facias de novo is awarded.