DocketNumber: Appeal, 199
Judges: Keller, Cunningham, Bald-Rige, Stadteeld, Bhodes, Hirt, Kenworthey
Filed Date: 4/23/1941
Status: Precedential
Modified Date: 10/19/2024
Argued April 23, 1941. This was an action in assumpsit against the surety on a contractor's bond given in connection with the *Page 10 improvement of a state highway, conditioned for the prompt payment by the contractor of "all sums of money which may be due any person . . . . . . for all material furnished and labor supplied or performed . . . . . . in connection with the prosecution of the work, whether or not the said material or labor enter into and become component parts of the work or improvement contemplated", in conformity with the provisions of the Act of July 12, 1935, P.L. 705, amending section 13 of the Act of May 31, 1911, P.L. 468. See also Act of June 22, 1931, P.L. 881.
The real point at issue on the trial was whether the contract between the use plaintiff and the highway contractor — which was entirely oral — was for the hiring together by the latter from the former of two trucks and drivers at $1.90 per hour for each truck and driver, (See Phila. to use v. Stange,
The testimony was rather vague and in some respects contradictory, but it would have supported a finding either way if the jury had arrived at their verdict after a charge adequately defining the issues involved. But the charge of the court was so inadequate and so utterly lacking in its presentation of the issue or issues of fact to be determined by the jury, that it gave the latter no help whatever in arriving at their verdict and left the *Page 11 jury without compass or direction to guide them. A new trial will have to be had in consequence.
Judgment reversed, and a new trial awarded.