DocketNumber: Appeal 17
Citation Numbers: 156 A. 617, 102 Pa. Super. 97, 1931 Pa. Super. LEXIS 136
Judges: Baldbige, Trexler, Keller, Linn, Gawthrop, Cunningham, Baldrige, Drew
Filed Date: 3/13/1931
Status: Precedential
Modified Date: 10/19/2024
Argued March 13, 1931. The appellant, a sub-contractor, filed a mechanic's lien against the real estate of the Gettysburg National Bank, the appellee. The lien was stricken off by the court on the application of the owner for the reason that it did not set forth, in detail, the kind and amount of materials furnished, the nature and kind of work done, and when the materials were furnished and the work was done. From that order, this appeal was taken.
Paragraph 6 of Section 11 of the Mechanics' Lien Act, approved June 4, 1901, P.L. 431, as amended by the Act of April 17, 1905, P.L. 172, requires the claimant to set forth in his lien, a detailed statement of the kind and character of the labor or materials furnished, or both, and the prices charged for each thereof, when the contract is with other than the owner, or not for an agreed sum. The provisions of the Act of 1901, as amended, are substantially in the same language as the Act of April 12, 1836, P.L. 695; hence the decisions under the earlier statutes are still applicable.
The mechanic's lien filed by the appellant sets forth as follows:
"On January 21, 1928, claimant received a written order from the contractor, the said Simons, Brittain and English, Inc., for the furnishing and installing of a complete Duplex Grade ``A' cable in concrete vault alarm system complete in every respect with the exception that no conduits were to be installed by claimant, and also to include in the vault alarm system a complete daylight holdup system with eleven outlets for tellers and seven button stations on desks. The price for said work was $1,500, which is fair, reasonable and market price for the labor done and performed and the materials furnished and supplied, and which are the same prices that the contractor promised and agreed to pay the claimant therefor. A true and *Page 100 correct copy of said written order is annexed hereto, made part hereof and marked Exhibit ``A'."
The written order referred to states that the claimant is to "furnish and install complete Duplex Grade ``A' cable in concrete vault alarm system," etc., as set forth in the body of the claim.
Although the language of the statute does not expressly say so, a distinction has long been recognized between a claim of a contractor and a claim of a sub-contractor. In the former case, the work done and materials furnished under a special contract with the owner for a stipulated sum need not be itemized as he has a knowledge of the claim and information is available to him to ascertain if the terms of the contract have been fulfilled: Brown v. Myers,
In the case of Wharton et al. v. Investment Co.,
The claim in the case at bar was for the furnishing and installing of a "Complete Duplex Grade ``A' cable in concrete vault alarm system." "System" is defined in Webster's New International Dictionary as "an aggregation or assemblage of objects united by some form of regular interaction or interdependence; a natural combination, or organization of part to part." The contract required the installation of a vault alarm, in the operation of which, the component parts depend upon or relate to each other and form one complete and entire article or device. If this system is a unit, as we conceive it to be, it is not reasonable or necessary to require a particularization of the wire, conduits, buttons, and other various parts which entered into its composition. After all, the courts do not demand anything more than a substantial and sensible compliance with our Mechanics' Lien Law: Este v. P.R.R. Co.,
In the case of Day v. P.R.R. Co.,
The appellee, no doubt, was just as fully advised of the claim as if it had had possession of the specifications, for, on September 29, 1928, after the work was completed, the following letter was sent to the appellant:
"Gentlemen:
The installation of your Duplex Electrical Alarm System has this day been completed by your Mr. F.T. Hintz and he has demonstrated the protection to us in detail.
The work has been done in a first-class manner and to our entire satisfaction and your representative has thoroughly informed us as to the care and operation of the system and has left written instructions with us. City, Gettysburg; State, Pennsylvania.
Bank Gettysburg National, By C.W. Stock, Cashier."
It is reasonable to infer that this letter was not written until the appellee had informed itself of the quality, extent and nature of the work that was done. It was evidently satisfied that the appellant had fully performed its part of the contract.
It is argued upon the part of the appellee that the claim filed is for at least two systems, each of which is made up of constituent parts, consisting of wires, conduits, bells, fuses, etc. The contract provides for the furnishing and installing of a vault alarm system, which includes "a complete daylight holdup system with eleven outlets for tellers and seven button stations on desks." In our view, the daylight system is not distinct and separate, but a part of the one system, and thus affords the means of giving the alarm in the daytime as well as at night.
We have examined the authorities cited by the appellee in support of the contention that this lien is *Page 104
defective in that it contains a lumping charge, but find no trouble in readily distinguishing this case from those cited in which the liens have been stricken off for a lump sum. For instance, in Lee v. Exeter Club,
After a careful consideration, we are constrained to differ with the conclusions reached by the learned court below. The order is reversed and the lien is directed to be reinstated.
Johnson Service Co. v. Fayette Title & Trust Building , 1929 Pa. Super. LEXIS 199 ( 1929 )
Calhoun v. Mahon , 14 Pa. 56 ( 1850 )
McFarland v. Schultz , 1895 Pa. LEXIS 846 ( 1895 )
Wharton v. Real Estate Investment Co. , 180 Pa. 168 ( 1897 )
Day v. Pennsylvania Railroad , 224 Pa. 193 ( 1909 )
Burrows v. Carson , 244 Pa. 6 ( 1914 )
Dyer v. Wallace , 264 Pa. 169 ( 1919 )
Chapman v. Faith , 1902 Pa. Super. LEXIS 4 ( 1902 )
Murphy v. Bear , 240 Pa. 448 ( 1913 )
Este v. Pennsylvania Railroad , 1905 Pa. Super. LEXIS 95 ( 1905 )
Barker Painting Co. v. General Carbonic Co. , 1922 Pa. Super. LEXIS 146 ( 1922 )