DocketNumber: Appeal, 250
Citation Numbers: 84 Pa. Super. 337, 1925 Pa. Super. LEXIS 343
Judges: Orlady, Porter, Henderson, Trexler, Keller, Linn, Gawthrop
Filed Date: 11/21/1924
Status: Precedential
Modified Date: 11/14/2024
Argued November 21, 1924.
The plaintiff filed a mechanic's lien for the amount of a claim for the erection of a garage and for extra work and material in connection with said construction amounting to $998.50, alleged to have been ordered by the defendant. There was a contract in writing for the erection of the garage and a shed thereon. An affidavit of defense was filed and on proceedings leading thereto, judgment was entered against the defendant for want of a sufficient affidavit of defense. This appeal was thereupon taken. The written contract provided for the construction of the garage and shed for the consideration of $1,200; "$500 to be paid when brick work and iron beam are erected and balance to be paid at completion of building." Five hundred dollars had been paid on the contract before the filing of the lien. The defendant alleged in the affidavit of defense that the building was not constructed in a good and workmanlike manner; that the walls were not properly built by reason of which surface water seeped through; and that the shed leaked to the great damage of the owner; that the plaintiff was notified at different times personally by the defendant to comply with the contract and that he had never corrected the work nor completed it. Further denial was made that the extra work charged for was ordered by the defendant. On the contrary it was asserted that the extra work was a part of that contracted for for the consideration of $1,200. The learned trial judge was of the opinion that the allegation in the affidavit that the claim for extra material and work was included in the original contract was a conclusion of law; this view having been *Page 339
arrived at apparently because the defendant failed to deny the furnishing of the materials and labor claimed for as extras, and failed to furnish a copy of any contract other than that set forth in the lien claim filed. But inasmuch as it was stated in the lien that the extra items were not covered by the written contract and were furnished in the construction and erection of the garage and shed, the affidavit denying this averment and asserting that what was furnished and done in the construction of the work was all covered by the contract would seem to be as comprehensive as the averment in the lien, and an appropriate denial that any other material or labor than that which was necessarily included in the written contract entered into the construction of the building. This is made clearer by reference to two items constituting a considerable part of the claim for extras. The first is: "digging foundation and replacing cement, $25." The second is: "3,000 bricks, lime, sand and iron reamer, $75." It would seem that digging a foundation was an important part of the erection of a cement garage, and as the written contract included brick work, lime and sand it can hardly be said to be a conclusion of law that these items were covered by the contract. The relation of the other items of extras is not so clear, but the statement of claim says they were involved in the construction of the garage, and whether they were covered by the contract which is general in its terms, or were the cost of changes made in the contract, does not appear from the lien. A denial therefore that they were ordered by the defendant and an averment that they were included in the contract in writing relates as well to the facts in the transaction as to the legal conclusion to be drawn therefrom. The averments in an affidavit of defense are to be taken as true and the defendant is not required to set forth the manner in which they will be proved nor the evidence by which they will be substantiated: Lackawanna Trust Co. v. Carlucci,
The judgment is reversed and the record remitted with a procedendo.