DocketNumber: Appeal, 219
Judges: Poeter, Henderson, Trexler, Keller, Gawthrop
Filed Date: 4/24/1925
Status: Precedential
Modified Date: 10/19/2024
Argued April 24, 1925. This appeal is from a judgment entered for want of a sufficient affidavit of defense on a scire facias sur municipal lien. *Page 573
The ordinance authorizing the improvement and forming the basis of the claim in suit directed the grading and paving with concrete of a strip eighteen feet wide to be laid in the center of certain streets and avenues. It was enacted without petition of property holders and assessed two-thirds of the cost of the directed improvement upon the owners of property bounding or abutting thereon, by the foot front rule. (Act of May 14, 1915, P.L. 312, Chap. VI, Art. VII (c), sec. 9, pp. 350-1).
The contract made by the borough authorities was not restricted to a paving of the eighteen foot strip provided for by the ordinance but called for the undergrading and paving at street intersections of the entire square, for the full width of the intersecting streets, and the construction of certain concrete curbing and the laying of some concrete drainage pipe, rendered necessary by such additional paving outside the eighteen-foot strip.
In calculating the amount to be collected from the abutting property owners per foot frontage the borough engineer included two-thirds of the cost of the extra paving and concrete curbing and pipe, laid and constructed outside the terms of the ordinance as aforesaid.
To the scire facias sur municipal claim filed to collect the amount so assessed against their property the defendants filed an affidavit of defense averring in substance the facts above stated and that the additional paving at street intersections and the laying of the curbing and drainage pipe necessitated thereby were in violation of the ordinance authorizing the improvement and relied upon in the collection of the claim and could not be collected from the property owners under the terms of the ordinance. The affidavit set forth in detail the amount expended for such extra and unauthorized paving, curbing and pipe and the amount illegally assessed and sought to be collected from the defendants; and admitted liability for $274.40, representing the amount chargeable against them by the foot front rule *Page 574 for two-thirds of the cost of grading and paving the eighteen foot strip in accordance with the provisions of the ordinance. The court entered judgment against the defendants for $340.80, the full amount of the claim. In our opinion this was error.
The ordinance here being considered was not a general one for the grading and paving of the streets involved, nor providing that such improvement should be made according to plans and specifications to be prepared; it was special, fixing the material to be used and limiting the improvement to an eighteen feet wide strip. The borough authorities had the right to grade and pave these streets for their entire width and include therein the street intersection squares for their full width and assess two-thirds of the cost thereof on the abutting property owners by the foot front rule: Altoona City v. Laughlin,
The present ordinance would not have sustained the grading and paving of the several streets for their full width and the collection of two-thirds of the entire cost thereof by assessment on the abutting property owners. The borough authorities, no doubt, could ratify such a contract, in excess of the authority of the ordinance, so as to validate the contract as between the borough and the contractor and make the borough itself liable to the contractor, but could not without amendment or supplemental ordinance impose two-thirds of the cost of the additional and unauthorized width on the property owners, who were charged by the ordinance with a limited liability; and the property owners would have a defense pro tanto to such unauthorized charge: Mt. Lebanon Twp. v. Robinson,
The same rule applies where the borough, without amending or supplementing the ordinance imposing liability on the property owners for two-thirds of the cost of a limited improvement, enlarges, increases or widens the improvement at certain places or sections, such as street intersections, instead of for the entire length contemplated by the improvement. The property owners were not put upon notice that any part of the cost of the additional paving done by the contractor would be assessed against them from the mere fact that the additional work was being done, for the borough had the power to provide for such improvement out of its own funds: Phila. v. Bilyeu, supra, p. 569; they could rely, so far as their foot front assessment was concerned, on the improvement specified in the ordinance and the necessary drainage requirements in connection therewith.
The assignment of error is sustained, and it is directed that the judgment be modified by reducing it to the amount admitted to be due, $274.40, with interest from September 1, 1924, with leave to the borough to proceed for the balance, in case it questions any of the facts or figures averred in the affidavit of defense.
*Page 1
Township of Mt. Lebanon v. Robinson ( 1924 )
City of Philadelphia v. Burgin ( 1865 )
Fell v. Philadelphia ex rel. Cunningham ( 1876 )
Western Pennsylvania Railway Co. v. City of Allegheny ( 1879 )
Philadelphia v. Jewell ( 1890 )
City of Erie v. Piece of Land Fronting on Eighteenth Street ( 1895 )
Philadelphia v. Bilyeu ( 1908 )
Altoona City v. Laughlin ( 1920 )
City of Philadelphia v. Ramsay ( 1919 )
Borough of Sharpsville v. Randall ( 1919 )
Reilly v. City of Philadelphia ( 1869 )
Philadelphia ex rel. Dyer v. Brooke ( 1876 )
Thomas v. Northern Liberties ( 1850 )
Marshall v. Commonwealth ex rel. Mayor ( 1868 )
Hutchinson v. Pittsburg ( 1873 )