DocketNumber: 857
Judges: Cercone, Price, Spaeth, Hester, Cavanaugh, Montgomery, Hoffman
Filed Date: 10/3/1980
Status: Precedential
Modified Date: 10/19/2024
Appellant contends that the lower court erred in concluding that the parties’ contract required appellant to indemnify appellee for a loss resulting from appellee’s negligence. We disagree and, accordingly, affirm the entry of judgment n. o. v. in favor of appellee.
Appellee, Urban Redevelopment Authority of Pittsburgh (URA), owns a tract of land in the East Liberty section of Pittsburgh. Appellant, Noralco Corporation (Noralco), is engaged in demolition work. In 1965, the URA and Noralco entered into a contract whereby Noralco agreed to perform demolition and site clearance work at the East Liberty site. The contract stated that the URA assumed no responsibility for the condition of existing buildings and other structures. Additionally, the contract obligated Noralco, inter alia, to inspect the premises to acquaint itself with the existing conditions; to provide supervision, technical personnel, labor, and materials; to ask the URA for any additional information which might be needed in planning and performing the work; and to demolish structures in such a manner as to avoid hazards to persons and property. The contract further provided that Noralco “shall exercise proper precautions of persons and property and shall be'responsible for all damages to persons or property, either on or off the site, which occur as a result of [its] fault or negligence in connection with the prosecution of the work.” Another contract provision required Noralco to “indemnify and save harmless the [URA] from any claims for damages resulting from personal injury and/or death suffered or alleged to have been suffered by any person as a result of any work conducted under this contract.”
On August 1, 1968, while Noralco’s employees were tearing down a brick wall at the site, the wall collapsed and fell upon one of the employees, resulting in his death. The
The question of whether an indemnity contract requires a contractor to indemnify an owner against the latter’s own
We think it clear, on reason and authority, that a contract of indemnity against personal injuries should not be construed to indemnify against the negligence of the indemnitee, unless it is so expressed in unequivocal terms. The liability on such indemnity is so hazardous, and the character of the indemnity so unusual and extraordinary, that there can be no presumption that the indemnitor intended to assume the responsibility unless the contract puts it beyond doubt by express stipulation. No inference from words of general import can establish it. The manifest purpose, in such cases, to indemnify against the injury which, under the circumstances, could reasonably be apprehended only from the action of the indemnitor, or his servant, is a weighty consideration in construing indemnity contracts. The circumstances surrounding the parties, the one, the owner for whom the building is to be erected, and the other, the contractor who is to construct the building and hence from whose acts injuries to persons and property may be anticipated, would seem to make the conclusion irresistible, that unless expressly stipulated in the contract the owner is not to be indemnified against his own negligence. In the case at hand the parties have not expressly stipulated against injury occasioned by the in-demnitee’s own negligence, and we are satisfied, from the terms of the instrument read in light of the circumstances surrounding the parties as well as the manifest purpose inducing the bond, that they did not intend to protect the indemnitee against his own or his servant’s negligence.
Id. 217 Pa. at 262-63, 66 A. at 556-57.
In Pittsburgh Steel Co. v. Patterson-Emerson-Comstock, Inc., 404 Pa. 53,171 A.2d 185 (1961), the contractor agreed to “indemnify, save harmless and defend [the owner] from all liability for loss, damage or injury to person or property in any manner arising out of or incident to performance of this
In the instant case, Noralco contends that because the indemnification provision herein is similar to those in Perry and Pittsburgh Steel Co., it was not required to indemnify
In Potter Title and Trust Co. v. Young, 367 Pa. 239, 80 A.2d 76 (1951), our Supreme Court stated:
Generally speaking, the term “passive negligence” denotes negligence which permits defects, obstacles or pitfalls to exist upon the premises, in other words, negligence which causes dangers arising from the physical condition of the land itself. “Active negligence”, on the other hand, is negligence occurring in connection with activities conducted on the premises, as, for example, negligence in the operation of machinery or of moving vehicles whereby a person lawfully upon the premises is injured.
Id., 367 Pa. at 242-43, 80 A.2d at 78-79. See also Kopp v. R. S. Noonan, Inc., 385 Pa. 460, 123 A.2d 429 (1956); Komlo v. Balazick, 169 Pa.Super. 296, 82 A.2d 706 (1951).
Although the lower court gave instructions on active negligence, the jury’s general verdict for Noralco does not reveal whether or not the jury found the URA to be actively negligent.
In arguing that the rule announced in Perry does not apply where the indemnitee was passively negligent and not in possession of the premises at the time of the accident, the URA misapprehends the scope of that rule. Under Perry and its progeny, the parties’ intent to have their indemnity contract apply to a loss caused by the indemnitee's own negligence must be expressed in clear and unequivocal language. In applying this rule, however, the courts do not examine only the four corners of the contract to determine whether it specifies losses caused by the indemnitee’s negligence.
In Stern v. Larocca, supra, the contractors and owners entered into a contract to convert the owners’ building into a garage. The contract stated that “[t]he Contractors] shall bear all loss or damage from accidents which may occur to any person or persons, by or on account of the prosecution of the work, until possession is taken by the owner[s].” While performing the contract, an employee of the contractors was injured when part of the ceiling fell upon him. In an action instituted by the employee, the owners had been found to have been negligent because they had actual or constructive notice of a defect in the ceiling. After settling the employee’s claim, the owners sought indemnification pursuant to their contract. The New Jersey Superior Court noted that in construing an indemnity contract, courts generally have given great weight to the question of whether the contractor had exclusive possession of the place or instrumentality producing the accident. Additionally, the Court stated that courts have acknowledged that to deny recovery in every case in which the owner’s negligence in any way contributed to the loss would leave practically no circumstance in which
The owners had nothing to do with the actual process of the work of alteration under the contract.... [T]he contract contemplated that the contractors were to completely familiarize themselves with the building before doing the work. It was further provided therein that they were to do the job in entirety, including “all minor details necessary.” In providing in the agreement that the contractors were to “bear all loss or damage from accidents which may occur to any person or persons, by or on account of the prosecution of the work until possession is taken by the owner,” the parties must be taken to have in mind what experience and litigation in this field teach would be the most likely occasion for such a claim, an accident to an employee of the contractors during the work. Moreover, since the Workmen’s Compensation Act ... would preclude a common law action by such an employee against the contractors, an action of the kind here brought against the owners by the employee was one of the contingencies clearly to have been contemplated by the parties in drawing the agreement. We deem it to have plainly been the intent of the parties that the absent owner should be entirely relieved of any concern over a claim arising out of such accident, no matter whose fault it was, so long as it arose out of the doing of the work. Presumably the contractors were willing to take their chances with respect to any defective condition of the structure, relying either upon advance inspection and precautions in doing the work or the availability of insurance to cover the risk.
49 N.J.Super. at 506, 140 A.2d at 409. The Court added, however, that if the employee had been injured as a result of the active negligence of an agent of the owners, it would have held the indemnity provision inapplicable because loss
In Harvey Machine Co. v. Hatzel & Buehler, Inc., supra, the Supreme Court of California distinguished a prior decision which had held that a general indemnity provision did not indemnify the owner for a loss resulting from the owner’s negligence as follows:
Here the indemnitee did not continue to maintain independent operations on the premises whereon construction was in progress. The injuries did not result from some conduct or omission unrelated to the indemnitors’ performance. Most significantly of all, the claimed breach of duty on the indemnitee’s part was not active, affirmative misconduct, but at most passive negligence-a failure to act in fulfillment of a duty of care which devolved upon the indemnitee as the owner or occupier of land. Finally, the misconduct does not relate to some matter over which the indemnitee exercised exclusive control.
54 Cal.2d at 448, 353 P.2d at 926, 6 Cal.Rptr. at 286-87. See also Bartlett v. Davis Corp., supra, 219 Kan. at 156, 547 P.2d at 808 (“Where the indemnitor has possession and control of the work or premises and the owner does not maintain independent operations on the premises, a contract of indemnity is generally construed to cover passive negligence of the owner.”). See generally Annot., 27 A.L.R.3d 663 (1969).
We conclude that the surrounding circumstances in this case manifest the parties’ intention that the URA be indemnified for losses resulting from its passive negligence. As in the cases above cited, the contractor herein, Noralco, had exclusive control and possession of the premises at the time of the accident and the owner, the URA, was merely passively negligent. Moreover, a review of the provisions of the contract other than the general indemnity provision support our conclusion. The contract stated that the URA was not responsible for the condition of existing buildings and other structures. Additionally, Noralco agreed to inspect the premises in order to acquaint itself with existing
Judgment affirmed.
. The URA sought recovery on two alternative theories: common law indemnity and contractual indemnity. The URA has not challenged the propriety of the jury’s finding that it was not entitled to common law indemnity.
. A panel of this Court, in an unpublished opinion, held that the URA was actively negligent and that the contract did not require Noralco to indemnify the URA under the circumstances of this case. Accordingly, the panel reversed the judgment and reinstated the jury verdict. Our Court subsequently granted the URA’s petition for reargument.
. Some courts have concluded that this aspect of Perry is no longer valid. See, e. g., Spurr v. Acme Steel Co., 238 F.Supp. 606, 610 (N.D.I11.1964) (“In Perry v. Payne, supra, the court based its opinion, in part, upon a feeling that one party would not undertake a very large indemnity upon a very small job; but today, in reality, the indemnity agreements do not shift the loss, but shift the burden of paying for and procuring insurance.”); Cozzi v. Owens Corning Fiber Glass Corp., 63 N.J.Super. 117, 125, 164 A.2d 69, 74 (App.Div.1960) (“We may take judicial notice of modern business conditions which make the rationale no longer pertinent. Today the risk of injury may be shifted to an insurance company, and commonly is.”) See also Westinghouse Electric Co. v. Murphy, Inc., 425 Pa. 166, 173 n.5, 228 A.2d 656, 660 n.5 (1967) (“It would appear that ... contracts [indemnifying one against his own negligence] are useful to parties involved in construction and similar activities as a means of allocating the
. The jury found also that the contractor and subcontractor were negligent in failing to employ safety precautions which had been agreed upon, and that the owner was negligent in failing to enforce those safety provisions.
. The URA concedes that the jury found that Noralco was neither actively nor passively negligent.
. In a case involving an exculpatory provision, our Court held that a contract releasing the lessor “from any liability” precluded the lessee from recovering damages for injuries allegedly resulting from the lessor’s negligence. Zimmer v. Mitchell and Ness, 253 Pa.Super. 474, 385 A.2d 437 (1978). Our Court stated: “Although we must construe the contract strictly, we must also use common sense in interpreting this agreement. The mere fact that the word ‘negligence’ does not appear in the agreement is not fatal .... ” Id., 253 Pa.Super. at 479, 385 A.2d at 439. In Dilks v. Flohr Chevrolet, 411 Pa. 425, 192 A.2d 682 (1962), the Supreme Court stated: “While an exculpatory clause • ... differs somewhat from an indemnity clause ... there is such a substantial kinship between both types of contracts as to render decisions dealing with indemnity clauses applicable to decisions dealing with exculpatory clauses, and vice versa.” Id., 411 Pa. at 435 n.11, 192 A.2d at 687 n.11.
. On this appeal Noralco has not challenged the lower court’s statement in its opinion that Noralco received fair consideration for its agreement to indemnify the URA. See note 3 supra and accompanying text. Compare American Oil Co. v. Hart, 356 F.2d 657 (5th Cir. 1966) (broad language of indemnity provision did not require contractor to indemnify owner for loss caused by passive negligence of owner where contract price was only $40.45).
. The Pennsylvania Workmen’s Compensation Act provides:
In the event injury or death to an employe is caused by a third party, then such employe, his legal representative, husband or wife, parents, dependents, next of kin, and anyone otherwise entitled to receive damages by reason thereof, may bring their action at law against such third party, but the employer, his insurance carrier, their servants and agents, employes, representatives acting on their behalf or at their request shall not be liable to a third party for damages, contribution or indemnity in any action at law, or otherwise, unless liability for such damages, contribution or indemnity shall be expressly provided for in a written contract entered into by the party alleged to be liable prior to the date of the occurrence which gave rise to the action.
Act of Dec. 5, 1974, P.L. 782, No. 263, § 6:77 P.S. § 481(b) (Supp.) (emphasis added). This provision went into effect on February 3, 1975. Because the contract in this case was entered into in 1965, we do not decide the applicability of this provision to this case.