DocketNumber: Civil No. 94-2036 (DRD)
Citation Numbers: 922 F. Supp. 707, 1996 U.S. Dist. LEXIS 4499, 1996 WL 166525
Judges: Dominguez
Filed Date: 3/26/1996
Status: Precedential
Modified Date: 11/7/2024
OPINION AND ORDER
Pending before this Court are cross motions for summary judgment. Plaintiff Cabot LNG Corp. (“Cabot”) has moved for summary judgment requesting that defendant Puerto Rico Electric Power Authority (“PREPA”) be enjoined from executing or performing under any contract for the sale of electricity unless that contract results from public bidding pursuant to section 15 of PREPA’s Organic Act, P.R.Laws Ann. tit. 22, § 205 (1987) (Docket No. 5). Defendant PREPA and intervenors EcoEléctrica, L.P. (“EcoEléctrica”) and AES Puerto Rico L.P. (“AES-PR”) (collectively referred to as “Defendants”) have filed a reply to Plaintiffs motion and moved for summary judgment requesting that Cabot’s complaint be dismissed.
I. FACTUAL BACKGROUND
The material facts regarding this case are not complex and are not in dispute. Rather, the dispute turns on questions of law. The, following factual description is based on the affidavits, uncontested statements of material fact, and other pertinent materials submitted to this Court.
A. THE PARTIES
Defendant PREPA is a public corporation of the Commonwealth of Puerto Rico. It generates, transmits, and distributes electricity to consumers in Puerto Rico. PREPA was formed in 1941; its powers are enumerated by its Organic Act, 22 L.P.RA. §§ 191-247.
Intervenor EcoEléctrica is a Bermuda limited partnership whose general partners are Buenergia B.V. (a Dutch B.V.) and KES Bermuda, Inc. (a Delaware corporation).
Intervenor AES-PR is a limited partnership organized pursuant to the Laws of the State of Delaware and duly registered to do business in Puerto Rico. Its partners are AES Puerto Rico, Inc. and AES Las Mareas, Inc. (both Delaware corporations).
B. PURPA AND THE EVOLUTION OF THE INDEPENDENT POWER INDUSTRY
Prior to 1978, most of the electric energy that electric utilities sold was generated at power plants developed and constructed by themselves. Slusser Aff. ¶ 8. To the extent that utilities purchased electricity, they purchased it from other electric utilities. In 1978, however, Congress enacted the Public Utility Regulatory Policies Act (“PURPA”), which transformed the electric utility industry. Id. Section 210 of PURPA, 16 U.S.C. § 824a-3, requires utilities to purchase electricity from independently-owned generation facilities that meet certain qualifications, known as “qualifying facilities” or “QFs.” The Federal Energy Regulatory Commission (“FERC”) promulgated regulations implementing PURPA. Among other things, these regulations establish the rates that utilities must pay for electricity. 18 C.F.R. § 292.304.
Since PURPA was enacted into law, a whole new independent power industry has evolved in the United States. Slusser Aff. ¶8. Most new generating capacity constructed in the United States is now independently-owned, instead of being owned by electric utilities. Independently-owned electric generation facilities have allowed utilities to diversify their sources of generation and uses of fuel. Such facilities have also allowed utilities to avoid incurring the large capital costs associated with the construction of electric generation facilities because independently-owned generation facilities are also independently financed. Samson Aff. ¶ 5.
It is undisputed that a wide variety of skills and expertise are required to develop and operate an independently owned electric generation facility. Slusser Aff. ¶ 9; Samson Aff. ¶ 6. Financial expertise is necessary to obtain the complex, off-balance sheet financing typically employed by these facilities, which cost hundreds of millions of dollars. Scientific and engineering expertise is required to successfully apply the advanced technologies that are frequently employed. Environmental expertise is required to satisfy the numerous federal, state and local environmental requirements. Specialized business expertise is required to finalize the fuel supply, power sales, and other contractual arrangements necessary for the operation of the facility. Finally, operational expertise is required to run the facility in an efficient, reliable, and economic fashion. Slusser Aff. ¶ 10; Samson Aff. ¶ 6.
C. CIRCUMSTANCES LEADING TO THIS PROCEEDING
By 1993, after it became evident that the Cogentrix project would not go forward,
The project developers made presentations regarding their projects to the Cogeneration Task Force, a group formed by the Government of Puerto Rico and consisting of the directors of several governmental agencies and other persons from the Executive Branch that were or might be involved in the formulation of Puerto Rico’s public policy on energy. Id. Presentations also were made to the Puerto Rico House of Representatives’ Committee on Socioeconomic Development and Planning. The presentations before the House committee were open to the public and were widely reported in the press. Id.
Of the proposals submitted to PREPA, five, including the submittals by EcoEléctri-
On February 25, 1994, PREPA informed EcoEléctriea and AES-PR by letter that they had been selected to supply electricity to PREPA in accordance with their proposals, pending the successful negotiation of a contract. One day later, PREPA informed Cabot by letter that its proposal had not been among those selected for inclusion in PREPA’s expansion plan and advised Cabot that PREPA would consider a revised proposal in future expansion plan revisions.
Cabot did not easñy accept the loss. In a letter to PREPA dated April 20, 1994, Cabot’s counsel urged PREPA to “initiate negotiations with the third, fourth or fifth finalist,” and “if the presently selected LNG project is rejected, [then] PREPA would turn to the next LNG alternative.” This letter contained no suggestion that Cabot understood that PREPA was required to engage in a formal bidding process.
Almost three months later in a letter to PREPA dated June. 15, 1994, Cabot stated to PREPA its belief that formal bidding was required. Complaint ¶ 14. Although having fidly participated in PREPA’s evaluation process, Cabot now expressed “considerable doubts and concerns ... about the process by which PREPA selected the projects for the supply of electricity ... announced in February,” and, for the very first time, requested that PREPA initiate a public competitive bidding process pursuant to section 205 of PREPA’s Organic Act.
Subsequent to the filing of Cabot’s complaint, EcoEléctriea and AES-PR continued negotiations with PREPA, and each company ultimately executed long-term contracts in which they agreed to finance, engineer, construct, and operate .cogeneration plants generating electricity to be sold to PREPA well into the next century. They have also continued their development activities, including the following: (1) arranging for non-recourse “project financing” for their projects; (2) completion of conceptual engineering to support the filing of permits and other applications requiring agency approvals; (3) foñow-up meetings with, and hearings before, those agencies responsible for granting permits and approvals; (4) conducting environmental, geotechnical, seismic, and marine studies in the proposed site areas; (5) preparation and submittal of permit and
II. SUMMARY JUDGMENT STANDARD
Summary judgment is appropriate in those cases in which “there is no genuine issue as to any material fact” and the moving party is entitled to judgment as a matter of law. Fed.R.Civ.P. 56(c). The intricacies and general standards of Rule 56, have been documented by the First Circuit Court in a “cascade of eases.”
A fact is material if, under applicable substantive law, it may affect the result of the case. Ortega-Rosario v. Alvarado-Ortiz, 917 F.2d 71 (1st Cir.1990). A dispute is genuine only if there is conflicting evidence that requires a trial to resolve the discrepancy. Id. at 71. A court should deny a motion for summary judgment if the dispute about a material fact is genuine when, based on the evidence, a reasonable jury could return a verdict for the nonmoving party. Woods v. Friction Materials, Inc., 30 F.3d 255, 259 (1st Cir.1994). See also Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248, 106 S.Ct. 2505, 2510, 91 L.Ed.2d 202 (1986).
In determining whether summary judgment is warranted, the Court views the facts alleged in the light most favorable to the nonmoving party and must indulge all inferences in favor of that party. See LeBlanc v. Great American Ins. Co., 6 F.3d 836, 841 (1st Cir.1993), cert. denied, — U.S. -, 114 S.Ct. 1398, 128 L.Ed.2d 72 (1994); Mottolo v. Fireman’s Fund Ins. Co., 43 F.3d 723, 725 (1st Cir.1995); Libertad v. Welch, 53 F.3d 428, 435 (1st Cir.1995); John & Kostas Service Station, Inc. v. Cumberland Farms, Inc., 948 F.2d 821, 822 (1st Cir.1991).
The party opposing the motion for summary judgment can not rely on “mere allegations or denials” of the pleadings. Fed. R.Civ.P. 56(e). Rather, the opposing party must be able to show by affidavits, depositions, answers, and admissions in the record that there is a genuine issue for trial. Celotex Corp., 477 U.S. at 324, 106 S.Ct. at 2553.
III. LEGAL ANALYSIS
According to Plaintiff, PREPA is required under section 205 to purchase electric energy through competitive bidding pursuant to detañed procurement regulations. Therefore, Plaintiff contends that because PREPA faded to use competitive bidding procedures for the purchase of electricity, PREPA must be enjoined from performing under its contracts with EcoEléctrica and AES-PR. This Court finds that the purchase of energy fañs within the professional service exception to § 205 and as such PREPA is not required to utilize competitive bidding for the purchase of energy.
Competitive bidding statutes are effective tools aimed at preventing favoritism or collusion in the public arena.
The open competition fostered by competitive bidding serves two recognized purposes. First and primarily, it protects the taxpayer or ratepayer by assuring efficient use of public revenues. Competitive bidding also serves to provide a fair forum for those interested in undertaking public projects.
General Engineering Corp. v. Virgin Islands Water & Power Auth., 636 F.Supp. 22, 40 (D.V.I.1985), aff'd, 805 F.2d 88 (3d Cir.1986).
The Puerto Rico statute at issue in the present case is P.R.Laws Ann. tit. 22, § 205 (1987) (official translation), which reads in pertinent part:
All bids for purchases and contracts for supplies or services, except for personal services, made by the Authority, including construction contracts, shall be advertised with sufficient time before the date the bids are opened, so that the Authority can guarantee public knowledge and appearance through competitive bidding.
Section 205 also sets forth six exceptions to the formal public bidding requirements, including a professional services exception. “Advertisement for bids shall not be required when ... professional or expert services or work are required and the Authority deems it in the best interests of good administration, that such work or services be contracted without such advertisement.” P.R. Laws Ann. tit. 22, § 205 (1987).
The instant case is in all material aspects similar to the selection of a power supplier made by the Virgin Islands Water and Power Authority (“WAPA”). General Engineering Corp., 636 F.Supp. at 22. In the midst of a potential energy crisis, WAPA began negotiations with an investment banking firm, Donaldson, Lufkin, & Jenrette (“DLJ”), to finance a third party cogeneration
The United States District Court for the District of the Virgin Islands dismissed the suit, holding that the professional services exception from competitive bidding was applicable. Id. at 48. The court rejected the contention that “the contract is a mere sale of power” as “simplistic and wrong.” Id. at 44. Instead, the court viewed the proposed project as a package consisting of many parts. Although some of the parts, such as the provision of the equipment, might have been, by themselves, subject to the competitive bidding statute, other parts, such as design and financing, clearly were exempt. Id. at 42. The court thus found that the
In analyzing this issue, the court looked to “the relative importance of the services to the overall success of the project.” Id. at 44 (citing Waste Management, Inc. v. Wisconsin Solid Waste Recycling Auth., 84 Wis.2d 462, 267 N.W.2d 659 (1978); Autotote Ltd. v. New Jersey Sports & Exposition Auth., 85 N.J. 363, 427 A.2d 55 (1981)).
Similarly, the instant contract between Defendants was not merely for the purchase of energy as argued by Plaintiff during an Oral Argument held on September 25, 1995. The contract requires the construction, development, financing, and management of a cogen-eration plant. This Court recognizes the complexity of such a plant and acknowledges that various expertises are required to set up and operate such a project, including scientific, engineering, financial, environmental, and operational expertises. In total, the development of a cogeneration or small power production facility requires a sophisticated package of highly specialized knowledge and skills. Therefore, the present contract falls within the purview of sec. 205’s professional service exception.
Plaintiff argues that the WAPA case is distinguishable, because in that case one of the partners of the independent power company had also been engaged to give WAPA financial advice, a role that none of parties were retained to perform here. This distinction is overstated. The contract in dispute in the WAPA case was not the contract pursuant to which the financial advice was provided. Instead, it was the contract signed by WAPA for the “design, construction, financing, installation and operation of a cogeneration plant.” 636 F.Supp. at 33. Furthermore, as the aforementioned quotes set forth above demonstrate, the provision of the entire “package” of skills involved led the court to conclude that the exemption was applicable, not merely the provision of financial advice. As a consequence, the WAPA case is directly on point, further supporting the interpretation that the similar provision in section 205(2)(d) would apply.
Further, in Sea Air Shuttle Corp. v. Virgin Islands Port Auth. 800 F.Supp. 293 (D.V.I.1992), a subsequent decision by the same court involving the same professional and expert services exception to the Virgin Islands’ public bidding statute, a sea plane service sued another competing service and the Virgin Islands Port Authority for wrongfully awarding an exclusive lease of sea plane ramps without conducting bidding. In that case, the competing service argued that the lease of the ramps was purely a real estate transaction, as Cabot argues that PREPA’s cogeneration contracts with AES-PR and EcoEléctrica are merely purchases of electricity. The Court was not swayed by the argument and relied on the WAPA decision as controlling precedent without making the financial services distinction advanced by Cabot in this case:
This position [purely a real estate transaction] oversimplifies the ... lease and*715 ignores the principle that in deciding whether the professional service exception is fulfilled, a court must focus on the nature of the work implicit in the proposal or bid. See General Engineering Corp. v. Virgin Islands Water & Power Auth., 636 F.Supp. 22, 42 (D.V.I.1985), aff'd, 805 F.2d 88 (3d Cir.1986) [other citations omitted]. In this ease, the work inherent in the lease of the sea plane ramps is the provision of sea plane service between the United States Virgin Islands and other islands. The Third Circuit recognized that the professional services exception allows a public agency the discretion to avoid competitive bidding when it is in the interest of good administration. General Engineering Corp., 805 F.2d at 95 (citations omitted). Further, the Third Circuit identified the public interest in reliability os a paramount concern in allowing services of an expert nature to be contracted for without compliance with competitive bidding requirements. Id.
Sea Air Shuttle, 800 F.Supp. at 300-01 (emphasis added).
In the present ease, the public interest in reliability of the cogeneration projects is also of vital concern to PREPA in assuring the people of Puerto Rico that the Island’s electric energy demands will be adequately met by 1997.
IV. CONCLUSION
For the reasons stated above, the Court hereby GRANTS the motion for summary judgment filed by Defendants and DENIES the motion for summary judgment filed by Plaintiff. Plaintiffs complaint and request for injunction are hereby dismissed with prejudice. Costs to be imposed to Plaintiffs; no imposition of lawyers fees is made since the Court does not find temerity by Plaintiff. Rodriguez v. John Hancock Mutual Life, 110 D.P.R. 1 (1980) (no obstinacy finding in first impression cases). See also P.R.R.Civ.P. 44.1(d), P.R. Laws Ann. tit. 32, App. III, R. 44.1(d) (1983).
IT IS SO ORDERED.
AMENDED JUDGMENT
Our opinion and order and the judgment filed on March 26, 1996, is amended to correct the imposition of costs to Plaintiff instead of Defendants.
The Court having granted Defendants’ motion for summary judgment (docket nos. 11, 20, 31, 43) and denied Plaintiffs motion for summary judgment (docket no. 5), judgment is hereby entered DISMISSING Plaintiffs claims WITH PREJUDICE against Defendant. Costs to be imposed to Plaintiffs; lawyer’s fees are not to be imposed.
IT IS ORDERED AND DECREED.
. This Court previously granted the requests for intervention filed by AES-PR and EcoEléctrica. (Docket No. 48).
. The Court, in its discretion, authorized the parties to supplement the summary judgment sub-mittals, Cia. Petrolera Caribe Inc. v. Arco Caribbean Inc., 754 F.2d 404, 410 (1st Cir.1985), on an alleged administrative practice exempting the application of the competitive bidding law of Puer-to Rico. P.RXaws Ann. tit. 22, § 205. (Docket No. 57). The Court does not rely on the arguments of either party on this subject and decides this case on other grounds.
. PREPA has been found to be subject to FERC's PURPA regulations. See Puerto Rico Electric Power Auth. v. FERC, 848 F.2d 243 (D.C.Cir.1988).
. The Cogentrix Company, which had an idea for a coal-fired project, executed a power sale agreement with PREPA, but the necessary permits were not obtained so the project was canceled. Slusser Aff. ¶ 11.
. Plaintiff originally requested a preliminary injunction. However, because Plaintiff actively participated in the procedure, it has "unclean hands.” "He who seeks equity must do equity.” See K-Mart Corp. v. Oriental Plaza, Inc., 875 F.2d 907, 910 (1st Cir.1989). A party will not succeed in obtaining an injunction when it participated in the specific act sought to be enjoined. “One’s misconduct need not necessarily have been of such nature as to be punishable as a crime or as to justify legal proceedings of any character. Any willful act concerning the cause of action which rightfully can be said to transgress equitable standards of conduct” constitutes “unclean hands.” Precision Instrument Mfg. Co. v. Automotive Maintenance Machinery, 324 U.S. 806, 815, 65 S.Ct. 993, 997-98, 89 L.Ed. 1381 (1945).
Puerto Rico recognizes the application of equitable remedy defenses such as that of "unclean hands.” See Asociacion de Vecinos de Villa Caparra v. Iglesia Catolico, 117 D.P.R. 346, 354 (1986); Colon v. San Patricio Corp., 81 D.P.R. 242, 262 (1959). Further, the Puerto Rico Supreme Court has also adopted the rationales and theories underlying equitable remedy defenses. See Colon, 81 D.P.R. at 255.
Plaintiff therefore is barred from seeking equitable relief because of the applicability of the doctrine of "unclean hands.” Plaintiff and four others participated in the private bidding process. Further, Plaintiff actively competed for the opportunity to develop the cogeneration plant by submitting proposals for the plant. Only after discovering that the development contract was not awarded to them, Plaintiff blew the whistle and informed PREPA that competitive bidding was required. Subsequently, Plaintiff sought to enjoin Defendants. However, Plaintiff's action exemplifies "unclean hands” and is thus impeded from obtaining equitable relief.
. McCarthy v. Northwest Airlines, Inc., 56 F.3d 313, 315 (1st Cir.1995) (citing Coyne v. Taber Partners I, 53 F.3d 454, 457-58 (1st Cir.1995); National Amusements, Inc. v. Town of Dedham, 43 F.3d 731, 735 (1st Cir.), cert. denied, - U.S. -, 115 S.Ct. 2247, 132 L.Ed.2d 255 (1995); Pagano v. Frank, 983 F.2d 343, 347 (1st Cir.1993); United States v. Plat 20, Lot 17, 960 F.2d 200, 204 (1st Cir.1992); Rivera-Muriente v. Agosto-Alicea, 959 F.2d 349, 351-52 (1st Cir.1992); Griggs-Ryan v. Smith, 904 F.2d 112, 115-16 (1st Cir.1990); Medina-Munoz v. R.J. Reynolds Tobacco Co., 896 F.2d 5, 7-8 (1st Cir.1990); Garside v. Osco Drug, Inc., 895 F.2d 46, 48-49 (1st Cir.1990)).
. There seems to be no Puerto Rico case law interpreting the professional services exception within § 205. The parties, in their briefs, failed to cite any Puerto Rican case law on the issue. The Court did further research and was unable to find such case law. This Court then relies on the District of Virgin Islands’ interpretation of a similar statute.
. The professional services exception to the Virgin Islands’ competitive bidding statute reads as follows: "Advertisement for bids shall not be required, however, when ... professional, financial (including financial printing) or other expert services or work are required and the Authority shall deem it best in the interest of good administration that contracts therefore be made without such advertisement....” V.I.Code Ann. tit. 30, § 116(a)(3). This statute is strikingly similar in language to the professional services exception in § 205 and as such this Court finds highly persuasive the District of the Virgin Islands' interpretation of the exception.
.“Cogeneration facility means a facility which produces — (i) electric energy, and (ii) steam or forms of useful energy (such as heat) which are used for industrial, commercial, heating, or cooling purposes.” 16 U.S.C. § 796(18)(A).
. In Autotote Ltd. v. New Jersey Sports & Exposition Auth., 85 N.J. 363, 427 A.2d 55 (1981), the New Jersey Supreme Court held that a contract for installation and servicing of a totalisator system at a racetrack operated by the New Jersey Sports and Exposition Authority involved inextricable integration of computer system and services of such technical and scientific nature as to constitute "professional services” within the statutory exception to requirements of public bidding. The Court also considered the party challenging the award to be estopped given its participation in the negotiation process with the Authority. In Waste Management v. Wisconsin Solid Waste Recycling Auth., 84 Wis.2d 462, 267 N.W.2d 659 (1978), the Court held that a contract for the design, construction and operation of a solid waste recycling facility fell under a "professional” services exception in a bidding statute similar to the one in the case at hand.
. Cabot argues, without any statutory support, that PREPA never made a finding that expert or professional services were required and it would be in the best interests of good administration to contract such services without bidding. While the statute, P.R.Laws Ann. tit. 22, § 205(3), recognizes PREPA’s discretion in this matter, it does not impose on PREPA any obligation to make an express finding that the exception applies. The WAPA and Sea Air Shuttle cases are also apposite in the sense that in those cases the Court, in the context of a similarly worded statute, did not hold that an express finding by the governmental bodies was required for the exception to apply.