DocketNumber: C.A. No. PC 10-0404
Judges: STONE, J.
Filed Date: 9/1/2011
Status: Precedential
Modified Date: 7/6/2016
OCI's investigations into the alleged violations began after DEM received a September 2002 report entitled "Release Investigation Report: Light Non-Aqueous Phase Liquid Occurrence Proximate to Dunellen Road, East Providence, Rhode Island" prepared by Vanasse Hangen Brustlin, Inc. ("VHB") on behalf of CTC.2 (VHB, "Light Non-Aqueous Phase Liquid (LNAPL) occurrence proximate to Dunnellen Road, East Providence, Rhode Island," Release Investigation Report, Sept. 2002.) Therein, VHB reported that LNAPL — having the characteristics of weathered, leaded gasoline — had been discovered in groundwater monitoring wells located on CTC's property, and the petroleum product pipelines located on the Site were a possible source. Id. at 25-27, 28-29. In its findings of fact, OCI stated that the release of the LNAPL resulted in pollutants entering the waters of the state. (NOV at 2.)
On December 2, 2002, DEM issued a Letter of Responsibility to GPM, Power Test, and GPC, which notified the companies that the aforementioned report documented the presence of separate phase petroleum in groundwater on Parcel 15, and the likely source of the petroleum was the abutting pipeline easement controlled by the three *Page 3 respondents. (Letter of Responsibility from Margaret Dein Bradley, CPG, December 2002 ("Letter of Responsibility").) The letter further explained that due to the confirmed release of petroleum product to the land and waters of the state, the three respondents were required to perform a site investigation to determine the nature and extent of contamination and to evaluate and design a proposed remedy, as well as submit a Site Investigation Report ("SIR") on or before February 1, 2003. Id. In response to this letter, Power Test, GPM, and GPC notified DEM of their intent not to comply with the requirements set forth therein. Id.
Consequently, on July 21, 2003, DEM issued a Notice of Intent to Enforce, in which Respondents were required to comply with the following: submit a written response to DEM on or before August 8, 2003; notify all abutting owners and tenants on or before August 15, 2003 that a site investigation was to be performed in accordance with the Remediation Regulations; commence site investigation activities no later than August 25, 2003; submit preliminary monitoring well analytical results and a proposal for short term response action on or before September 15, 2003; and submit a Site Investigation Report before October 3, 2003. On August 8, 2003, counsel for Power Test and GPC notified DEM that GPM would take primary responsibility for complying with the requirements set forth in the Notice of Intent to Enforce. (NOV at 3.)
DEM subsequently received a report entitled "Preliminary Monitoring Well Results, Subsurface Investigation," prepared by The Tyree Organization, Ltd. ("Tyree") on behalf of GPM on September 15, 2003. This report explained that soil borings had been advanced on or near Parcel 11 and that soil samples were collected for laboratory analysis. It further disclosed that five groundwater monitoring wells had been installed, *Page 4 and non-aqueous phase liquid ("NAPL") had been discovered in each groundwater monitoring well. Id.
On December 18, 2003, DEM issued a second Notice of Intent to Enforce to GPM and CTC. This Notice required GPM to submit a focused Site Investigation Work Plan on or before January 9, 2004, and to submit a Sight Investigation Report within seventy-five days of DEM's approval of the focused Site Investigation Work Plan.Id. It further ordered GPM and CTC to resolve all outstanding access issues within thirty days of DEM's approval of the focused Site Investigation Work Plan.
On July 6, 2004, VHB notified DEM that VHB and Tyree had performed groundwater monitoring on the wells located on Parcels 11, 15, and 10.3 Id. This report stated that all five of the groundwater monitoring wells on or near Parcel 11 contained LNAPL ranging in thickness from 1.33 feet to 2.57 feet, and six of the twenty groundwater monitoring wells on Parcel 15 contained LNAPL ranging in thickness from .09 feet to 2.46 feet.Id. It also determined that the groundwater gauging activities indicated that the GPM pipeline was the most likely source of the LNAPL.4 Id.
Upon the issuance of the NOV, no party had complied with the Letter of Responsibility and either Notice of Enforcement.Id. The NOV found that "[u]pon information and belief, Respondents discharged petroleum product to the land and waters of the state" and failed to take immediate steps to contain and remove the oil and/or hazardous materials in accordance with the OPC regulations upon their discovery. Id. *Page 5
The NOV determined that Power Test violated, among other statutes and regulations, the OPCA, G.L. 1956 §
The NOV then ordered Power Test to notify DEM to identify the party that will act as the single point of contact for the Site Investigation, within ten days of receipt of the NOV. Additionally, it required Power Test to provide written notification to all abutting property owners and tenants that an investigation is about to occur at the Site. The NOV also mandated Power Test to begin conducting a Site Investigation within thirty days of receipt of the NOV, and to submit preliminary monitoring well results for review with a proposal to implement a short term response within sixty days of receipt. Id. at 6. Furthermore, it required Power Test to submit a completed Site Investigation Report and Site Investigation Report Checklist within seventy-five days of receipt of the NOV. Under G.L. 1956 §
On August 16, 2005, 5 Power Test, GPC, and GPM timely appealed the NOV to the Administrative Adjudication Division of DEM ("AAD"). (Request for Administrative Hearing, Aug. 15, 2005.) Following discovery, the AAD conducted hearings on the matter on May 5 and May 6, 2008, during which Power Test, GPC and GPM presented written evidence and testimony, as well as stipulated to several facts and exhibits. (Admin. Tr., May 5, 2008; Admin. Tr., May 6, 2008.)
On October 20, 2008, the AAD Hearing Officer issued a recommended decision, which was affirmed as a final decision by the DEM Director on October 20, 2008. *Page 6 Subsequently, on December 23, 2009, the Director of DEM affirmed an amended recommended decision, which contained a recalculated administrative penalty.
In the final decision, the AAD Hearing Officer made findings of fact based on the parties' stipulations. (DEM Decision, December 23, 2009, ("Decision") at 2-6.) He then summarized the testimony at the hearing and each party's argument.Id. at 7-9. Analyzing the OPCA and OPC Regulations violations, the Hearing Officer recognized that OCI found that petroleum had been in the groundwater prior to Power Test's involvement with the property. Under the OPCA, the Hearing Officer noted that OCI contended that a "discharge" is ongoing and, thus, the oil continues to "migrate in the groundwater" until the contaminants are removed.Id. at 23. He additionally explained that Power Test conversely argues that the word "discharge" requires proof that the party, in fact, caused the discharge and that the mere presence of petroleum is not sufficient to constitute a violation of the OPCA and the OPC Regulations. Id.
Addressing Power Test's argument, the Hearing Officer disregarded its supporting case, L.B. Foster Co. v. State,
Instead of following Power Test's supporting law, the Hearing Officer turned to AAD precedent and a Superior Court bench decision on appeal from DEM. Id. at 23-25. The Hearing Officer referenced Merva v. Department of Environmental Management, *Page 7 C.A. No. PC 97-0115, in which the Appellant appealed from a judgment by DEM holding him responsible for petroleum contamination on his property caused by a prior owner because of his failure to remediate the contamination. Id. at 24-25. The Hearing Officer explained that in a bench decision, the Superior Court justice mentionedin dicta that through enacting the "new Oil Pollution Control Act, the legislature defined discharge. . . . Strict liability for cleanup on account of passive conduct is now definitively and clearly imposed." Id. at 25. In accordance with this premise, the Hearing Officer found that the OPCA and OPC regulations "provide a definition of discharge which encompasses the Respondent's failure to act . . . Respondent's liability can be imputed to a property owner for passive conduct for failure to remove petroleum contaminants form the groundwater under its property once discovered." Id. at 26. He elaborated that "this liability is not excused by the fact that the petroleum was released by a prior owner." Id.
Finding that the testimony, stipulated facts, and exhibits provide sufficient evidence that petroleum product is present in the groundwater, the Hearing Officer concluded that leaching currently exists and has existed since Power Test took ownership of the property.6 Given the definition of discharge, the Hearing Officer found that the leaching of petroleum in the groundwater of Power Test is a "discharge" under the OPCA and OPC Regulations. Accordingly, the Hearing Officer concluded that under the OPCA *Page 8 and OPC Regulations, Power Test is responsible for the mitigation and remediation of the contamination once aware of its presence. The Hearing Officer further found that as liability for the failure to remove contaminants from the groundwater rests with the property owner, only Power Test, not GPC or GPM, is responsible for the violation. The assessed penalty for these violations was $50,000.
Power Test timely appealed the DEM Decision to the Court. Upon appeal, Power Test avers that DEM's interpretation of the OPCA is clearly erroneous because causation is required under this statute. Furthermore, Power Test argues that DEM's interpretation of the OPCA renders the Rhode Island Industrial Property Remediation and Reuse Act ("IPRRA") meaningless. It additionally contends that DEM's decision was arbitrary and capricious because no factual basis exists to uphold the NOV, as Power Test claims that it did not have knowledge of the LNAPL until the NOV. Finally, Power Test maintains that even if it is liable under the OPCA, it may only be liable for the LNAPL on its own property.
In response, DEM argues that its interpretation of the OPCA and OPC Regulations is not clearly erroneous because their standard of liability applies regardless of fault. In addition, DEM opines that the OPCA is a separate statute from IPRRA and, therefore, both create schemes of liability without rendering each other meaningless. DEM also contends that Power Test had knowledge prior to the issuance of the NOV; accordingly, it argues that its decision is not arbitrary and capricious. *Page 9
"The court shall not substitute its judgment for that of the agency as to the weight of the evidence on questions of fact. The court may affirm the decision of the agency or remand the case for further proceedings, or it may reverse or modify the decision if substantial rights of the appellant have been prejudiced because the administrative findings, inferences, conclusions, or decisions are:
(1) In violation of constitutional or statutory provisions;
(2) In excess of the statutory authority of the agency;
(3) Made upon unlawful procedure; (4)Affected by other error of law;
(5) Clearly erroneous in view of the reliable, probative, and substantial evidence on the whole record; or
(6) Arbitrary or capricious or characterized by abuse of discretion or clearly unwarranted exercise of discretion." Sec.
42-35-15 (g).
Under this statute, the Court must uphold the agency's decision if legally competent evidence exists in the record. Town ofBurrillville v. Rhode Island State Labor Relations Bd.,
DEM uses a two-tier review process in which a hearing officer first hears grievances and then issues a written decision that is submitted to the Director of DEM. The Director considers the decision, along with any further arguments, and renders his or her own decision. This two-tier review is similar to a funnel.Environmental Scientific Corp. v. Durfee,
Conversely, DEM avers that the OPCA and OPC regulations are meant to apply liability broadly, regardless of fault. Hence, DEM maintains that the language of the statute applies responsibility to a party, like Power Test, which fails to perform remedial actions when an ongoing migration of petroleum already released into groundwater is discovered. Accordingly, DEM opines that its interpretation is not clearly erroneous in light of the language within the statute.
The Rhode Island OPCA provides that "[n]o person shall discharge, cause to be discharged, or permit the discharge of oil into, or upon the waters of the land of the state *Page 12
except by regulation or by permit from the director." G.L. 1956 §
"provide[s] a definition of discharge which encompasses the Respondent's failure to act. I find that the Respondent's liability can be imputed to a property owner for passive conduct for failure to remove petroleum contaminants from the groundwater under its property once discovered. This liability is not excused by the fact that the petroleum was released by a prior owner." (Decision at 26.)
Within the OPCA, "discharge" is defined as "any spilling leaking, pumping, pouring, emitting, emptying, releasing, injection, escaping, leaching, dumping, or disposing into the environment." Sec.
Leaching, therefore, by its plain meaning, is a passive and continuous action. See, e.g., Olin Corp. v. CertainUnderwriters at Lloyd's London,
Notwithstanding the use of "leaching," Power Test argues that the inclusion of the term "into" within the OPCA requires causation. The plain meaning of the preposition "into" is "[t]o the inside or interior of." Webster's New College DictionaryII 581 (2001). Within the context of the section, contaminants "leach into" — or "to the inside of" — the land when they "passively migrate" within it. See Olin Corp.,
This interpretation is bolstered by the stated purpose of the OPCA: to ensure that "[t]he citizens of the state should not have to bear the burdens of the cleanup and the losses of economic livelihood that result from the discharge of oil in any degree." Sec.
Power Test supports its interpretation by arguing that Cookman Realty Group v. Taylor,
"``Except for any source or class of sources which has been granted a variance for the particular contaminant at issue, any person who owns or operates a source subject to the Act which has caused, in whole or in part, the concentration of any constituent to exceed any applicable groundwater quality standard subject to the Act, must cease further release of that contaminant and must make every *Page 16 reasonable effort to identify, remove or mitigate the source of such contamination and strive where practical to reduce the level of contamination over time to support drinking water use of such groundwater.'" Cookman Realty Group, 566 S.E.2d at 297 (quoting W. Va. Code R. § 47-57-4.1 (1994)).
Under the definitions therein, the term "source" is "``any facility or activity which has caused a release or is reasonably likely to cause a release.'"Id. at 298 (quoting W. Va. Code R. § 47-57-2.13)). Defining the terms "facility" and "activity" with their plain and ordinary meanings, the Cookman Realty Group Court determined that the Defendant at issue was classified as neither because the Defendant never performed a positive act and none of its current or former owners used the space for hazardous materials storage, use, or disposal. Id. at 299.
As a result of the West Virginia regulation language "[a]lthough a ``release' may indeed arise from an ``omission,' there still remains the limitation that a landowner, in order to be deemed the owner of a ``source,' must be in control of a ``facility' or otherwise engaged in an activity that causes such a release." Id. Accordingly, pursuant to the West Virginia regulation, the owner of a "source" may not be subject to a remediation order "where it is demonstrated that neither the landowner nor its predecessors in title were involved in originating such pollution." Id. at 299-300.
The use of the term "source" and its definition distinguish the West Virginia statute at issue in Cookman Realty Group from the Rhode Island OPCA. For example, the OPCA fails to include the terms "source," "activity," or "facility," like the West Virginia regulation; instead, in the Rhode Island OPCA, the broad definition of person includes "an individual, trust, firm, joint stock company, corporation, . . . club, non profit *Page 17
agency, country." Compare
W. Va. Code R. § 47-57-4.1 with Sec.
IPRRA, like the federal Comprehensive Environmental Response, Compensation and Liability Act ("CERCLA"), 10 excludes "petroleum" under its definition for hazardous substances. G.L. 1956 §
Rhode Island courts afford great deference to agency decisions under the "arbitrary and capricious" standard of review.Goncalves v. NMU Pension Trust,
On December 2, 2002, DEM issued a Letter of Responsibility to GPM, Power Test, and GPC. (Letter of Responsibility.) This letter notified these parties that the likely source of the petroleum found on the land and waters of the state was from Power Test's *Page 20 property. Id. (stating that "[t]he likely source of the petroleum was the abutting pipeline easement controlled by Getty Properties Corp. (``the Site')"). In response to this letter, Power Test, GPM, and GPC notified DEM of their intent to not comply with the requirements set forth within the letter. (NOV at 4.)
In its decision, DEM noted that the LNAPL in question was observed on March 22, 2002. (Decision at 4.) Additionally, DEM explained that on July 21, 2003, DEM issued a Notice of Intent to Enforce to Power Test. Id. at 4. It concluded in its finding of facts that "the presence of the petroleum product in the groundwater was made known to [Power Test] on or after March 22, 2002."Id. at 33. The correspondence between DEM and Power Test, including the Letter of Responsibility and Notice of Intent to Enforce, represents competent evidence that Power Test had knowledge of the violation. Accordingly, DEM's decision is not arbitrary or capricious.
"The process by which moving fluid separates the soluble components of a material. Under CERCLA, leaching is considered a release of contaminants. The term is sometimes used to describe the migration of contaminating materials, by rain or groundwater, from a fixed source, such as a landfill.
42 U.S.C.A. § 9601 (22)."
"the owner and operator of the vessel or facility would be deemed insurers for a harm flowing from what made the activity hazardous in the first place: a release of oil or hazardous substance. The culprit for purposes of causation was the vessel or facility, and both the owner and operator would be liable regardless of whether their individual conduct caused the release. . . . [T]he owner of a vessel might not have personally engaged in any direct conduct causing a release but the act of ownership would be sufficient for strict liability." James R. MacAyeal, "The Comprehensive Environmental Response, Compensation, and Liability Act: The Paradigm of Strict Liability and the Problem of Individual Causation," 18 UCLA J. Envtl. L. Pol'y 217, 273 (2000) (emphasis added) (discussing the strict liability scheme within the Clean Water Act).
*Page 1
Castaic Lake Water Agency v. Whittaker Corp. ( 2003 )
Sartor v. Coastal Resources Management Council ( 1988 )
carson-harbor-village-ltd-a-limited-partnership-dba-carson-harbor ( 2001 )
Doyle v. Paul Revere Life Insurance ( 1998 )
RI Pub. Tel. Auth. v. RI Labor Rel. Bd. ( 1994 )
Abb Industrial Systems, Inc. v. Prime Technology, Inc., ... ( 1997 )
United States v. Coastal States Crude Gathering Company ( 1981 )
L.B. Foster Co. v. State ( 2003 )
Pawtucket Power Associates Ltd. v. City of Pawtucket ( 1993 )
Labor Ready Northeast, Inc. v. McConaghy ( 2004 )
United States v. City of New York ( 1979 )
Gollobin v. Air Distributing Co., Inc. ( 1993 )
United States v. Dixie Carriers, Inc., and Water Quality ... ( 1980 )
Environmental Scientific Corp. v. Durfee ( 1993 )
Goncalves v. NMU Pension Trust ( 2003 )
Iselin v. Retirement Board of the Employees' Retirement ... ( 2008 )
Town of Burrillville v. Rhode Island State Labor Relations ... ( 2007 )