DocketNumber: C.A. 89-2447
Judges: <underline>GIBNEY, J.</underline>
Filed Date: 2/10/1994
Status: Non-Precedential
Modified Date: 4/18/2021
For financial and tax purposes many business entities were used in implementing each phase of the project. However, these various entities comprised the same individual persons and operated as coadunate components of the larger business enterprise. Woodland Manor III Associates, the plaintiff in this action, is a Rhode Island limited partnership to which MDC transferred land in completing the final phase of the long term multi-phase project.
Following the original purchase of the land, MDC needed to determine the amount and location of the buildable land as situated upon the eight-nine acre tract. In pursuit of this interest MDC sought to determine the jurisdiction of the Department of Natural Resources (now called the Department of Environmental Management; hereinafter simply "the Department") over the subject parcel. Such jurisdiction derived from the Freshwater Wetlands Act. Pursuant to this statutory scheme as codified in G.L. 1956 § 2-8-8 et seq., in June, 1974, a representative of the MDC filed a "Request for Freshwater Wetlands Applicability Determination" (hereinafter "Request").
At the evidentiary hearing Messrs. Giordano, a general partner in Woodland Manor III Associates, and Peter Janaros, the Supervisor of the Department's Wetlands Division, testified about the Wetlands regulatory process. As part of the preliminary determination the Department first conducts an on-site inspection of the land and "flags" or delineates the wetlands in accordance with applicable regulations. Robert Rocchio, a land surveyor for the developer, testified that Michael Pickering, a Department wetland biologist, went to the site and established the 247.5 contour as the limit of disturbance. The Department then determines whether the proposed development would impact the delineated wetlands such that a "Formal Application" is necessary.
Attached to the Request filed in accordance with this procedure was a site plan prepared by C.E. Maguire, the engineering firm engaged by the developer. In response to this Request the Department sent the developer a letter dated June 17, 1974 which stated in part that:
Provided there is no construction or regrading below the 247.5 foot contour as shown on the above-referenced plan and that final grading and drainage plans and computations are submitted for review and approval of the Department prior to start of construction, it is our conclusion that the Fresh Water Wetlands Act does not, at this time, appear applicable to this proposal.
This language is central to the instant controversy.
Following this statement by the Department, the developer continued the process of presenting the project to the myriad state regulatory agencies whose permissions would eventually be needed in order for the project to reach completion as planned. This process had begun with the creation of a "bubble plan" which illustrated the general features of the entire project. This plan embodied the concept but not the details of the project and was used to assess the feasibility of the proposal. Following discussion, modification, and analysis of the "bubble plan" the developer created a "Master Plan." This plan contained a more detailed site plan of the "bubble plan" and served to provide a basis for coordination among the developer and all the state and local regularity agencies concerned.
One such area of concern was that of the sewage system. At the evidentiary hearing, Antone Giordano, on behalf of the developer, testified regarding the role of the then "Master Plan" in designing a sewage system to serve the project. Mr. Giordano stated that the magnitude of the project together with the localized high water table demanded the installation of a sewage system through the Town of Coventry to the project site. The "Master Plan" defined the scope and nature of the entire project so that the sewage needs could be computed and an appropriate design could be made. Indeed, a 3.5 mile sewer system was eventually sized, designed and installed at substantial expense for the multi-phase project.
In 1978 the developer was ready to begin construction of the first phase of the project, a nursing home entitled Woodland Manor I, and submitted a final grading and drainage plan to the Department pursuant to the 1974 letter. The Department responded to this submission in a letter dated June 29, 1978 which stated in pertinent part:
Under the following provisions: adequate measures are taken to prevent sediments from entering adjacent wetlands . . . it is our conclusion that the fresh water act does not appear applicable to this proposal. (emphasis added).
Similarly, in 1980, the developer submitted a final drainage and grading plan for another phase of the project, a nursing home owned by Coventry Health Center Associates. The Department responded by stating:
Under the following provisions, . . . adequate measures are taken to prevent sediments from entering adjacent wetlands . . . it is our conclusion that this proposal represents an insignificant alteration of a freshwater wetland. Therefore, under the aforementioned provisions, a permit to alter freshwater wetlands will not be required. (emphasis added).
The event precipitating the instant controversy over the scope and import of the 1974 letter occurred after the completion of all but the final phase of construction. In August, 1986, the Department responded to a submission by the plaintiff Woodland Manor Associates (WMA) seeking the approval of the final grading and drainage plan for the last phase of construction pursuant to the 1974 letter. The 1986 letter contained the following language:
Proposed alteration, including filling, vegetative clearing, grading, building construction, tennis court and drainage installation will result in encroachment, significant loss, disturbance and alteration of the natural characteristics of a freshwater wetland, adversely impacting wildlife habitat value, recreational value, and groundwater recharge and quality. Be advised that the public value of the wetland, its outstanding wildlife habitat value and its location within one of this state's primary groundwater reservoirs, require that the wetland receive the highest level of protection. As proposed, this project has the highest probability of being denied by the department's Freshwater Wetlands Section.
The letter further stated that a formal wetland application would be required by law. The parties scheduled a series of meetings commencing in September, 1986 in an attempt to resolve this matter. These efforts failed and in May, 1989, plaintiff filed this action.
In respect to the threshold issue raised by the Department, our Supreme Court has stated on many occasions that "exhaustion of administrative remedies will not be required when those remedies are inadequate and may result in a futile exercise."Greenwich Bay Yacht Basin Association v. Brown,
In reaching the more substantive issue raised in this matter this Court agrees with the plaintiff that the 1974 letter forms a representation critical to an equitable estoppel analysis.
Our Supreme Court has most recently addressed the doctrine of equitable estoppel as applied against governmental agencies inGreenwich Bay Yacht Basin Association v. Brown,
In Greenwich Bay the Court relied on a line of cases that had announced the rule that "building permits lawfully issued for a permitted use should be immune to impairment or revocation by reason of a subsequent amendment to the zoning evidence when the holders thereof, acting in reliance thereon, in good faith, initiate construction in some reasonably substantial measure or incur some reasonably substantial obligation promoting such construction." Shalvey v. Zoning Board of Review of the City ofWarwick,
As articulated, the above rule encompasses three elements: substantial performance undertaken; in reliance on the permit; in good faith. In formulating this rule the court in Shalvey was careful to point out the policy underlying it. The court wrote, "in our opinion the rule thus stated promotes justice by protecting the interests of a permittee who has acted under a permit in good faith but withholding protection from permits where good faith does not appear, and thus protects the public interest in an effective regulation of land uses." Shalvey, 210 A.2d at 593. This statement recognizes the tension between the public interest in land use regulation and an individual's interest in conducting affairs in reliance on the actions of governmental agencies.
In applying the above elements to this matter this Court relies substantially on the credible testimony of Antone Giordano, a general partner of the plaintiff partnership who testified for both sides at the hearing. This Court found Mr. Giordano's testimony consistent, forthcoming, and plausible. His testimony was corroborated by Robert Rocchio and Peter Janaros, the Department's wetlands supervisor from 1978-1987, who also testified on behalf of the plaintiff. The Department, on the other hand, put on Charles Horbert, a wetlands biologist, and Ray Larson, a professional engineer. These witnesses testified regarding technical aspects of delineating wetlands in an attempt to discount the 247.5 elevation as an immutable determination. This Court is unpersuaded by their testimony as it applies here to an estoppel theory.
With respect to the first element of substantial performance undertaken, this Court finds that the design and construction of the entire project was predicated on the developer being able to build up to the 247.5 foot elevation. The cost of the sewer system alone, just one aspect of the project designed to serve the entire development, constituted substantial performance. Accordingly, this first element is satisfied.
The second element of the estoppel doctrine requires reliance on a representation, here the 1974 letter. This Court is satisfied that such reliance occurred. This point is supported by observing the procedure the Department had followed when administering the earlier phases of the project.
The third element of good faith presents the most elusive requirement. Determining good faith turns largely on reasonableness and honesty. See, e.g., Goodman v. Turner,
The Department contends that the meaning of the 1974 letter is clear and unambiguous in that it states that future construction could proceed only upon the submission of final grading and drainage plans to the Department for approval. The Court finds this interpretation unreasonable in that it would render the contour line referenced in the 1974 letter a nullity. Were the Court to accept this interpretation the Department would be free to make demands upon the developer without regard to the 247.5 foot elevation that was established after careful procedures and stated plainly in the letter as a guideline for future action.
On the other hand the Court agrees with the plaintiff's interpretation of the letter as establishing the limit of disturbance to the contours line thereby delimiting the jurisdiction of the Department. The testimony elicited at the hearing, by supplying the context of the letter, persuaded the Court that the Department was aware of the scale of the project at the time the letter was written and knew or should have known that the developer would rely, and would be reasonable in relying, on the critical elevation as applied to the entire project. This testimony also revealed, in this Court's opinion, the honest intentions of the developer.
Accordingly, this Court is satisfied that the Department should be equitably estopped from requiring a formal wetlands application on the basis of any disturbance above the 247.5 foot elevation that does not adversely impact areas below the elevation and otherwise within the Department's jurisdiction. This concern for adjacent wetlands was made apparent to the developer throughout the phases in above referenced letters dated June 29, 1978; January 15, 1980; and January 19, 1981. In light of this notice it would be unreasonable for the plaintiff to insist that the 1974 letter would allow any disturbance whatsoever occurring above the 247.5 foot elevation.
Counsel shall prepare an appropriate judgment for entry.