DocketNumber: PM 00-0408
Judges: GIBNEY, J.
Filed Date: 6/7/2002
Status: Precedential
Modified Date: 7/6/2016
R.J.P. supervised the construction process from 1998 through the summer of 1999. Sometimes R.J.P. performed the construction work itself, and sometimes it hired subcontractors. However, no matter who did the work, the Millers were never satisfied with the results. The Millers frequently relayed their complaints to R.J.P. In early September of 1999, after more than a year of conflict, the Millers fired R.J.P. R.J.P. attempted to collect $55,591.44 from the Millers, which amount R.J.P. claimed as the outstanding balance for the work it had performed. The Millers refused to pay.
R.J.P. instituted the instant Petition to Enforce Mechanic's Lien against the subject property in order to facilitate collection of the outstanding balance. In its prayer for relief, R.J.P.'s complaint requested "[t]hat Judgment enter against the Defendants . . . in the amount of $55,181.44, plus interest and costs, and that the Lien be enforced against the real estate . . . ." The Millers responded to the Petition by filing a Statement of Claim, which alleged that R.J.P. "failed and refused to complete the work" on the house and that the work it performed was "unsatisfactory, unworkmanlike and [done in a] negligent manner, resulting in significant damage. . . ."
Prior to commencement of the trial in the instant action, the Millers filed a separate action against R.J.P. seeking damages for breach of contract and negligence. (P.C. 2001-5669). Subsequently, the Millers moved to consolidate the two actions. However, even though the issues in both actions were likely to be the same, the Millers' motion to consolidate was denied because consolidation of the actions would lead to a delay in contravention of R.J.P.'s right to expedited process in the mechanic's lien action.
This Court held a nonjury trial over several days in November 2001.1 At trial, the two key disputed issues were the quality of R.J.P.'s workmanship and the employment status of Simon Mourato (Mourato), a stone mason, whose work-product formed the basis of the most expensive of the Millers' complaints. Including two experts, the Millers presented no fewer than six witnesses to support their position regarding the allegedly defective work. Additionally, the Millers offered over 70 exhibits into evidence.
In lieu of closing arguments, each side submitted a memorandum summarizing its claims. In its Post Trial Memorandum, R.J.P. concluded that "Plaintiff is entitled to $51,335.40, plus interest, costs, and reasonable attorney's fees."2 Conversely, in their Summation Memorandum, the Millers concluded that "due to the plaintiffs [sic] breach of contract and negligence, as well as the negligence of the Mason . . . the defendants have incurred expenses in the amount of $37,145.79, plus future expenses to repair the property in the amount of approximately $240,000.00."
On May 7, 2002, this Court ruled that R.J.P. failed to comply with the Mechanic's Lien statute, denied its Petition to Enforce, and awarded the Millers costs and attorney's fees in the amount of $14,849. Additionally, this Court ruled that R.J.P. remained responsible for the employment of the stone mason, Mourato. This Court also found that R.J.P. violated the implied warranty of workmanship in a variety of ways, entitling the Millers to relief from payment in the amount of $26,546.58, and directed the Millers to pay $14,195.86 on the balance of R.J.P.'s claim. In calculating the outstanding balance owed to R.J.P., the amount for which R.J.P. requested judgment on multiple occasions, this Court specifically denied some of the Millers' more expensive assertions of deficient work3 and limited the Millers' relief on others due to insufficient proof.4
Concerned about the res judicata effects of this Court's Decision on their separate pending action, the Millers now move this Court to vacate its findings of fact regarding the amount of relief that this Court granted to the Millers based on their assertions of deficient work. Particularly, the Millers claim that this Court's analysis of the Petition should have ceased following its conclusion that R.J.P. failed to comply with the statute. Although the Millers "concede that they did in fact present evidence that the plaintiff breached the terms of the contract," the Millers maintain that they were required to introduce such evidence to "challenge the value [of the materials and labor] added to the property" "in the event the Court ruled against the defendants on plaintiff's petition to enforce." (Defendants' Memo. at 2-3.) Because their Motion to Consolidate was denied, the Millers argue that they were forced to partially litigate similar, but not identical, issues in two different actions. Therefore, the Millers ask this Court to vacate the implied warranty section of its Decision in order to present additional evidence on the issue at a subsequent jury trial against R.J.P. and Mourato.
A motion for relief from a judgment under Rule 60(b) of Superior Court Rules of Civil Procedure "is addressed to the trial justice's sound judicial discretion and his [or her] ruling will not be disturbed on appeal absent a showing of an abuse of discretion or an error of law." SeeCasa DiMario, Inc. v. Richardson,
In the present case, the Millers title their request a "Motion to Reconsider." Within the Motion itself, however, the Millers specifically ask the Court to vacate its May 7, 2002 Decision. Therefore, this Court will treat Defendants' Motion pursuant to Rule 60(b).
Pursuant to the liberal pleading requirements provided by the Superior Court Rules of Civil Procedure, this Court read the Petition to Enforce and the other materials submitted by both parties requesting a determination of the quality of R.J.P.'s workmanship and the outstanding balance owed by the Millers. See Super. R. Civ. P. Rules 1 and 8. This Court then conducted a trial, at which time the parties presented a substantial quantity of evidence on these two issues. At best, in this motion, the Millers now ask this Court to reconsider alleged mistakes of law concerning this Court's interpretation of the pleadings and the scope of this Court's rulings on R.J.P.'s Petition.5 However, such errors of law cannot form the basis of a motion to vacate under Rule 60(b). SeeJackson, 734 A.2d at 507. Consequently, the Millers' Motion to Reconsider must be and is denied.
As a practical matter, this Court must also deny the instant Motion for the same reason that the Millers claim they were required to provide potentially duplicative evidence relating to the value of the defective work. The present matter was tried before this Court without a jury. As such, this Court was required to make findings of fact and conclusions of law.6 See Hood v. Hawkins,
All counsel shall submit appropriate judgments for entry both in this matter and in the May 7, 2002 Decision.
"Although not specifically raised herein, the defendants do not concede the Court's findings relative to cost of repair/replacement, etc., and reserve the right to address these issues in oral argument should the Court order an oral presentation on the issues raised herein." (Memo. at 4.)
Inasmuch as this can be read as a motion for another hearing in this matter, this Court does not believe that such "oral argument" would be helpful in resolving the issues raised herein. Therefore, the Millers' motion for an additional hearing in this case is denied.
Tilcon Gammino, Inc. v. Commercial Associates ( 1990 )
Bailey v. Algonquin Gas Transmission Co. ( 2002 )
marjorie-hatfield-v-the-board-of-county-commissioners-for-converse-county ( 1995 )
Bendix Corp. v. Norberg ( 1979 )
Casa DiMario, Inc. v. Richardson ( 2000 )