In January of 2001, Mr. and Mrs. Totman ("Plaintiffs") amended their Complaint to add an additional defendant. Since that time, several defendants have been withdrawn from the case either by motion or by settlement. The present application before this Court is GE's Motion for Summary Judgment. With regard to the Defendant, GE; Plaintiffs' allegations stem from the boiler work performed by Mr. Totman on U.S. Navy ships while he was employed at the Quincy ForeRiver Shipyard for Bethlehem Steel. In its Memorandum, GE argues that Plaintiffs' motion should be summarily denied on the grounds that discovery in this action demonstrates that Plaintiffs have no reasonable expectation of offering at trial either product identification evidence against GE or evidence that demonstrates a causal connection between Mr. Totman's alleged injuries and a product manufactured by GE.
According to GE, Mr. Totman did not identify at his January 19, 2001 deposition any asbestos-containing products manufactured by GE with which he may have worked or to which he may have been exposed. At his audiovisual deposition taken on January 24, 2001, he testified that he worked in the vicinity of marine turbines on occasion, although he had no responsibility for the marine turbines and never worked on them. (Mr. Totman's January 24, 2001 Deposition at 46, 49-50.) GE argues that Mr. Totman's identification of GE as one of the marine turbine manufacturers is merely unsubstantiated deposition testimony which does not constitute a prima facie case. GE also argues that the GE products alleged to be present where Mr. Totman worked did not contain thermal insulation. According to the affidavit of David Hobson (attached to Defendant's Memorandum as Exhibit C,) GE's marine turbines are complex mechanical devices made of various metal alloys and are manufactured and shipped with only a coat of paint on the surface of the metal. GE, he states, did not manufacture, sell, distribute, or supply marine turbines equipped with thermal insulation; nor did it specify the material to be used to insulate its marine turbines. According to Mr. Hobson, any thermal insulation materials, including thermal insulation blankets, that may have been applied to GE's marine turbines after they left GE's manufacturing facility would have been supplied and installed by entities other than GE. GE concludes that the Plaintiffs, having failed to produce sufficient evidence of product identification and/or exposure evidence against GE and having no reasonable expectation of producing any such evidence, have not met their burden in establishing a prima facie case of asbestos exposure. Therefore, GE contends that Summary Judgment is appropriate.
Plaintiffs rebut GE's motion by submitting the following evidence in support of their claim: Plaintiffs' interrogatory answers; Mr. Totman's testimony; GE's admissions in its Responses to Plaintiffs' Requests for Admission dated September 28, 2001; GE's admissions in its Responses to Plaintiff's Requests for Admission in the Perusse v. A.C. and S., Inc., et al., Superior Court, PC 2000-5768; the sworn affidavit of Edwin Fletcher, who worked at the Avondale Shipyards in the capacity of Chief Engineer and Vice President of Engineering and Vice President from 1955-1962; and the testimony of Anthony Vigliotta, an electrical inspector working in the Federal Shipbuilding shipyard in Kearny, N.J. from 1941 to 1943.
At the outset, this Court rejects Plaintiffs' proffer of evidence pertaining to certain admissions GE made in Perusse v. A.C. and S., Inc., et al., Superior Court, PC 2000-5768. This evidence is inadmissible as proof of the present claim. Rule 36(b) of the Superior Court Rules of Civil Procedure states:
"Effect of Admission. Any matter admitted under this rule [regarding "Requests for admission"] is conclusively established unless the court on motion permits withdrawal or amendment of the admission. . . . Any admission made by a party under this rule is for the purpose of the pending action only and is not an admission by the party for any other purpose nor may it be used against the party in any other proceeding except in a subsequent action between the same parties involving the same claim."
As GE's admission in the Perusse case is prohibited for any purpose beyond the Perusse claim, this Court will not consider it in determining the present Motion for Summary Judgment.
Plaintiffs refer first to their interrogatory answers in response to movant GE's arguments. The interrogatory answers list the job sites where Mr. Totman worked and the years he worked at those sites. According to their interrogatory answers, Mr. Totman worked at the Quincy ForeRiver Shipyard in Quincy, MA from approximately 1939 to 1946. (See, Plaintiffs' Exhibit 1.) Mr. Totman also indicates in his interrogatory answers the identity of several of the ships he recalls working on during this time period in his interrogatory answers. (See, id.) Additionally, Mr. Totman testified at his January 24, 2001 deposition that he worked on ships where GE turbines were being installed and insulated. (See, Plaintiffs' Exhibit 2.) Although he primarily worked on the boilers and in the fire rooms, he testified that he worked in the same vicinity where the turbines were being installed (Id. at 21, 46-51); that he often walked through the turbine areas while they were being worked on (Id. at 46-47, 50), and that on some occasions the fire room and turbine room were one and the same (Id. at 50).
Furthermore, Plaintiffs argue GE admitted in its Responses to Plaintiffs' Requests for Admission dated September 28, 2001 that it has done business in the State of Rhode Island (Plaintiffs' Exhibit 3, Resp. 1) and that it "manufactured and sold marine steam turbines for use on [eleven] ships on which Mr. Totman has claimed exposure. . . ." (Id., Resp. 2.) Additionally, GE stated that it "is in the process of searching for turbine files and, if they become available, GE will produce them to plaintiffs . . .," (Id., Resp. 4-8 and 10) and "is still in the process of searching for any existing master turbine files, service records, drawings, part lists, brochures, promotional materials, and specifications for the turbines on [Mr. Totman's] ships and GE's investigation will continue." (See, GE's response to Supplemental Interrogatories and Requests to Produce.) Therefore, Plaintiffs argue, summary judgment is both inappropriate (due to remaining factual issues) and premature (due to the outstanding discovery).
In addition, Plaintiffs submit the sworn affidavit of Edwin Fletcher, who worked at the Avondale Shipyards in the capacity of Chief Engineer and Vice President of Engineering and Vice President from 1955-1962. (See, Plaintiffs' Exhibit 5.) According to Mr. Fletcher's affidavit, asbestos-containing products were being used in the installation of a GE gas turbine aboard a barge. Mr. Fletcher noted that
"General Electric occasionally had representatives present during the installation of the gas turbine . . . [and that GE] provided specifications and/or drawings that detailed the requirements of insulation normally required. The installation of the large gas turbine included insulation with asbestos-containing cloths, cements, block, gaskets, and pipe covering." (Id., Resp. 4.)
Although, Mr. Fletcher was referring to a specific GE turbine not at issue in the present case, Plaintiffs argue a jury could reasonably infer that GE's marine turbines, or many of the turbines that Mr. Totman worked near, required the same asbestos-containing insulation, possessed the same specifications or had the same types of GE representatives on site directing work. This too, Plaintiffs argue, is a factual issue that needs to be fleshed out at trial.
Lastly, Plaintiffs submit the deposition testimony of electrical inspector, Anthony Vigliotta. Mr. Vigliotta was deposed regarding a different lawsuit entitled In re: New York City Asbestos Litigation on August 31, 1999; September 1, 1999; and September 2, 1999. (Plaintiffs' testimony is attached to Plaintiffs' Memorandum as Exhibits 6, 7, and 8.) Mr. Vigliotta testified that GE would have contractor representatives on site "representing their company working in the Federal Shipbuilding." (Plaintiffs' Exhibit 7 at 229.) "Any time a major assembly that related — belonged to a special company like . . . GE, there would always be a GE representative . . . to make sure that their equipment was being properly put in place and all that." (Plaintiffs' Exhibit 8 at 398-99.) He described the turbine area as a "high density" asbestos area. (Plaintiffs' Exhibit 6 at 390.) He noted that the turbines had to be covered with asbestos blankets and that he probably "got some exposure from examining and testing . . . the GE . . . components, of which there were many aboard the ship." (Plaintiffs' Exhibit 8 at 381.) He further testified that "usually, the turbines that were driving the generators were highly intense asbestos-related products that went onto it as far as the insulating of the turbines and the piping necessary to feed the turbines." (Id. at 387.)
In light of the foregoing, Plaintiffs argue they have amply presented their prima facie case. They argue the evidence of record when viewed in the light most favorable to them, creates a genuine issue of fact for a jury.
A party opposing the motion "cannot rely solely on mere allegations or on the denials contained in the pleadings to defeat the motion." Avco Corp. v. Aetna Casualty Surety Co.,
So extreme a remedy as summary judgment should not be used as a substitute for trial or as a device intended to impose a difficult burden on nonmoving party to save his [or her] day in court unless it is clear that no genuine issue of fact remains to be tried. North Am. Planning Corp. v. Guido,
Plaintiffs have set forth a prima facie case in which there are genuine issues of material fact to be decided at trial. Accordingly, GE's Motion for Summary Judgment is denied. Counsel shall prepare the appropriate order for entry.
Hydro-Manufacturing, Inc. v. Kayser-Roth Corp. , 1994 R.I. LEXIS 124 ( 1994 )
Avco Corp. v. Aetna Casualty & Surety Co. , 1996 R.I. LEXIS 179 ( 1996 )
NORTH AMERICAN PLANNING CORPORATION v. Guido , 110 R.I. 22 ( 1972 )
Hueston v. Narragansett Tennis Club, Inc. , 1986 R.I. LEXIS 388 ( 1986 )
Volino v. General Dynamics , 1988 R.I. LEXIS 51 ( 1988 )
Gorman v. Abbott Laboratories , 1991 R.I. LEXIS 203 ( 1991 )
DeChristofaro v. MacHala , 685 A.2d 258 ( 1996 )
Nichols v. R.R. Beaufort & Associates, Inc. , 1999 R.I. LEXIS 63 ( 1999 )
Mitchell v. Mitchell , 2000 R.I. LEXIS 157 ( 2000 )