DocketNumber: Appellate Case No. 2012-213563; No. 5281
Judges: Few, Lockemy, Thomas
Filed Date: 12/3/2014
Status: Precedential
Modified Date: 11/14/2024
Rizón Commercial Contracting, Inc. appeals the circuit court’s order vacating its mechanic’s liens and dismissing its counterclaim for foreclosure. We find the circuit court erred in determining as a matter of law that Rizón was not a “laborer” that performed work “for the improvement of real estate” under subsection 29-5-20(A) of the South Carolina Code (2007). We reverse and remand for foreclosure proceedings.
I. Facts and Procedural History
In 2010, the Greens of Rock Hill, LLC and GRH 2011, LLC (collectively the “owners”) initiated the “Riverwalk development project,” which involved developing several pieces of property on the Catawba River in Rock Hill into a large, mixed-use community. The owners hired Celriver Services, LLC to serve as the general contractor for portions of the development project, which included demolishing an abandoned manufacturing facility on the property, grading the land, and installing roads andl infrastructure.
Following the demolition of the manufacturing facility, large pieces of “scrap concrete” remained on the property. Celriver
The Work to be performed by the Subcontractor [Rizón] includes mobilization of all labor, equipment, materials and other items required to crush and screen 30,000 tons of concrete stockpiled [on the property]. The concrete material is to be crushed and screened, as required, to meet the South Carolina Department of Transportation specifications for Graded Aggregate Base....
Rizón paid for the rental equipment used to crush the concrete and for all expenses incurred in completing the contract, including labor and operating costs. Upon completion of the work, Celriver moved the crushed concrete to “various sites” on the property, where it was used as a paving base for roads, sidewalks, and parking lots.
Rizón subsequently filed mechanic’s liens against the River-walk property pursuant to section 29-5-20, claiming it was owed $295,591 for the work it performed. The owners filed a petition to vacate the liens, claiming Rizón “did not provide labor, material, or supplies for the improvement of real property” and was thus “not entitled to a mechanic’s lien.” Rizón filed an answer and counterclaim seeking foreclosure.
The trial court issued an order vacating Rizon’s mechanic’s liens and dismissing its foreclosure claim. The court found Rizón was not a laborer because it “did not ... do anything to improve the real estate.” Although the court acknowledged that “crushing the concrete may have been a benefit to Celriver,” it determined this work, by itself, “did not improve
II. Rizon’s Entitlement to Mechanic’s Liens
Mechanic’s liens “are purely statutory and may be acquired and enforced only in accordance with the terms and conditions set forth in the statutes creating them.” Ferguson Fire & Fabrication, Inc. v. Preferred Fire Prot, L.L.C., 409 S.C. 331, 340, 762 S.E.2d 561, 565 (2014). According to subsection 29-5-20(A), “[e]very laborer, mechanic, subcontractor, or person furnishing material for the improvement of real estate ... has a lien thereon ... to the value of the labor or material so furnished.” The purpose of subsection 29-5-20(A) “is to protect a party who provides labor or materials for the improvement of property but does not have a contractual relationship with the property owner.” Sloan Constr. Co. v. Southco Grassing, Inc., 377 S.C. 108, 121, 659 S.E.2d 158, 165 (2008).
The circuit court vacated Rizon’s mechanic’s liens based on the procedure approved by the supreme court in Sea Pines Co. v. Kiawah Island Co., 268 S.C. 153, 157, 232 S.E.2d 501, 502 (1977), which allows the circuit court to consider the propriety of a mechanic’s lien under a standard that “may be ... likened to the [courtj’s authority to grant a summary judgment if there is no genuine issue of material fact to be determined.” We hold the circuit court erred by vacating the liens. Viewing the evidence in the light most favorable to Rizón, we find Rizón was a “laborer” that performed work “for the improvement of real estate,” which entitles it to a mechanic’s lien under subsection 29-5-20(A). See Wachovia Bank, N.A. v. Coffey, 404 S.C. 421, 425, 746 S.E.2d 35, 38 (2013) (stating that when considering a motion for summary judgment, “the evidence and all inferences which can reasonably be drawn therefrom must be viewed in the light most favorable to the nonmoving party”).
The owners admit the concrete crushed by Rizón “was used to improve the property,” but contend the sole task for which Rizón contracted did not, by itself, improve the real estate. We disagree. Celriver hired Rizón to accomplish two tasks: (1)
We find further support for our holding in certain sections ot~ the mechanic's lien statute. As this court stated in A. V.A., "There has been over the years a tendency of the General Assembly to liberalize the mechanic's lien statute, making available each time a lien to additional providers of labor and materials." 303 S.C. at 335, 400 S.E.2d at 500. The legislature has expanded the scope of the mechanic's lien statute to cover persons performing a component of the labor necessary to complete construction and development projects, even though "the labor performed [did not] go into something which has attached to and become a part of the real estate." George A.Z. Johnson, Jr., Inc. v. Barnhill, 279 S.C. 242, 245, 306 S.E.2d 216, 218 (1983). For example, a person "who provides a landscape service," which includes "land clearing, grading, filling, plant removal, natural obstruction removal, or other preparation of land," is entitled to a mechanic's lien under section 29-5-20. S.C.Code Ann. § 29-5-26 (Supp.2013). Additionally, South Carolina Code section 29-5-27 (2007) states, "Ai~y person providing construction and demolition debris disposal services, . .. including, but not limited to, final disposal services ... is a laborer within the meaning of Section[] 29-5-20."
III. Conclusion
We hold the circuit court erred in vacating Rizon’s mechanic’s liens and dismissing its foreclosure action as a matter of law. Therefore, the order of the circuit court is REVERSED and the case REMANDED for the court to hold foreclosure proceedings consistent with this decision.
. The owners included with their petition to vacate the mechanic’s liens a written contract between Celriver and Rizón dated 2010. Rizon’s owner claimed in an affidavit, however, that "the contract from 2010 was not the contract under which [Rizón was] working.” At oral argument, Rizón told the court Celriver initially hired Rizón in 2010 to crush the scrap concrete, and the 2010 contract covered the work performed by Rizón for that year. Rizón explained, however, that there was no written contract covering the work performed in 2011, which is the work relevant to this litigation. Notwithstanding this, Rizón admitted that the terms of the oral contract established in 2011 were "substantially the same” as those provided in the 2010 written contract. This is supported by the affidavit of Dave Williams, Vice President of Celriver, which used the same language contained in the 2010 contract to describe the work to be performed by Rizón under the 2011 contract.
. The circuit court also found (1) Rizón did not furnish the material that was used to improve the property because "Rizon's sole task was simply to change the form of the scrap concrete supplied by others into stone usable in the construction of roads”; and (2) "Rizón was not a subcontractor as it relates to the improvement of the subject real estate” because “there is no indication that Celriver’s contract with the Owners required crushing of the concrete in order that it could be used in building roads and sidewalks.” We decline to address these findings because our conclusion that Rizón is a laborer under subsection 29-5-20(A) is sufficient to support our holding. See § 29-5-20(A) (providing a mechanic’s lien to "[e]very laborer, mechanic, subcontractor, or person furnishing material” (emphasis added)). We also do not address Rizon’s argument that the circuit court erred in ruling on the owners’ petition without allowing discovery because our holding is dispositive of this issue. See Futch v. McAllister Towing of Georgetown, Inc., 335 S.C. 598, 613, 518 S.E.2d 591, 598 (1999) (declining to address other issues raised by appellant because resolution of a prior issue was dispositive).