DocketNumber: 28401
Citation Numbers: 2018 SD 67, 918 N.W.2d 396
Judges: Severson, Kern
Filed Date: 9/19/2018
Status: Precedential
Modified Date: 10/19/2024
[¶1.] Domson, Inc. brought suit against Dakota Engineering and Kadrmas, Lee and Jackson (KLJ) for professional negligence.
Background
[¶2.] The Oglala Sioux Tribe hired Dakota Engineering/KLJ to design a road reconstruction project on the Pine Ridge Indian Reservation. On March 21, 2012, the Tribe advertised the project for bids. Prospective bidders could inspect the contract documents, including the drawings and project manual. It is unclear whether Dakota Engineering or KLJ prepared the bid documents, including the project manual, the proposal to bidders, plans, specifications, estimates, and amendments for the project. However, the record reveals that the manual and documents relevant to the request for bids were signed and sealed in March 2012 by Tonya Tordsen of KLJ.
[¶3.] It is undisputed that Domson obtained the bid documents and submitted a bid on the project. The public bid opening revealed Domson as the apparent low bidder. KLJ informed Domson that Domson had been awarded the bid. On July 5, 2012, Domson and the Tribe executed a contract for the project. The contract between Domson and the Tribe designated Dakota Engineering/KLJ as the "Engineer" and the Tribe's representative. The contract provided that "Engineer assumes all duties and responsibilities, and has the rights and authority assigned to Engineer in the Contract Documents in connection with the completion of the Work in accordance with the Contract Documents." KLJ had the duty to administer the contract for the Tribe, including the processing of applications for payment by Domson. Change orders and payments needed approval from the Tribe.
[¶4.] It is undisputed that Domson did not substantially complete the project in the time required under the contract. KLJ, as the Tribe's representative, assessed Domson $103,950 in liquidated damages. In January 2015, Domson brought suit against Dakota Engineering and KLJ, alleging professional negligence. Domson asserted that "Dakota Engineering/KLJ owed a duty to Domson to reasonably draft, interpret, and apply the project's contract documents." Domson alleged that "Dakota Engineering/KLJ were negligent in their design, interpretation, and application of the plans and specifications[.]" According to Domson, Dakota Engineering/KLJ's negligence in designing and administering the contract caused Domson approximately $1,138,027.28 in damages.
[¶5.] Dakota Engineering and KLJ filed a joint answer. Dakota Engineering denied that it was a proper defendant because Dakota Engineering's "only involvement was initial design work[.]" Dakota Engineering/ KLJ asserted that Domson's alleged damages arose out of its contract with the Tribe. Dakota Engineering and KLJ filed a joint motion for summary judgment. They again indicated that Dakota Engineering was only involved in the design work and did not administer the contract. Dakota Engineering/KLJ also highlighted Paragraph 9.09 of the standard general conditions contract document. That paragraph provides:
Neither Engineer's authority or responsibility under this Article 9 or under any other provision of the Contract Documents nor any decision made by Engineer in good faith either to exercise or not exercise such authority or responsibility or the undertaking, exercise, or performance of any authority or responsibility *400by Engineer shall create, impose, or give rise to any duty in contract, tort, or otherwise owed by Engineer to Contractor, or any Subcontractor, any Supplier, any other individual or entity, or to any surety for or employee or agent of any of them.
(Emphasis added.)
[¶6.] Domson did not submit "a separate, short, and concise statement of the material facts as to which" it contended a genuine issue existed as required by SDCL 15-6-56(c)(2). Instead, it submitted a brief in opposition to the motion for summary judgment. But the brief did not "respond to each numbered paragraph in the moving party's statement with a separately numbered response and appropriate citations to the record." See id. Rather, Domson's brief grouped arguments together with general responses. Domson's brief also did not cite to the record. Nevertheless, in the brief, Domson referred the circuit court to Mid-Western Electric, Inc. v. DeWild Grant Reckert & Associates, Co. , as authority for recognizing that Dakota Engineering/KLJ owed a duty to Domson to reasonably draft, interpret, and apply the project's contract documents.
[¶7.] The circuit court issued a memorandum decision. The court granted summary judgment on all claims against Dakota Engineering. It concluded that Dakota Engineering was not an appropriate party in the lawsuit. The court also granted summary judgment on all claims against KLJ. Although Domson did not comply with SDCL 15-6-56(c)(2), the court gave Domson "the benefit of the doubt with what [it had] submitted" in response to the motion for summary judgment. After considering Domson's submissions, the court concluded that Domson offered mere general allegations and denials. The court also interpreted Paragraph 9.09 to insulate KLJ from liability to Domson for negligence, absent a claim by Domson that KLJ acted in bad faith.
[¶8.] In response to the court's decision, Domson filed a motion and brief in support requesting the circuit court reconsider its decision granting summary judgment. It asserted that Paragraph 9.09 was unlawful under SDCL 53-9-3. Domson then filed a supplemental brief in support of its motion for reconsideration. It restated its position that because KLJ owed it a duty, a jury must determine whether KLJ breached that duty. The court denied Domson's motion to reconsider.
[¶9.] Domson appeals and asserts the following issues, which we restate as follows:
1. Whether summary judgment was improper because defendants failed to plead Paragraph 9.09 as an affirmative defense.
2. Whether the circuit court erred when it granted summary judgment based on Paragraph 9.09 of the standard general conditions contract document.
3. Whether the circuit court erred when it granted summary judgment despite that defendants admitted they owed a duty to Domson.
Standard of Review
[¶10.] Under our well-settled standard of review on appeal from a grant of summary judgment:
We must determine whether the moving party demonstrated the absence of any genuine issue of material fact and showed entitlement to judgment on the merits as a matter of law. The evidence must be viewed most favorably to the *401nonmoving party and reasonable doubts should be resolved against the moving party. The nonmoving party, however, must present specific facts showing that a genuine, material issue for trial exists. Our task on appeal is to determine only whether a genuine issue of material fact exists and whether the law was correctly applied. If there exists any basis which supports the ruling of the trial court, affirmance of a summary judgment is proper.
Brandt v. Cty. of Pennington ,
Analysis
[¶11.] Domson contends that Dakota Engineering and KLJ could not rely on Paragraph 9.09 in the standard general conditions contract document to insulate themselves from liability because they failed to plead Paragraph 9.09 either in avoidance or as an affirmative defense. Dakota Engineering and KLJ respond that they asserted Paragraph 9.09 as a defense in their answer by pleading the affirmative defenses of estoppel and waiver. They also claim that Domson failed to raise waiver before the circuit court. We agree that Domson waived the issue. Because Domson failed to assert this argument to the circuit court, we will not address it for the first time on appeal. See Rush v. U.S. Bancorp Equip. Finance, Inc. ,
[¶12.] We combine Domson's next two issues because both relate to whether Dakota Engineering and KLJ owed Domson a duty under the circumstances. The circuit court recognized that under South Dakota law, an engineer can owe a duty to a contractor despite the lack of contractual privity between the parties. See Mid-Western Elec. ,
[¶13.] Domson argues that "the exculpatory clause should be construed as an indemnity provision that violates statute[,]" citing SDCL 56-3-16, -17. But Domson did not assert this argument to the circuit court, and further, it exceeds the scope of this Court's inquiry on supplemental briefing. We, therefore, decline to address whether Paragraph 9.09 should be construed as an indemnity provision. For the same reason, we decline to examine Domson's claim that Paragraph 9.09 is unconscionable and its argument in its supplemental brief that the contract between the Tribe and Domson is a contract of adhesion. See Rush ,
[¶14.] Nonetheless, Domson further claims that Paragraph 9.09 "is against the policy of the law" under SDCL 20-9-1, SDCL 53-9-3, and SDCL 53-9-1. It claims that SDCL 20-9-1 and SDCL 53-9-3 evince a public policy forbidding the enforcement of Paragraph 9.09. It also asserts that Lyndon Property Insurance Co. v. Duke Levy and Associates , "is persuasive authority on the unenforceability of an engineer's exculpatory clause."
[¶15.] It is well settled that "[a] contract provision contrary to an express provision of law or to the policy of express law ... is unlawful." SDCL 53-9-1.
*402Law Capital, Inc. v. Kettering ,
[¶16.] Although SDCL 20-9-1 mandates responsibility for injury caused by willful acts or want of ordinary care or skill, nothing in this statute prohibits one party from agreeing by contract to release a third party from liability for ordinary negligence. See, e.g. , Lee v. Beauchene ,
[¶17.] We next address Domson's claim that this Court should adopt the view that exculpatory clauses such as Paragraph 9.09 are unenforceable based on the reasoning espoused in Lyndon Prop. Ins. Co. ,
[¶18.] In Lyndon , the Fifth Circuit Court of Appeals examined the enforceability of exculpatory language similar to that in Paragraph 9.09.
[¶19.] Here, however, Domson is not seeking to stand in the shoes of the Tribe in its suit against Dakota Engineering and KLJ. Moreover, the doctrine of equitable subrogation is not implicated. Transpower Constructors is likewise distinguishable. In Transpower Constructors , the court found the exculpatory clause unenforceable because of ambiguity, not because of public policy.
[¶20.] "[T]his Court has cautioned ever since territorial days" that " '[t]he power of courts to declare a contract void for being in contravention of sound public policy, is a very delicate and undefined power; and, like the power to declare a statute unconstitutional, should be exercised only in cases free from doubt.' " Law Capital ,
[¶21.] This is not to say that every exculpatory clause insulating a third party from liability for negligence will be enforceable. Nor does today's decision mean that we adopt the views expressed by the authorities cited by Dakota Engineering/KLJ in response to this Court's request for supplemental briefing. Rather, Paragraph 9.09 is valid and enforceable in this case because Domson has not identified that Paragraph 9.09 contravenes sound public policy in this State under these particular circumstances. The exculpatory language unambiguously informed Domson that Dakota Engineering/KLJ would be immune from suit in tort or contract arising out of Dakota Engineering/KLJ's good-faith acts and failures to act by the authority given to them under the contract and contract documents.
[¶22.] Although we hold that Paragraph 9.09 is valid and enforceable under the circumstances, Dakota Engineering and KLJ must still establish entitlement to the protections afforded by Paragraph 9.09. When the circuit court granted summary judgment, relying on Paragraph 9.09, it erroneously imposed the initial burden on Domson to establish bad faith on the part of the engineer. Paragraph 9.09 is an affirmative defense. As the party asserting the defense, Dakota Engineering and KLJ had the burden of showing that they acted in good faith. See Klein v. Sanford USD Med. Ctr. ,
[¶23.] As we recognized in Klein , the party asserting the affirmative defense must establish a prima facie case of good faith.
[¶24.] Domson alleged that Dakota Engineering and KLJ were negligent in their interpretation and application of the plans and specifications for the project, which negligence harmed Domson. In response, Dakota Engineering/KLJ claimed that their interpretation and application of the project documents met their professional responsibilities and was appropriate under the circumstances. Dakota Engineering/KLJ relied on letters sent between Domson and KLJ and on the deposition testimony of defendant representatives as evidence of Domson's failures throughout the project.
[¶25.] Good faith is not defined in Paragraph 9.09. This Court has defined "good faith" in the context of immunity statutes, in estate cases, in cases of breach of contract under the Uniform Commercial Code, and in insurance cases. See Klein ,
[G]ood faith is an 'excluder.' It is a phrase without general meaning (or meanings) of its own and serves to exclude a wide range of heterogeneous forms of bad faith. In a particular context the phrase takes on specific meaning, but usually this is only by way of contrast with the specific form of bad faith actually or hypothetically ruled out.
Garrett ,
[¶26.] Based on our review of the record, Dakota Engineering/KLJ established a prima facie case of good faith against Domson's claim of negligent interpretation and application, implicating the protections under Paragraph 9.09. Therefore, as the party resisting summary judgment, Domson was required to identify a material issue of fact in dispute on the question of Dakota Engineering/KLJ's good-faith acts and failures to act. See Klein ,
[¶27.] Although Domson presented evidence that Dakota Engineering/KLJ allegedly performed below acceptable engineering standards in administering the contract, Domson has not identified, in response to Dakota Engineering/KLJ's prima facie showing, that a material issue of fact is in dispute on whether Dakota Engineering/KLJ acts or failures to act lacked good faith. Rather, Domson relies on general allegations and denials that because Dakota Engineering/KLJ performed below acceptable standards, their actions necessarily lacked good faith. But a party may not resist summary judgment with mere denials and allegations. Tolle v. Lev ,
[¶28.] Domson's complaint also alleged a cause of action against Dakota Engineering/KLJ for negligent design . The complaint asserted that "it was readily foreseeable that Domson, who was bound to follow these documents prepared by the engineering firm , could be harmed by the engineering firm's negligent drafting or interpretation and application of the contract documents." (Emphasis added.) The circuit court did not examine whether a material issue of fact existed on this claim or whether Paragraph 9.09 insulated Dakota Engineering/KLJ from liability. It summarily dismissed Domson's entire suit. Nevertheless, "[c]ontract interpretation is a question of law reviewable de novo." Black Hills Excavating Servs., Inc. v. Retail Constr. Servs., Inc. ,
[¶29.] The plain language of the exculpatory clause only disclaimed Dakota Engineer/KLJ from liability in tort and contract for their "authority or responsibility under this Article 9 or under any other provision of the Contract Documents [or] any decision made by Engineer in good faith either to exercise or not exercise such authority or responsibility or the undertaking, exercise, or performance of any authority or responsibility by Engineer[.]" When Dakota Engineering or KLJ designed and drafted the plans and specifications for the project, Domson and the Tribe had not yet executed the contract. Therefore, Dakota Engineering/KLJ could not have been exercising authority or responsibility under Article 9 or under other provisions of the contract documents as provided in the contract between the Tribe and Domson.
[¶30.] In Mid-West Electric , we quoted Waldor Pump & Equipment v. Orr-Schelen-Mayeron & Associates , for the proposition that an engineering firm could owe a duty to reasonably draft and interpret the project specifications and that it is foreseeable that a contractor, bound to follow the specifications prepared by the engineering firm, could be harmed by the firm's negligence in drafting and interpreting the specifications.
[¶31.] Here, Dakota Engineering and KLJ do not dispute that they owed Domson a duty. Nevertheless, they assert that Domson has not identified a material issue of fact in dispute on the element of breach of that duty. They direct this Court to Domson's expert's letter opinion. In that letter, Kostaneski recognized that
[n]o set of project documents are perfect, nor are field conditions exactly as described in those documents. Consequently, projects have several strategies for adjusting to these changed conditions. Change orders are a commonly recognized method for dealing with any condition or circumstance that might arise and was unforeseen or overlooked at the time of document preparation.
[¶32.] In response, Domson argues that errors existed in the project and bid documents. It quoted excerpts from deposition testimony by Dakota Engineering/KLJ experts, in which depositions those witnesses purportedly admitted to the errors. In particular, they admitted that the formal artifact search had not been completed prior to the bid, which failure Domson claimed caused delay in completing the project. Domson also relied on its expert's opinion and on correspondence between Trig Domson and KLJ that many problems in the design phase were negligent, including that the documents did not identify an existing pipe, which omission Domson claimed affected grading.
[¶33.] While Domson's evidence establishes that errors existed in the project and bid documents, Domson has not demonstrated a genuine, material issue for trial concerning whether the existence of errors in a project's bid documents constituted a breach of the applicable standard of care for the duty to reasonably draft project specifications. In fact, although Kostaneski identified errors in the project documents, he never suggested that design problems violated any standard of care, let alone the standard of care for architects and engineers. Moreover, he unequivocally indicated that problems in the design phase were normal and should have been worked out during the contract administration. He noted that each of Domson's "25 separate claims" was based on "events and decisions of KLJ that occurred during the course of the project." Although summary judgment is disfavored in cases of negligence, Domson has not established a material issue of fact in dispute on the question of breach.
Conclusion
[¶34.] Domson has not identified that Paragraph 9.09 contravenes sound public policy under the circumstances, and Paragraph 9.09 unambiguously insulates Dakota Engineering and KLJ for liability in tort and contract for their good-faith acts and failures to act under the authority granted to them by the contract and contract documents. Further, although the court improperly imposed a burden on Domson to prove bad faith, on this record, Dakota Engineering/KLJ established a prima facie case of good faith, and Domson has failed to identify a material issue of fact in dispute on the issue of Dakota Engineering/KLJ's good-faith acts and failures to act in the interpretation and application of the contract documents. Also, Domson has not presented specific facts showing that a genuine, material issue exists for trial that Dakota Engineering/KLJ's design and drafting fell below a professional standard of care. Therefore, we affirm.
[¶35.] GILBERTSON, Chief Justice, and ZINTER and JENSEN, Justices, concur.
[¶36.] KERN, Justice, concurs in part and dissents in part.
[¶37.] SALTER, Justice, not having been a member of the Court at the time this action was assigned to the Court, did not participate.
The contract documents and the parties at times refer to the defendants as Dakota Engineering/KLJ and at times as independent defendants. Throughout this opinion, we use the designations employed by the parties and contract where appropriate.