DocketNumber: Docket No. 5895
Citation Numbers: 7 T.C. 967, 1946 U.S. Tax Ct. LEXIS 57
Judges: Harkon
Filed Date: 10/16/1946
Status: Precedential
Modified Date: 10/19/2024
*57
*967 The respondent has determined a deficiency in income tax for the year ended April 30, 1942, in the amount of $ 3,951.71; and deficiencies in excess profits tax for the years ended April 30, 1941, and April 30, 1942, in the respective amounts of $ 3,011.88 and $ 60,571.29.
Petitioner has abandoned several of its allegations of error. Only two questions remain for decision, and both issues relate to petitioner's liability for income and excess profits*58 taxes for the fiscal year ended in 1942.
The first question is whether petitioner, for the fiscal year ended April 30, 1942, has computed properly the amount of the excess profits credit allowed by
The second question is whether petitioner is entitled, under section 23 (a) (1) (A), to a deduction of $ 18,200 in computing its net income for the fiscal year ended April 30, 1942, as a reasonable allowance for the salary of its president. Respondent determined that $ 10,200 was reasonable compensation and disallowed $ 8,000 of the deduction.
Petitioner filed its several returns with the collector for the fifth district of New Jersey.
FINDINGS OF FACT.
Petitioner, a New Jersey corporation, having its office at Phillipsburg, New Jersey, conducts a business made up of two divisions -- the designing and manufacture of fiber bodied, custom made containers for packaging dry and liquid products, and the designing and manufacture of automatic machinery for the loading and assembling of ammunitions and of special purpose machinery for commercial use.
Petitioner keeps its books and reports income on the accrual method of accounting.
The president and sole stockholder of petitioner is R. T. Garfein, who organized petitioner in 1924.
Article 8.
The funds advanced will be liquidated by crediting 30 per cent of each payment becoming due under the contract to the advance until the full amount of the advance is liquidated.
It is agreed that, in case of default by the contractor in the performance of this contract or the termination thereof, before liquidation of the advance due to causes of contractor's responsibility, the contractor shall refund to the Government upon demand a sum equal to the unliquidated advance, all other provisions of the contract and all rights of the Government to remain in full force and effect.
A bond shall be furnished in a sum equal to 30 per cent of the total contract price guaranteeing the accounting for, or repayment, of the sum advanced, provided that in case of default by the contractor in the*62 performance of the contract or any termination thereof before liquidation of the advance due to causes of the contractor's responsibility, the contractor shall refund to the Government upon demand a sum equal to the unliquidated advance, all other provisions of the contract and all rights of the Government to remain in full force and effect; provided, further, that if the principal shall well and truly account for or repay the aforesaid advance payment in accordance with the terms of the contract or any modifications or agreements pertaining thereto that may have been or may subsequently be entered into, notice of such modifications to the surety being hereby waived, then the obligation under the bond to be void, otherwise to remain in full force and virtue.
* * *
On August 7, 1941, the date of the execution of the contract, the Government advanced to petitioner $ 559,870.50, 30 per cent of the contract price of $ 1,886,235.
On August 7, 1941 a "Performance Bond," Treasury Form No. *63 25 (Revised), in the penal sum of $ 559,900 was executed by petitioner as principal and United States Guarantee Co. as surety to the Government. The premium charged for the bond was $ 4,199.25. The bond recites,
The Condition of This Obligation Is Such, that whereas the principal entered into a certain contract, hereto attached, with the Government, dated August 7th, 1941, for
Machinery, 20 Millimeter. am. per contract NOs-86604.
*970 Whereas, provision is made under the contract to advance to the contractor funds in an amount equal to 30 per cent of the total contract price, subject to the stipulation that in case of default by the contractor in the performance of the contract, or any termination thereof before liquidation of the advance due to causes of contractor's responsibility, the contractor shall refund to the Government, upon demand, a sum equal to the unliquidated advance; provided, further, that in case the material covered by the said Contract NOs-86604 should not be manufactured and delivered by the principal in accordance with the provisions of the contract, and if the principal fails to reimburse the Government in the amount due in the sum or *64 sums paid by the Government to the principal, the surety on the bonds shall be liable to the Government for the amount thereof.
Now Therefore, If the principal shall well and truly perform and fulfill all the undertakings, covenants, terms, conditions, and agreements of said contract during the original term of said contract and any extensions thereof that may be granted by the Government, with or without notice to the surety, and during the life of any guaranty required under the contract, and shall also well and truly perform and fulfill all the undertakings, covenants, terms, conditions and agreements of any and all duly authorized modifications of said contract that may hereafter be made, notice of which modifications to the surety being hereby waived, then, this obligation to be void; otherwise to remain in full force and virtue.
* * * *
The contract dated August 7, 1941, called for delivery of goods by petitioner "within 540 days after the date of the contract or order awarded on this bid." Petitioner did not make any deliveries under this contract during its fiscal year ended April 30, 1942.
The contract dated August 7, 1941, provided for payment of 90 per cent of the contract*65 price of each item upon delivery, as follows:
Ninety percent (90%) of the contract price of each item will be paid upon delivery of each item at its destination for installation. The final ten percent (10%) will be paid upon completion of installation, satisfactory test and acceptance of each item by the Government, including for the last item delivery by contractor of tracings of drawings, instructions, etc., required by contract specifications.
A supplemental contract was executed by petitioner and the Government on March 2, 1942, for the manufacture and delivery of additional machinery for the contract price of $ 3,654,200. The Government agreed to advance to the contractor funds not to exceed 30 per cent of the contract price, under provisions in the agreement which are substantially the same as in the original contract of August 7, 1941, except that sums advanced under the supplemental contract were to be liquidated by crediting 35 per cent (instead of 30 per cent) of each payment becoming due under the contract to the advance until the full amount of the advance should be liquidated.
On March 2, 1942, the Government advanced $ 1,098,260 to petitioner, which represented 30 *66 per cent of $ 3,654,200. And on March 2, 1942, petitioner, as principal, and certain corporations, as sureties, executed an "Advance Payment Bond" in the penal sum of $ 1,096,300:
*971 * * * to save the Government harmless against any and all losses which may result from the failure of the Principal to liquidate or repay to the Government all or any portion of the advance payments so made;
Now Therefore, if the advance payments so made are repaid to the Government or are liquidated by deductions from other payments due the Principal, or otherwise, in accordance with the terms of said contract, then this obligation to be void; otherwise to remain in full force and virtue.
The machinery to be delivered under the supplementary contract was to be delivered by petitioner by February 28, 1943. Petitioner did not make any deliveries under the supplementary contract during the fiscal year ended April 30, 1942.
Petitioner did not include in its gross income for the fiscal year ended April 30, 1942, any of the sums advanced by the Government under the original and the supplementary contracts; and respondent has not determined that any of such advance payments should have been included*67 in gross income.
The gross sales and net income of the business, before officer's salaries and taxes, for the fiscal years 1939, 1940, 1941, and 1942 were as follows:
1939 | 1940 | 1941 | 1942 | |
Sales, machinery division | $ 81,769 | $ 119,311 | $ 189,842 | $ 555,921 |
Sales, container division | 285,699 | 423,577 | 538,486 | 860,945 |
Total gross sales | 367,469 | 542,888 | 728,328 | 1,413,595 |
Net income before salaries and taxes | 5,940 | 35,565 | 100,029 | 226,401 |
*68 The capital stock of petitioner is $ 250,000.
The number of employees of petitioner during the years 1939 through 1942 was as follows: 1939, 147; 1940, 245; 1941, 262; 1942, 287.
The fiber containers were sold to the Government and to corporations. About 70 per cent of sales of this division were to the Government and to the Picatinny Arsenal, in 1942, which purchased shell *972 containers. Commercial organizations purchased a variety of containers designed for their special products, which were designed and patented by petitioner. During the fiscal year 1942 new container designs were worked out which were sold in large quantities in later years. Garfein devoted a large part of his time to the designing of the new containers. Garfein negotiated all sales and made all sales of products of the fiber container division in the fiscal year 1942, except for $ 100,000 of sales which were made by one commission salesman, the only salesman employed by petitioner except Garfein. Garfein was responsible for fixing prices charged for containers and for purchasing raw materials. During the fiscal year 1942 the plant capacity of the container division was increased and $ 25,000 additional*69 machinery was purchased. The business of this division increased in 1942 by about $ 300,000. Hours of operations increased to a 2-shift day.
The machinery division of the business increased in the fiscal year 1942 by $ 366,000. The division was enlarged in 1942 by the use of an additional building and an increase in personnel. Hours were increased in 1942 from 40 to 50 hours a week, and later to 60 hours for the day shift and 66 hours for the night shift. In 1942 this division went on a 2-shift basis. Most of the machinery produced in 1942 was sold to the War and Navy Departments. Garfein did all of the selling for this division, negotiated contracts, and fixed prices. Garfein controlled all purchases of raw materials and made the final decisions upon designs.
During 1942 Garfein devoted all of his time to petitioner's business. His duties, hours, and services were increased.
The salary of $ 18,200 was reasonable compensation for Garfein's services in the fiscal year of 1942.
OPINION.
*71 The Congress restricted the definition of "borrowed capital" to an indebtedness evidenced by one of several stated documents which are written evidence of indebtedness. It has been held in the above cited cases that a narrow construction of the statute is required. The omission of a catch-all phrase, such as "any other written evidence of indebtedness," has been held to be of significance.
In this case, the situation serves to illustrate the point that the first emphasis in the statutory definition is the existence of a
A "bond" is but a written evidence of a debt, whether in the hands of the original payee, or in the hands of some other person by proper transfer * * *. A "debt" is a sum of money which is certainly, and at all events, payable as a debt, without regard to whether it is payable presently or at a future time. [Words and Phrases, Permanent Ed., vol. 5, p. 653.]
The contracts in question called*72 for the payment of prices by the Government for articles delivered by the contractor. The contractor's obligation was to make and deliver the goods. The Government's obligation was to pay money for the goods, and that obligation included an agreement by the Government to pay not more than 30 per cent of the total contract price in advance. By the terms of the contract the payments with which we are concerned were advance payments under the contract, and not loans. The contractor, petitioner, made an agreement to guarantee an accounting for the sums advanced by the Government under a performance or advance payment bond, and the evident purpose was to keep the Government free from any loss on account of the advance payment. The guarantee of the contractor and the performance bond were part of the entire contract to make and deliver goods. If the contractor, petitioner, well and truly performed all of his undertakings under the contract to make and deliver goods, then the obligation under the bond to pay a "penal sum" to the Government would be void.
Such guarantee to perform the contract or to pay a penal sum was not the giving of a "bond" to evidence an "indebtedness" as provided*73 in
It is held, therefore, that respondent did not err in determining that no part of the advance payments was includible in invested capital as "borrowed capital." See
*. On the signing of the contract.↩
1.
(a) Borrowed Capital. -- The borrowed capital for any day of any taxable year shall be determined as of the beginning of such day and shall be the sum of the following:
(1) The amount of the outstanding indebtedness (not including interest) of the taxpayer which is evidenced by a bond, note, bill of exchange, debenture, certificate of indebtedness, mortgage, or deed of trust * * *↩