DocketNumber: Docket No. 9169-75.
Filed Date: 10/9/1980
Status: Non-Precedential
Modified Date: 11/20/2020
MEMORANDUM OPINION
DAWSON,
The facts of this case have been fully stipulated pursuant to
Petitioner (hereinafter also referred to as the Corporation) is a corporation organized and existing under the laws of the Commonwealth of Kentucky with its principal place of business located in Frankfort, Kentucky. The Corporation uses the accrual method of accounting and has a taxable year ending March 31. Its Federal corporate income tax returns for the taxable years ended March 31, 1972 and March 31, 1973 (hereinafter the 1972 and 1973 taxable years, *129 respectively) were filed with the Internal Revenue Service Center in Memphis, Tennessee.
Throughout the taxable years in issue the Corporation was engaged in the general contracting business. During the period from March 1971 to July 1972 it was awarded four highway construction contracts by the Department of Highways of the Commonwealth of Kentucky (hereinafter referred to as the Department of Highways). The contracts are individually referred to by the parties as the Perry County 5-3 Contract, the Perry County 5-4 Contract, the Garrard-Jessamine Contract, and the Pike County Contract.
Each contract referred to and incorporated therein by reference the Department of Highways Standard Specifications for Road and Bridge Construction and Department of Highways Special Provision No. 83 (hereinafter collectively referred to as Standard Specifications). Section 1.9.6(A) of the Standard Specifications provided that monthly progress payments were to be paid by the Department of Highways on the contract price, and that the amount of each partial payment was to be based upon monthly estimates of the value of the work performed and materials complete in place. The monthly estimates*130 were not to be considered as acceptance of any portion of the work performed. Ninety-five (95) percent of each partial payment was to be paid directly to the contractor; the remaining 5 percent was to be retained (i.e., "retainage") pending a final determination of the actual amount owed to the contractor upon completion of the project.
The actual amount due the contractor could not be determined until (1) the work to be performed had been completed and accepted by the Department of Highways as in compliance with contract specifications, and (2) the Department of Highways and the contractor had agreed upon the actual quantity of each bid item used in construction and the amount of liquidated damages or other claims, if any, with the Department of Highways having the right to resolve finally any dispute as to the sum due. The contractor and the Department of Highways evidence their agreement as to the actual qnautities used in construction and the amount of any liquidated damages or other claims when the contractor executes Department of Highways Form
*131 Each contract provided that retainage withheld under section 1.9.6(A) of the Standard Specifications could be withdrawn by the contractor upon the deposit of securities as authorized by
Concurrent with its execution of the contracts with the Department of Highways, the Corporation was required by the Department of Highways regulations to execute a document entitled "Contractor's Election as to Retainage" (hereinafter referred to as retainage election). The retainage election required the Corporation to select one of three methods for treatment of the retainage*132 funds. The first method was to deposit qualified securities with a custodian in order to withdraw the retainage. The second method was to elect to have a custodian purchase securities with the retainage funds for the Corporation's account. The third method was to elect not to withdraw the retainage until otherwise due under the Standard Specifications. The Corporation elected the second option.
The election document for each contract was incorporated into and became a part of the contract between the Department of Highways and the Corporation in accordance with the Department of Highways regulations. The Winchester Bank (hereinafter referred to as the Bank) in Winchester, Kentucky was designated and approved as the custodian referred to in each election document. The Bank and the Corporationthen executed a standard Department of Highways form entitled "Escrow Agreement" with respect to each contract. Under the Escrow Agreement the Department of Highways was to deliver checks payable to the Bank for deposit in the Corporation's account. Upon receipt the Bank was required to invest the funds in certain listed United States or Kentucky governmental securities, the income from*133 which was required to be distributed to the Corporation on a regular basis. *134 was accepted by the Department of Highways as complete and in physical compliance with the applicable contract specifications on the following dates: Contract Date Perry County 5-3 11/8/72 Perry County 5-4 7/11/73 Garrard-Jessamine 10/1/74 Pike County 7/15/75
With respect to each contract the Corporation executed Department of Highways Form
Contract | Date |
Perry County 5-3 | 8/13/73 |
Perry County 5-4 | 4/19/75 |
Garrard-Jessamine | 11/29/76 |
Pike County | 2/20/76 |
During the 1972 taxable year the Bank received from the Department of Highways under the terms of the four Escrow Agreements a total of $284,171.51. During the 1973 taxable year the Bank received a total of $420,021.29. None of the amounts received were distributed to the Corporation until after March 31, 1973. In accordance with the terms of the contracts, the Department of Highways authorized the Bank to make partial and/or final releases of the escrowed funds as follows: *135 Date Partial Amount of Date Final Amount of Release Partial Release Final Contract Authorized Release Authorized Release Perry County 5-3 8/28/73 $258,296.63 Perry County 5-4 5/13/75 316,219.63 Garrard-Jessamine 11/12/74 $96,536.77 12/8/76 96,662.04 Pike County 3/3/76 101,096.33
The Bank distributed these amounts to the Corporation approximately one to two months after the release authorizations were received. The Corporation included the distributions in gross income in the taxable year of receipt.
In his statutory notice o deficiency dated July 10, 1975, respondent increased petitioner's taxable income for the 1972 and 1973 taxable years to reflect the retainage received by the Bank in each year. Under respondent's original theory the retainage constituted gross income to petitioner at the moment the funds were paid into escrow. Now, however, respondent maintains that the retainage should not be taxed until the year in which it is actually invested by the escrow custodian. On a first-in, first-out basis the actual amounts invested by the Bank in the 1972 and 1973 taxable years were $246,431.70 and $451,458.32, *136 respectively. Accordingly, respondent has increased the amount of his deficiency for the 1973 taxable year by $15,089.77 to reflect retainage received by the Bank in the 1972 taxable year but not invested until the following year.
Accrual basis taxpayers are not taxed on income until all events have occurred which fix the right to receive such income and the amount can be determined with reasonable accuracy.
(1) Under the terms of the contract, no retainage was to be released prior to approval and acceptance of the work by the Department of Highways.
(2) Under the terms of the Escrow Agreement the Department of Highways possessed the unilateral and unconditional*140 right to declare the contractor's performance to be in default at any time prior to final approval and to demand the return of the retainage. The Bank was contractually obligated to comply with this demand.
Given the existence of such conditions, we think neither the receipt nor the investment of the retainage by the escrow custodian sufficiently fixes the contractor's right to the funds so as to require accrual under the all-events test.
It is true that by electing to have the retainage placed in escrow petitioner became entitled to and did receive an economic benefit in the form of investment interest. Nevertheless,. petitioner's ownership rights in the excrowed funds were extremely limited, as we indicated in
Construction Company did possess certain powers with respect to the investment and receipt of income from the retainage funds. However, we regard such powers as inconsequential in view of the substantial conditions imposed upon the company's receipt of such "retainage" and in view of the restricted list of low-risk governmental obligations which could be purchased with the retainage funds. Such powers did not permit Construction Company to exercise unfettered or even substantial control over the disposition and utilization of the retainage funds.
Given such limited incidents of ownership, we are unwilling to find actual receipt simply by virtue of petitioner's*143 election to have the retainage invested pending completion of contract performance. Moreover, we think the substantial conditions imposed on the eventual release of the retainage make this case clearly distinguishable from the so-called "economic benefit" cases, where actual receipt to cash method taxpayers was premised on the existence of a vested, rather than contingent, right to future possession of a particular fund. See and compare
Accordingly, we hold that petitioner is not required to accrue any of the retainage received by the Bank during the taxable years in issue.
To reflect concessions made by the petitioner and our conclusion of the disputed issue,
1. The securities which could be purchased with the escrowed funds were restricted to U.S. Treasury Bonds; U.S. Treasury Notes; U.S. Certificates of Indebtedness; U.S. Treasury Bills; Bonds of the Commonwealth of Kentucky; and Bonds in any political subdivision of the Commonwealth of Kentucky, including school districts.↩
2. Section 1.9.7 of the Standard Specifications allows the Department of Highways to authorize a partial release of retainage subsequent to the completion and acceptance of the project but prior to a final determination of the actual amount owed the contractor.↩
3. Respondent has not made a corresponding downward adjustment to the deficiency for the 1972 taxable year. Such an adjustment would obviously be required, however, if we were to agree with respondent's theory of inclusion in this case.↩
4. In
5. We note that if the contractor receives a partial distribution from escrow pursuant to Section 1.9.7 of the Standard Specifications (see note 2,
Gar Wood Industries, Inc. v. United States ( 1971 )
United States v. Harmon ( 1953 )
Charles F. Dally and Sarafrancis Dally v. Commissioner of ... ( 1955 )
Spring City Foundry Co. v. Commissioner ( 1934 )
Commissioner of Int. Rev. v. Cleveland Trinidad Pav. Co. ( 1932 )