DocketNumber: Docket No. 7283-88
Judges: TANNENWALD
Filed Date: 7/10/1990
Status: Non-Precedential
Modified Date: 11/21/2020
MEMORANDUM OPINION
Respondent determined deficiencies in petitioner's Federal income taxes as follows:
Taxable Year Ended | Deficiencies | ||
3/31/82 | $ 69,342.00 4/30/83 | 605.00 4/28/84 | 12,732.00 |
4/27/85 | 32,012.00 |
After concessions, the issues for decision are: (1) whether petitioner's one-hour photo labs and their concrete foundations are section 38 *361 property as defined by
A contractor constructed the labs at his place of business. The principal building components of the labs included 10-inch "I" beams, 2-inch by 4-inch steel structural tubing, .188 gauge steel walls, roof panels, polished plate and tempered glass, wall porcelain panels and clear curved glazing. The steel frame components of the labs were reinforced beyond the support requirements for a similar structure of otherwise comparable size and materials which was not intended to be moved. This reinforcement allowed the *363 lab halves to be moved without the threat of collapse. The contractor built the labs in two halves measuring 12 feet wide, 28 feet long, and 12 feet high so that the halves would fit on the trucks used to move them to the lab sites. Together, the lab halves weighed 54,000 pounds.
Petitioner entered into ground leases with the owners of the property upon which the labs would be located. Petitioner intended to leave the labs on their original sites for an indefinite time. The leases were for 5 years, with an option which petitioner could unilaterally exercise to extend the lease, in most instances, for two 5-year periods or, in a few instances, for one 5-year period. Many of the leases included an "economic adversity" provision allowing petitioner to terminate the lease and move the lab when business at the site became uneconomic. The leases required petitioner to remove the labs upon termination of the lease and restore the premises to the condition which existed prior to the lease, including removing the concrete foundations at the landlord's request.
After petitioner leased a site, the site contractor constructed the lab foundation. The contractor poured continuous concrete *364 footings into trenches dug around the exterior wall perimeters of the labs, after removing the parking lot asphalt. The footings were approximately 24 inches deep, 12 inches wide, and extended 2 or 3 inches above ground level. A concrete footing of the same dimensions was also poured in a trench dug lengthwise along the center line of the area to be covered by the labs (the split line), directly below where the two lab halves were to be joined. The footings were reinforced with iron reinforcing bars.
At the same time the foundation footings were poured, the contractor poured a concrete base approximately 4 or 5 inches thick, reinforced with iron reinforcing bars. Steel weld plates measuring 10 inches wide, 10 inches long, and 3/8ths of an inch thick were inserted into the concrete foundation. Each weld plate had four "L" shaped legs, 5 to 8 inches in length, attached to its bottom side which were completely submerged in the concrete. The average lab foundation contained 22 weld plates spaced about every 5 feet around the perimeter of the foundation and the split line footing.
When the concrete had hardened, two 40-foot flat bed semi-truck trailers hauled the lab halves to the *365 site. At the site, a heavy duty crane lifted the lab halves onto the foundation. The lab halves were bolted together and joined with cap flashings and silicon caulking. Then, the "I" beams under the lab halves were tack welded to six weld plates, located at each of the four corners of the lab and at the two junctures of the split line footing and the perimeter footing. A hard foam pad was placed against the exterior of the "I" beams as a moisture barrier and to prevent concrete from adhering to the beams in the event the concrete later was removed. Concrete curbing was then poured on all sides of the lab so that the interior edge of the concrete came in contact with the perimeter "I" beams protected by the foam.
To finish the labs, the site contractor connected the utilities to the previously installed systems of the lab, installed a plastic sign reading, "FOX PHOTO 1-HR LAB," around the top perimeter of the labs, painted directional arrows and the words "DRIVE THRU" on the asphalt close to the lab, and planted shrubbery around the lab. On average, petitioner allowed 1 week for site preparation, including laying the foundation, 1 week for delivery and assembly of the lab, and 2 *366 weeks for finishing the lab and the surrounding area. Petitioner took a week, on average, to install and test its equipment inside the labs.
The estimated useful life of each of the labs is 50 years. The average cost of an uninstalled lab, not including the air conditioning system, was $ 48,579. The average installation cost per lab was $ 28,035.92, exclusive of the costs of the concrete foundations and the air conditioning systems. The average cost of a concrete foundation was $ 28,622.39. The average cost of a central air conditioning system was $ 10,274.14.
Petitioner's labs were typically open to the public from 9:00 a.m. to 6:30 p.m., Monday through Friday, and from 9:00 a.m. to 5:00 p.m. on Saturday. Petitioner emphasized personal service to its customers and considered the availability of on-site employees an important aspect of such service. The labs were staffed with one to four employees depending on the amount of business activity, including a store manager, a photo technician responsible for developing photographs, and a retail salesperson.
The labs contained three interior work areas: the retail area, the film development area, and the storeroom. Petitioner's employees *367 accepted film for developing, returned finished photographs to drive-up and walk-in customers, and sold photographic supplies in the retail area. The salesperson worked behind a traditional sales counter that separated the public walk-in area from the film developing and storeroom areas.
Employees developed the photographs in the film development area. In this area, separate work stations were designated for each stage in film developing. Petitioner's employees operated numerous pieces of equipment when developing film.
All the supplies for the labs were kept in the storeroom. Petitioner's employees mixed chemicals and operated silver recovery equipment in this room. The store manager's desk was in the storeroom.
Although petitioner constructed the labs so they could be moved from their original site, none of the 35 labs in question were moved during the years in issue. Subsequent to the years in issue, petitioner had between 75 and 80 labs in service and moved 5 labs, including 3 of the 35 labs in issue. To prepare the labs for removal, a contractor disconnected the utilities and removed the wrap-around sign. The contractor then broke up and removed the concrete from around *368 the lab with a track loader. After the weld points were exposed, the contractor cut the "I" beams of the lab from the weld plates with acetylene cutting torches. The two lab halves then were unbolted and separated. Two heavy duty cranes lifted the lab halves onto two flatbed trucks. The trucks moved the halves either to storage or to a location where they were refurbished for use at another site. The concrete foundation was either removed with a jack hammer or track loader when the lease terminated or reused for another lab if the site remained leased.
Removal of the labs took about five men approximately 12 to 18 hours over a 2- to 3-day period. The cost of moving a lab was approximately $ 6,000 in 1987. To restore a lab site to its original condition required an additional 32 hours at an additional cost of $ 9,500. In 1987, the cost of repairing and refurbishing a lab for reuse after its removal was approximately $ 19,000.
For its taxable years 1984 and 1985, petitioner treated its one-hour labs as section 38 property claiming ITC on its Federal income tax returns with respect to its investment in the labs placed in service in those fiscal years. Petitioner also treated its *369 one-hour labs, exclusive of the foundations, as "5-year property" and claimed ACRS deductions on its Federal income tax returns for 1984 and 1985 based on the applicable percentages in section 168(b)(1). Although petitioner did not elect, pursuant to section 168(f)(4), the straight line method of recovery in section 168(b)(3), petitioner now claims it is entitled to use the straight line method if we determine that the labs are 15- or 18-year real property.
Although petitioner did not claim ITC on its Federal income tax returns for the concrete foundations placed in service during the fiscal years 1984 and 1985, petitioner now claims that the concrete foundations are property qualifying for the ITC for those years. *370 On its Federal income tax returns, petitioner classified the foundations as "15-year real property" for its taxable year 1984 and as "18-year real property" for its taxable year 1985, and took ACRS deductions on that basis. Petitioner now claims that the concrete foundations are items of 5-year property eligible for additional ACRS deductions.
In his notice of deficiency, respondent disallowed the ITC claimed on the labs on the grounds that the labs did not meet the requirements of section 38 as defined in
Section 38 allows the investment tax credit against tax for investments in certain types of property, described as "section 38 property."
Respondent contends that the labs are "buildings" and their foundations are "structural components" that are ineligible for the ITC because both "buildings" and "structural components," defined in
In making our determination of whether the labs and their concrete foundations are tangible personal property, we do not consider the air conditioning systems which the parties have agreed to treat consistent with our decision on the labs. We first discuss whether the labs are tangible personal property within the meaning of
The dispute in this case centers around the definition of tangible personal property in
In advancing his theory of the inquiry required by the regulations, respondent relies on cases like
In cases in which the issue of movability has been involved, we have approached the question of whether the property was a "building" by determining whether the structure was inherently permanent. In cite[s] "buildings or 7 Emphasis to the word "other" has been added by the Court. This language in the regulations follows closely the language of the congressional committee reports that accompanied the initial enactment of the investment credit provisions. See H. Rept. No. 1447, 87th Cong., 2d Sess. (1962), and S. Rept. No. 1881, 87th Cong., 2d Sess. (1962).
The mobile homes in
In It is apparent that before the "functional use" test can properly be applied in this case, it must first be shown that the trailers were permanent improvements to land. * * * [T]his requirement is fully consistent with the respondent's own regulations and with congressional intent. [
Cf.
Respondent now urges us to follow the contrary approach in applying the definition of a "building" articulated by the The test for "tangible personal property" focuses on whether the property in question is an "inherently permanent structure." [Citations omitted.] Thus cases and Treasury rulings have determined that property that is easily removable * * * is section 38 property and qualifies for the ITC. [Fn. ref. omitted;
This apparent contradiction in the Seventh Circuit's approach to the issue is just one example of the morass of approaches taken by various courts in applying what has become a complex definition of "building" for purposes of the ITC -- a complexity that is recognized by numerous commentators. See, e.g., Note, "Undermining the Foundation of the ITC Building Exclusion," *380
We adhere to our position stated in Our review *381 of the Revenue Act of 1962, its legislative history, and the Treasury Regulations enacted thereunder leads us to the conclusion that the decision in
Since we have decided that the test of whether the labs are buildings for purposes of the ITC includes a determination of whether the labs were inherently permanent, we now address the issue of permanence. Whether property is inherently permanent depends upon the fashion in which it is affixed to the land and how permanently it is designed to remain in place.
(1) Is the property capable of being moved and has it in fact been moved?
(2) Is the property designed or constructed to remain permanently in place?
(3) Are there circumstances which tend to show the expected or intended length of affixation, i.e., are there circumstances which show that the property may or will have to be moved?
(4) How substantial a job is removal of the property and how time-consuming is it? Is it readily removable?
(5) How much damage will the property sustain upon its removal?
(6) What is the manner of affixation of the property to the land?
We find that the manner in which the labs themselves were constructed and the way they were set on their concrete foundations show that they were capable of being moved and were constructed so that they could be moved satisfying
The proper application of the
We do not agree with respondent that, because the mobile homes in
In contrast to the one-hour labs, the concrete foundations are immovable and inherently permanent structures as petitioner has conceded. Citing
The parties agree that whether the labs and the concrete foundations qualify for 5-year depreciation is dependent on whether they qualify for the ITC. Secs. 1245(a)(3), 168(b)(1), and 168(c)(2)(B). The labs do qualify for the ITC under
Our holdings make it unnecessary to address the alternative issue of whether petitioner may elect the straight-line method of depreciation with respect to the labs if we *387 had found them to be real property. This issue was not raised with respect to the concrete foundations, so our inquiry is complete.
1. This deficiency is a result of respondent's adjustment to the carryback of investment tax credit from the taxable year 1984.↩
2. The parties do not dispute this deficiency.↩
3. Unless indicated otherwise, all section references are to the Internal Revenue Code as in effect for the years in issue, and all Rule references are to the Tax Court Rules of Practice and Procedure.
4. The labs and concrete foundations placed in service after March 15, 1984, would be considered 18-year real property pursuant to amendments to sec. 168 made by sec. 111(a) of Pub. L. 98-369 (1984), 98 Stat. 494.↩
5. Of the 35 labs, we focus our opinion on the 33 model MLD labs that were essentially identical in design, because the parties have stipulated that they will apply our rulings to the two labs that differed in design and dimension from the MLD labs.↩
6. Although petitioner now also claims ITC for foundations placed in service during its fiscal year 1983, we do not discuss 1983 because the parties do not dispute the deficiency for that year. See page 2 and n.2,
7. The ITC was repealed by sec. 211(a) of the Tax Reform Act of 1986, Pub. L. 99-514, 100 Stat. 2166, effective, subject to transition rules, for property placed in service after Dec. 31, 1985.↩
8.
(1) In general. -- * * * the term "section 38 property" means --
(A) tangible personal property (other than an air conditioning or heating unit), or
(B) other tangible property (not including a building and its structural components) but only if such property --
* * *
* * *
Such term includes only recovery property (within the meaning of section 168 without regard to any useful life) and any other property with respect to which depreciation (or amortization in lieu of depreciation) is allowable and having a useful life (determined as of the time such property is placed in service) of 3 years or more. * * *↩
9.
(e) Definition of building and structural components. (1) * * * The term "building" generally means any structure or edifice enclosing a space within its walls, and usually covered by a roof, the purpose of which is, for example, to provide shelter or housing, or to provide working, office,parking, display, or sales space. The term includes, for example, structures such as apartment houses, factory and office buildings, warehouses, barns, garages, railways or bus stations, and stores. Such terms include any such structure constructed by, or for, a lessee even if such structure must be removed, or ownership of such structure reverts to the lessor, at the termination of the lease. Such term does not include (i) a structure which is essentially an item of machinery or equipment, or (ii) a structure which houses property used as an integral part of an activity specified in
(2) The term "structural components" includes such parts of a building as walls, partitions, floors, and ceilings, as well as any permanent coverings therefor such as panelling or tiling; windows and doors; all components (whether in, on, or adjacent to the building) of a central air conditioning or heating system, including motors, compressors, pipes and ducts; plumbing and plumbing fixtures, such as sinks and bathtubs; electric wiring and lighting fixtures; chimneys; stairs, escalators, and elevators, including all components thereof; sprinkler systems; fire escapes; and other components relating to the operation or maintenance of a building. * * *
10. Petitioner has conceded that the labs are not "other tangible property" as described in
11. Although we held that the mobile homes were tangible personal property, they did not qualify for the ITC because they were primarily used for lodging by nontransients pursuant to
Mallinckrodt, Inc. v. Commissioner of Internal Revenue ( 1985 )
Minot Federal Savings & Loan Assn. v. United States ( 1970 )
Jack E. Golsen and Sylvia H. Golsen v. Commissioner of ... ( 1971 )
King Radio Corporation, Inc. v. United States ( 1973 )
The Kramertown Company, Inc. v. Commissioner of Internal ... ( 1974 )
Illinois Cereal Mills, Inc. v. Commissioner of Internal ... ( 1986 )
Jack McManus Individually and as Personal Representative of ... ( 1988 )