DocketNumber: Docket No. 7204-76.
Filed Date: 6/29/1978
Status: Non-Precedential
Modified Date: 11/21/2020
*271
MEMORANDUM FINDINGS OF FACT AND OPINION
DRENNEN,
Construction of the Gavin Power Plant was initiated in the spring of 1971. This construction called for the installation of two major generators that would be used to produce electricity. At the initiation of construction, it was projected the first generator would be operational by October 20, 1974. The second generator unit was projected to be operational by July 6, 1975. Both generator units were made operational by the projected dates. The Gavin Power Plant was operational after the installation and completion of its first generator unit on October 20, 1974. The Gavin Power Plant became fully operational after the installation and completion of construction on its second generator unit, which was accomplished on July 6, 1975. The Gavin Power Plant is owned by Ohio Electric, a subsidiary of Ohio Power Company, which*274 in turn is a subsidiary of American Electric Power Company. The Gavin Power Plant produces electrical power for a 7-State area in the mid-West.
Petitioner was continuously employed by Sollitt Construction Co. at the Gavin Power Plant for approximately 26 months from January 1, 1972, through March 21, 1974, when he was laid off. Petitioner's job at the Gavin Power Plant project initially was to build construction slabs, and later (as of about April 1973) he put down decking.
Petitioner was aware when he accepted employment with Sollitt Construction Co. at the Gavin Power Plant that construction of the plant would require several years.
When he obtained the job at the Gavin Power Plant petitioner did not change his residence to his jobsite. Petitioner traveled by automobile daily to his place of employment at the Gavin Power Plant, Cheshire, Ohio, from his Shoals, W. Va., residence during the period January 1, 1972, through March 21, 1974. Petitioner returned to his Shoals, W. Va., residence after the completion of each day's work at the Gavin Power Plant. Petitioner's travel from his Shoals, W. Va., residence to Cheshire, Ohio, and return involved travel of 60 miles one*275 way and 120 miles round trip. Petitioner was not reimbursed for expenses incurred in traveling to and from the jobsite.
On petitioners' 1973 income tax return, petitioner claimed an employee business expense of $ 3,031.20 for his daily travel from his Shoals, W. Va., residence to the General Gavin Electric Power Plant jobsite at Cheshire, Ohio, and for his return trip to his residence. These expenses were incurred for transportation alone. In the notice of deficiency respondent disallowed the deduction of these expenses on the ground it had not been established that the expenses claimed were ordinary and necessary business expenses or were expended for the purpose designated.
The evidence indicates that the termination of petitioner's job could not be reasonably foreseen at the time the employment commenced. The fact that petitioner had no assurance of how long his employment at the Gavin Power Plant would last is not determinative of whether the employment was "temporary" or "indefinite." In light of the facts mentioned above it would have been reasonable to assume at the inception of the employment that it would continue for a substantial, indeterminate period of time, and the substantial actual duration of the employment is persuasive that the employment was "indeterminate in fact as it developed." See
In all other significant respects this case corresponds to
1. All section references are to the Internal Revenue Code of 1954, as amended and in effect in the year in issue, unless otherwise specified. ↩
2. See also companion cases
3. Respondent did not disallow the transportation expenses claimed by petitioner for travel between his residence and Cheshire, Ohio, on his 1972 return.↩