DocketNumber: No. 08-0634
Citation Numbers: 345 S.W.3d 60, 80 A.L.R. 6th 679, 54 Tex. Sup. Ct. J. 1339, 2011 Tex. LEXIS 509, 2011 WL 2586855
Judges: Willett
Filed Date: 7/1/2011
Status: Precedential
Modified Date: 11/14/2024
delivered the opinion of the Court.
This appeal challenges a final order of the Public Utility Commission in a true-up proceeding under Chapter 39 of the Utilities Code, a part of the Public Utility Regulatory Act (PURA). The district court affirmed the order in part and reversed it in part. The court of appeals affirmed the judgment of the district court in part and reversed it in part.
In its final order (Order), the PUC determined stranded costs, which generally are “based on the difference between the book value of generation assets and the market value of these assets.”
I. Market Value
Generally, “Section 39.262(h) provides that the affiliated power-generation company shall establish the market value of its generation assets using one or more of four methods: the sale of assets method, the stock valuation method, the partial stock valuation (PSV) method, and the exchange of assets method.”
Subsection (i) provides in part: “Unless an electric utility or its affiliated power generation company combines all of its remaining generation assets into one or more transferee corporations as described in Subsections (h)(2) and (3), the electric utility shall quantify its stranded costs for nuclear assets using the ECOM method.”
In this case, AEP chose to quantify its stranded costs under Subsection (h)(1), the sale of assets method, because it had sold its generation assets including its interest in the South Texas Nuclear Project. The Consumers argue that the market value of AEP’s nuclear assets could not be determined using the sale of assets method, because Subsection (i) requires use of the ECOM model for valuing nuclear assets unless the stock valuation or PSV method is used.
The PUC ruled that the sale of assets method could be used to determine the market value of nuclear assets, and that Subsection (i), by its terms, is limited to the valuation of “remaining” nuclear assets. It reasoned that once AEP sold its nuclear assets, they were not remaining. Like the court of appeals, we conclude that the PUC’s construction of the provision is
Further, we have noted that “[wjhile other methods are provided to determine market value indirectly, we think the actual sale of all the generation assets ... provides the best measure of market value,”
II. Net Book Value
A. Excess Mitigation Credits
The PUC required AEP to issue excess mitigation credits to customers based on interim projections that AEP would have no stranded costs. The projections turned out to be erroneous, and at the true-up proceeding, the PUC reasoned that the EMCs, including the EMCs paid to the affiliate retailer CPL Retail Energy, had by design increased the net book value (and decreased stranded costs) on a dollar-for-dollar basis, and accordingly stranded costs should reflect the total amount of EMCs paid. In State v. PUC, we affirmed
In today’s case, the same court of appeals remanded this issue to the PUC for reconsideration in light of its decision in the CenterPoint true-up case and its decision in another case holding that the PUC never had authority to issue EMCs.
AEP argues that the PUC did not err in including in stranded costs all EMCs that had been paid. The Consumers argue that stranded costs should be reduced by the amount of EMCs paid by AEP to its affiliated retail provider, CPL Retail Energy. Consistent with our decision in State v. PUC, we agree with AEP that no adjustment to the PUC’s calculation of stranded costs is warranted to account for EMCs paid to CPL Retail Energy. We rejected the same argument in State v. PUC, reasoning that regardless of whether the EMCs were paid to the affiliated retail electric provider or another retail provider, “the purpose of the EMCs was to increase the NBV of CenterPoint’s generation assets,”
AEP separately argues that the PUC miscalculated interest on the excess earnings. In this proceeding, the PUC calculated interest on stranded costs monthly, running from January 2002. As discussed further below, the interest rate and the start date for the running of interest were correct under our holdings in TIEC. Schedule II to the Order shows the PUC’s calculation of interest on the stranded cost true-up award, with the column for net book value increasing monthly to reflect the unrefunded EMC balance. The EMCs, by design, increased the net book value and were credited against excess earnings, and therefore correspondingly increased stranded costs and the interest on the principal amount of stranded costs. We see no error in the PUC’s treatment of interest in this true-up proceeding. We are not persuaded by AEP’s argument that the Order double-counted interest.
B. Construction Work in Progress
The Consumers complain that the PUC erred in including construction work in progress (CWIP) in the net book value determination. They argue that ratemak-ing standards must be met before the inclusion of CWIP in net book value. We rejected this argument in State v. PUC.
C. Adjustments to NBV for Commercially Unreasonable Conduct
AEP argues that once the PUC determined market value by concluding that the
On these issues, we agree with the PUC across the board. First, we agree that commercially unreasonable conduct can result in a reduction to net book value even when the PUC uses the sale of assets method to determine market value, and finds that the sale of assets was “a bona fide third-party transaction under a competitive offering,” as specified in Section 39.262(h)(1).
Section 39.252(d) provides:
An electric utility shall pursue commercially reasonable means to reduce its potential stranded costs, including good faith attempts to renegotiate above-cost fuel and purchased power contracts or the exercise of normal business practices to protect the value of its assets. The commission shall consider the utility’s efforts under this subsection when determining the amount of the utility’s stranded costs; provided, however, that nothing in this section authorizes the commission to substitute its judgment for a market valuation of generation assets determined under Sections 39.262(h) and (i).
A similar issue arose in State v. PUC. We held that market value should be determined under the sales of assets method, concluding that the sale of assets in that case “was indeed ‘a bona fide third-party transaction under a competitive offering’ ” as provided in Subsection (h)(1).
The PUC could consider the commercial reasonableness of the RRI Option in determining NBV. The PUC adjusted NBV in making the stranded cost determination, after finding that the conveyance of the Option was commercially unreasonable and did not represent normal business practices. Section 39.252(d) expressly directs the PUC, when making the stranded cost determination, to consider whether the utility used “commercially reasonable means” and “normal business practices” to reduce stranded costs. Since Section*67 39.252(d) bars the PUC from adjusting the market value component of stranded costs, it necessarily authorizes an adjustment to NBY, the other principal component of stranded costs.25
Hence, we accepted, as we do here, that even if the sale of assets is, overall, sufficiently “bona fide” and “competitive” to qualify for a market value determination under Section 39.262(h)(1), commercially unreasonable conduct by the utility affecting the value of the assets sold is subject to an adjustment to net book value under Section 39.252(d). This authority flows from Section 39.252(d), requiring the PUC, when determining stranded costs, to consider whether the utility engaged in “commercially reasonable” conduct and “normal business practices.” This authority also flows from Section 39.252(a), providing that a utility may only recover its “nonmi-tigable” stranded costs, and Section 39.262(a), providing that a utility “may not be permitted to overrecover stranded costs” at the true-up proceeding. These provisions should be read together in construing Chapter 39.
In today’s case, the utility’s election to use the sale of assets method under Section 39.262(h)(1), and a PUC finding that the sale of assets was conducted through a bona fide and competitive sale,
Our agreement with the PUC and the court of appeals dissent that an NBV adjustment is allowed in these circumstances leaves the question whether the PUC’s dollar adjustments to NBV are supported by substantial evidence. After considering numerous alleged instances of commercially unreasonable conduct, the PUC made two adjustments to NBV. AEP argues that one of the adjustments was too large, while the Consumers complain that both of the adjustments were too small.
Under substantial evidence review of fact-based determinations, “[t]he issue for the reviewing court is not whether the agency’s decision was correct, but only whether the record demonstrates some reasonable basis for the agency’s action.”
The PUC reduced AEP’s net book value by $68.7 million on grounds that AEP’s conduct before the sale of its interest in the South Texas Nuclear Project was commercially unreasonable. It found fault in AEP’s failure to prepare an adequate pre-sale valuation analysis so that it had an estimate of the intrinsic value of its interest, and to establish ahead of the sale a “walk-away” or reserve price. It arrived at the $68.7 million figure by comparing the price received by AEP and the price received by Texas Genco (Genco), a co-owner of the Project that also sold its interest. This figure was based on the relative sizes of the interests sold by the two companies. AEP and the Consumers, relying on conflicting evidence in the record, argue that the PUC miscalculated the relative sizes of the Genco and AEP interests. AEP further argues that the PUC offered no rational explanation for how its alleged unreasonable conduct affected the price for its interest in the Project. We have reviewed the evidence and conclude that the PUC’s calculation is supported by substantial evidence. The PUC gave rational reasons for the disallowance.
The PUC also made an $8 million adjustment to NBV on grounds that AEP had unreasonably bundled the sale of its Coleco Creek coal-fired plant with other plants instead of considering whether it could obtain a higher price by selling this plant separately. It noted that AEP had sold the bundled facilities for less than one bidder had offered for Coleco Creek plant by itself. The Consumers argue that a much greater adjustment was warranted. The PUC considered conflicting evidence and argument on this issue. In response to AEP’s contention that the other plants actually had negative value, the PUC noted evidence that AEP “was only concerned about selling these facilities as generation units, rather than examining other options such as selling the facilities for their land, parts and scrap metal, or the water rights associated with the facilities.” The PUC relied on an actual “nonconforming” bid for the Coleco Creek plant by itself, and compared that bid to the sale price of the bundled assets in reaching the $8 million figure. The bid was nonconforming in that it did not fully comply with AEP’s bidding instructions, but the PUC argues that evidence on which the Consumers relied were not actual bids at all, but less reliable evidence such as sales of allegedly similar plants or expressions of interest that occurred before the potential bidder had conducted any due diligence. Given the conflicting evidence and reasonable inferences to be drawn therefrom, the PUC’s adjustment is sustained under the substantial evidence test..
The Consumers also argue that the PUC should have made a further adjustment to NBV because AEP failed to execute “bridge power sales” agreements relating to the sale of certain assets. Some of the generation assets were sold under agreements that closed at a future date. AEP received the profits from these assets during the period between the signing of the agreements and the transfer of the assets to the buyer. Under a bridge power sales agreement, the purchaser of generation facilities receives the profits from power sales while the sale is pending. The Consumers argue that such agreements would have increased the calculated market value of the assets and correspondingly reduced stranded costs. The PUC, district court, and court of appeals have all rejected this argument.
AEP argues that, assuming the NBV adjustments were legally and factually warranted, the PUC erred in “grossing up” the disallowances to reflect the federal corporate income tax benefits of the adjustments to stranded costs. The PUC adjustments had lowered stranded costs, with the result that AEP would owe less tax on stranded costs than anticipated. But the utility already had an accumulated deferred federal income tax (ADFIT) account to pay taxes that it now would not owe. The PUC concluded that without the gross up to reflect the effect of taxes, AEP would retain funds in its ADFIT account for the payment of taxes collected from rates charged to customers in previous years that would never be paid, resulting in an overrecovery of stranded costs.
We see no error in the PUC approach. With the benefit of expert testimony, the PUC concluded that without the gross ups an overrecovery of stranded costs would occur, because straight-line depreciation is used for ratemaking while accelerated depreciation is used for paying taxes to the IRS. The result of these divergent depreciation methods is that the ADFIT account to pay income taxes accumulates funds in the early years of an asset’s life, as regulatory tax expense paid by ratepayers exceeds the actual tax expense, and then reverses in the later years. The excess funds from early years are held in the ADFIT account and then paid out in later years. Grossing up the adjustment assured that AEP would not receive a windfall in the form of customer charges to cover taxes that would never be paid. As one expert opined, without the gross ups AEP would retain a tax benefit that partially offset the disallowances, resulting in “the government partially subsidizing the disallowance[s].”
Grossing up a true-up amount to reflect the effect of taxes is not novel to this case. We have recognized, in the ratemaking context, that “[t]he propriety of including all taxes among cost of service expenses has been long established.”
III. Capacity Auction True-Up
AEP complains that the PUC and the court of appeals erred in declining to base the capacity auction true-up under Section 39.262(d)(2) on actual prices obtained in the capacity auctions it conducted under Section 39.153. Specifically, it contends: “The court of appeals erred by upholding an order that disregards the true-up statute and rule, both of which prescribe a formula that must be applied regardless of whether a utility sells 15% of its capacity at auctions in compliance with
AEP contends that due to lack of market demand it was unable to sell the full 15 percent of its capacity specified in Section 39.153 and PUC rules thereunder specifying four separate gas products, but that the Section 39.262(d)(2) capacity auction true-up should still be based on the prices actually obtained in the capacity auctions conducted under Chapter 39. The same issue arose in State v. PUC, and we agreed with the utility, as we agree with AEP today, that “Section 39.262 unambiguously specifies that the statutory capacity auction price, not some other blended price the PUC finds more appropriate, must be used in calculating the capacity auction true-up amount.”
IV. Interest on Stranded Costs
The Consumers argue that interest on stranded costs should not have been assessed under PUC Rule 25.263(0(3). They argue that we invalidated the Rule in CenterPoint Energy, Inc. v. Public Utility Commission,
V. Conclusion
We grant the petition for review, and without hearing oral argument,
. 258 S.W.3d 272, 276.
. See State v. Pub. Util. Comm'n, 344 S.W.3d 349, 352-54 (Tex.2011) (State v. PUC); Tex.
. Tex. Util.Code § 39.262. All statutory sections cited herein are found in Chapter 39 of the Texas Utilities Code.
. The issues and arguments discussed below are not all raised by the same Consumers. For brevity we identify any issue or argument raised by any Consumer as one raised by "the Consumers.”
. State v. PUC, 344 S.W.3d at 356.
. Id. at 356.
. Tex. UtiuCode § 39.262(i) (emphasis added).
. See State v. PUC, 344 S.W.3d at 353 n. 15 and accompanying text.
. See id. at ("[A]n agency’s interpretation of the statute it administers is entitled to serious consideration so long as it is reasonable and does not conflict with the statute's language.”).
. See Tex. Workers’ Comp. Ins. Fund. v. DEL Indus., Inc., 35 S.W.3d 591, 593 (Tex.2000).
. State v. PUC, 344 S.W.3d at 361.
. Tex. Util.Code§ 39.251(4).
. At one point, the ECOM model predicted "that no generation company was projected to have stranded costs,” CenterPoint Energy, Inc. v. Pub. Util. Comm’n, 143 S.W.3d 81, 91 (Tex.2004), but ultimately billions of dollars in stranded costs were assessed at the final true-ups of the utilities subject to Chapter 39.
. State v. PUC, 344 S.W.3d at 364.
. Id.
. 258 S.W.3d at 295-96 (remanding for reconsideration in light of CenterPoint Energy Houston Elec., LLC v. Gulf Coast Coalition of Cities, 252 S.W.3d 1 (Tex.App.-Austin 2008), rev’d in part sub nom. State v. Pub. Util. Comm’n, 344 S.W.3d 349 (Tex.2011), and in light of Cities of Corpus Christi v. Pub. Util. Comm'n, 188 S.W.3d 681 (Tex.App.-Austin 2005, pet. denied)).
. 344 S.W.3d at 364.
. Id. at 364.
. The PUC suggests in its briefing that some recovery of interest on retained excess earnings should be made on remand of the PUC docket that ordered the EMCs. We express no opinion on this question, and our decision today is not intended to foreclose an adjustment to interest on excess earnings in another proceeding.
. 344 S.W.3d at 377.
. 258 S.W.3d at 308-14.
. Id. at 287-93 (Patterson, J., dissenting).
. 344 S.W.3d at 361.
. See id. at 365.
. Id. at 366.
. See State v. Gonzalez, 82 S.W.3d 322, 327 (Tex.2002) ("[W]e determine legislative intent from the entire act and not just from isolated portions.”); State v. Pub. Util. Comm’n, 883 S.W.2d 190, 196 (Tex. 1994) ("In ascertaining the scope of the Commission’s authority, we must read PURA as a whole to ascertain the underlying legislative intent.”).
. In concluding that AEP’s auction of its generation assets met the test of a bona fide transaction under a competitive offering, the PUC was persuaded by evidence that AEP used competent and independent advisers, engaged in broad marketing efforts, employed an auction structure that promoted competitive bids, provided bidder access to equal and accurate data, and negotiated vigorously with bidders.
. State v. PUC, 344 S.W.3d at 366 (quoting Sections 39.252(d) and 39.262(j)).
. Id. at 355-56 (quoting Mireles v. Tex. Dep’t of Pub. Safety, 9 S.W.3d 128, 131 (Tex.1999)).
. The PUC plausibly reasoned in its Order: If [AEP] had determined an intrinsic value for its STP share, and established a walkaway price, it may have attempted to negotiate a higher price for STP, modified its
. See 258 S.W.3d at 293, 314-15.
. See § 39.262(a) (providing that a utility “may not be permitted to overrecover stranded costs” at the true-up proceeding).
. Suburban Util. Corp. v. Pub. Util. Comm'n, 652 S.W.2d 358, 363 (Tex.1983).
. 324 S.W.3d at 97.
. Id. at 104 n. 57.
. 324 S.W.3d at 101-05.
. See Tex.R.App. P.59.1.
. 344 S.W.3d at 376.
. 143 S.W.3d 81 (Tex.2004).