Plaintiff in error sued defendant in error for a balance of $150, alleged to be due it on a contract to furnish certain cement stone, to be used in finishing his residence and garage in Waco, in accordance with the plans and specifications of M. W. Scott, as well as for extra material furnished to him, and used thereon, but not specified in said contract, amounting to $642.15, aggregating the sum of $792.15.
Defendant, after admitting that he owed plaintiff on the contract and for extras a balance of $546.15, resisted payment thereof, on the ground that said stone was not in accordance with the contract, but was inferior in quality, grade, and finish, whereby he was damaged to the extent of $2,000; and likewise pleaded that certain of said material was not of the size and dimensions required, for which reason, he was compelled to do extra work and labor thereon to conform same to proper requirements, to his injury in the further sum of $250, both of which amounts, less his admitted indebtedness, he pleaded in set-off and as a counterclaim. *Page 1159
A jury trial resulted in a verdict for defendant in the sum of $1,000 damages, upon which judgment was entered, to the effect that plaintiff take nothing, and that defendant recover of plaintiff said amount. There was no disposition, however, by the verdict of plaintiff's cause of action, and it was urged in the motion for new trial that the verdict was not responsive to the issues, and failed to dispose thereof. It is also insisted that the court failed to give in charge the correct measure of damages, and these form the basis of the first and second assignments of error.
The court, in its charge, did not submit any issue under which the jury could have found in favor of defendant against plaintiff for any sum whatever, but were merely directed to set off such damages as they might find defendant sustained by reason of inferior stone having been furnished to him by plaintiff against such sum as they might find for plaintiff under the first section of the charge. The verdict must be responsive to the issues. Marsalis v. Patton,
The verdict of the jury is indefinite and uncertain, because from it we are unable to determine whether they meant merely to find $1,000 in favor of defendant as the maximum damages, or intended to find that such amount represented the difference between what they thought plaintiff was entitled to recover and the amount of damages actually suffered by defendant. It is probable, if we are allowed to indulge in speculation, that they found that defendant was only entitled to the sum of $1,000, as damages, and that the court would be authorized to deduct from this amount the amount that he admitted that he was due plaintiff under said contract and for extra work, which, however, the court was not authorized to do. But, be this as it may, the fact is the verdict is indefinite and uncertain, and does not pass upon the issues submitted in the charge, and should not, for this reason, be allowed to stand.
We think, however, that the proper measure of damages was given. The rule seems to be that an owner who has sustained injury by reason of the breach of a contract by the builder may recover, either in an independent action, or as a set-off or counterclaim in an action by the builder for damages which are the proximate result of the breach. The amount of such damages is usually the difference between the value of the work done or building constructed and that contracted for. See 6 Cyc. p. 113, subd. 2, note 71, and authorities there cited. This rule may be qualified, we think, so as to allow a recovery only for the difference between what it would actually cost to replace the inferior work and material with work and material conforming to contract, where this could be done without injury to the building, But no such qualification was requested by plaintiff in error, nor are we prepared to say that such limitation would be proper in the present case, for the reason that it may be impossible to remove the stone, and put in such as called for by the contract, even if inferior stone had been furnished, as contended by defendant in error.
For the error indicated in failing to grant a new trial, the judgment of the court below is reversed, and the cause remanded.
Reversed and remanded. *Page 1160
Sapp v. Anderson , 135 S.W. 1068 ( 1911 )
Hedrick v. Smith , 146 S.W. 305 ( 1912 )
City of Fort Worth v. Williams , 55 Tex. Civ. App. 289 ( 1909 )
Michon v. Ayalla , 84 Tex. 685 ( 1892 )
Marsalis v. Patton , 83 Tex. 521 ( 1892 )
Ft. W. D.C. Ry. Co. v. MacKney , 83 Tex. 410 ( 1891 )
Gulf, C. & S. F. Ry. Co. v. Saunders , 286 S.W. 919 ( 1926 )
Missouri, K. & T. Ry. Co. of Texas v. Pace , 184 S.W. 1051 ( 1916 )
Mulligan v. McConnell Bros. , 242 S.W. 512 ( 1922 )
Independent Shope Brick Co. v. Dugger , 281 S.W. 600 ( 1926 )
National Life & Accident Ins. Co. v. Parnell , 89 S.W.2d 789 ( 1935 )
Texas N. O. R. Co. v. Robinson , 57 S.W.2d 938 ( 1933 )
New Home Construction Corporation v. O'NEILL , 373 S.W.2d 798 ( 1963 )