In October, 1916, the appellant filed this suit againsst E. T. Grimmett and Dunk Inman, seeking a judgment for the sum of $1,011.68 alleged to be due him upon an account for merchandise sold and delivered to the defendant Grimmett. It is alleged, in substance, that Grimmett had a contract with the Womack Construction Company to build a section of a good road being constructed in Grayson county; that it was necessary, to enable Grimmett to carry out his .contract with the construction company, that he have financial assistance, and for that purpose Inman assumed to pay all of the indebtedness incurred by Grimmett necessary and incidental to the performance of his contract. It is further alleged that Inman had an interest in the contract with Grimmett, and that his interest was of such a.nature that any indebtedness incurred by Grimmett in the contraction work, or incidental thereto, was beneficial to Inman; and that Inman, in order to make the performance of Grimmett’s contract with the construction company possible, assumed to pay Grimmett’s debts; that he was to receive, and has received, commissions, profits, and percentages from the amounts due Grimmett by the construction company on the contract; that Inman has received, and is still receiving, money that was to have been paid Grimmett upon that contract as those *262 amounts became due and 'payable. It is also alleged that the plaintiff had an agreement with Inman by which the latter expressly promised to pay the debts already contracted by Grimmett and to guarantee the payment of future debts contracted by him in the prosecution of the work; and that the plaintiff, relying upon those promises of In-man, extended credit to Grimmett.
Grimmett filed no answer, and judgment was rendered against him by default. Inman answered 'by a general denial, and specially pleaded that, on or about May 29, 1916, he did agree to pay certain labor bills incurred by Grimniett then due and thereafter to become due; that in consideration of that undertaking he had an agreement by which he was to recover the money due Grimmett. from the construction company upon estimates made, and to pay it out in accordance with that understanding. He set out in his answer exhibits of money received and expended by him, in which it was made to appear that he had paid out more money upon those labor bills than he had received on Grimmett’s account. A demurrer to that portion of Inman’s answer was overruled.
This appeal is by Polk from a judgment rendered in favor of Inman.
In response to special issues submitted the jury found, in substance, the following facts: That Inman had no, interest in the construction contract with Grimmett; that the only contract ever made between Grim-mett and Inman was that evidenced by a written agreement to pay the labor bills due and to become due’by Grimmett in the course of the construction work; that Inman never agreed or promised to stand behind Grim-mett, or to guarantee the payment of any future purchases made by Grimmett to the plaintiff; that he never assumed unconditionally to pay an amount claimed by the appellant to be due from Grimmett. According to the appellant’s testimony, when he first presented his account against Grimmett and Inman for payment the latter agreed unconditionally to pay it, and also authorized the appellant to make future advances to Grim-mett. The jury found that Inman agreed to pay that account out of the balance, if any, of estimates due Grimmett after deducting amounts which Inman had previously paid or was obligated to pay under the terms of his contract with Grimmett. There is no contention that the evidence showed any balance of debt. It is not claimed that under the findings made by the jury any. other judgment than that entered should have been rendered.
The judgment is affirmed.