Judges: James
Filed Date: 10/11/1911
Status: Precedential
Modified Date: 11/14/2024
The parties herein, on November 28, 1908, made a contract, by which Powell agreed 'to make two wells for Williamson for the price of $2 per foot, the wells “to be made to a depth of 550 feet or to the second stratum of the artesian water, with 12-inch casing, and the balance of the depth tq be made with an 8-inch easing, is to be commenced not later than the 5th of December, 1908, and to be done in a good workmanlike manner and pushed to completion by party of the second part,” and further “to furnish his own fuel oil and to haul same and build derricks and to guarantee "these wells to be equal to the average of the surrounding wells.”
Williamson agreed “to furnish all material needed in the construction of said wells, ■ su.ch as all necessary casing, screenings and material for one derrick for each well and to do the hauling of all machinery and materials necessary for the completion of the work.” It was further agreed that Williamson “is to advance to the party of the second part $500.00 which is to be credited on the first well, and when the first well is completed the party of the first part is to pay the party of the second part $2.00 per foot for said well without delay.”
Appellee Powell brought this action, alleging the contract, and alleging in substance that defendant failed to haul plaintiff’s machinery and apparatus to the site of the first wells to be bored, and that plaintiff was compelled to do so at the expense of $50, completing said hauling on December 13, 1908, and on.January 7, 1909, he completed the first well to the depth of 521 feet to the artesian stratum, and was then ready and anxious to place the easing therein and complete the well for washing and testing; that, though under the contract the casing should have been on the ground, in order for it to be rushed to completion and to protect the well from caving, defendant failed to have it there when so needed, whereby plaintiff was compelled to suspend operations and permit said well to remain uncased, and to hold his crew and machinery idle for 27 working days and until about February 10, 1909, waiting for the casing, and causing great additional damage and loss of time by the caving in of said well, to plaintiff’s damage, $675; that on March 25, 1909, when said well was ready for the washing and placing of the pit and pump therein, and a Lane & Bowler interlocking steel pit and pump had been placed upon the ground, to be placed in said well, and the use of the same would have permitted the sinking of the well to any depth desired by defendant, defendant refused to permit said pit and pump to be used, and thereafter, after plaintiff being thus caused a delay of three days at an expense of $75, defendant delivered for use in said well a Gray pump in lieu thereof; that on April 3, 1909, plaintiff completed said well in accordance with the terms of the contract, and placed the Gray pit and pump therein, and pumped and tested said well, and proved an exceptionally good well, and defendant thereupon received and accepted said well, and promised to pay plaintiff therefor, and, then and there discharged plaintiff from all further obligation to sink the second well, and promised to pay plaintiff $2 per foot for the 521 feet, the depth of said well, less the sum of $500 advanced, leaving a balance of $542 of the contract price.
The petition claimed damages for the said sums of $542, $75, $675, $5, and the further sum of $150, for the sinking and setting of the Gray pit and pump, which defendant promised to pay, and which was a reasonable charge therefor, making in all $1,492. Certain persons joined the plaintiff as interven-ers.
The defenses need not be stated, unless it may be necessary to do so in passing on the assignments of error. There was a verdict for plaintiff for $542, balance of the contract price, $270 for 27 days delay in waiting for *361 materials, and $76 for three days holding the crew waiting for the pit and pump.
We overrule the third assignment of error; to sustain it would be to hold that a party has to plead his evidence.
The tenth assignment complains of the following charge: “If you believe from the evidence that the first well was completed by plaintiff and interveners in compliance with the contract, and that the well was equal in flow to the average of the surrounding wells then in existence, and you further believe that at the time of such completion of the'first well, if it was so completed, that the defendant failed and refused to pay the balance of the contract price due thereon, and failed to provide the lumber for the derrick for the second well, and failed to provide and place the materials necessary to the making and completion of the same on the ground, and failed to mark or indicate the location of the said second well and notify plaintiff and interveners thereof, then you are instructed that the plaintiff and interven-ers were not required to go further in the execution of the contract, and could not proceed to enforce same for liabilities created in the sinking of the first well.” The proposition is that: “When one party seeks to justify abandonment of a contract, or a discharge from performance of the same, on account of the failure of the other party thereto, he must allege and prove an offer or ability to perform his part thereof;” and appellant words his contention as follows: “Plaintiffs never having furnished the first well, the occasion never arose for lumber for derricks for the second well, nor for designating the spot where it should be bored.” Defendant pleaded failure of performance by plaintiff, and introduced testimony to establish same, and pleaded in reconvention. Plaintiffs alleged and proved performance on their part and sufficient matter to excuse them from proceeding with the second well; therefore there is no merit in the proposition.
The thirteenth assignment, complaining of the refusal of a new trial, is overruled.
In the preparation of this opinion, we have confined ourselves to the points as they are made in appellant’s brief. There being no error in what is presented in the brief, the judgment is affirmed.