It appears from the record that appellants objected, but did not state the grounds of their objection, to certain instructions the trial court gave to the jury. A general objection is not a compliance with the requirement of the statute (article 1971, Vernon's Sayles' Civ. St. 1914) that objections a party has to instructions shall be presented to the court before such instructions are read to the jury. The plain purpose of the statute, said Chief Justice Phillips, in Walker v. Haley (Sup.)
"is to provide the court, in advance, with the objections to which the charge is deemed subject, so as to afford opportunity for its correction. * * * It is, in a word, to secure, as far as possible, the preparation and submission of a correct charge to the jury."
It is obvious that an objection which fails to particularly point out supposed defects in a charge would be of little, if any, aid toward the accomplishment of such purpose, and hence that a general objection was not the kind of an objection the members of the Legislature had in mind when they enacted the statute. It follows that appellants are not in a position different from that they would have been in had they not objected to the charge at all, and that, not only are they not entitled to have the assignments in their brief based on instructions given considered, but this court is without right to consider same. Waterman Lumber Co. v. Beatty, 218 S.W. 363; Railway Co. v. Dickey,
The other assignments in appellants' brief are predicated on the action of the trial court in refusing their request to give to the jury the special charges numbered 1, 2, 3, and 4, set but in the record.
It was not error to refuse the first and fourth of said special charges, because the issues they presented were, so far as they were material, sufficiently covered by the court's main charge.
The second and third of the charges, had they been given, would have told the jury to find for appellants if they believed the effect of the dam constructed by appellees across Boggy creek was to divert its waters and cause same to be discharged at the end of the ditch in "greater quantities and more rapidly," quoting from one of them, "than they had been previously discharged at said point, and that as a result the plaintiffs' land was caused to be overflowed more often or to a greater extent than had previously been the case," and further believed that an effect of such increase in the number and extent of overflows on appellants' land was to depreciate the market value thereof. A majority of the members of the court think that the fact alone, if it was a fact, that appellants' land, because of acts of appellees shown by the testimony, was overflowed to a greater extent, or more frequently, and its market value thereby depreciated, than it otherwise would have been, did not entitle them to recover damages of appellees, and therefore that it was not error to refuse the charges. The writer is of a contrary opinion, but will not discuss the question, as he agrees with the other members of the court that the assignments based on the refusal of the charges should be overruled on another ground, to wit, that the charges were not consistent with parts of the main charge appellants were in the attitude of not having objected to, in which the jury were told to find for appellees if they believed Boggy creek had lost its channel on their land, and that as a consequence thereof its waters had been so diverted as to flow southwest along a natural depression thereon, and further believed that the ditch appellees dug and the levee they constructed were in said depression, and that in digging the ditch and constructing the dam and levee they used due care, notwithstanding they also believed that the effect of the dam, ditch, and levee was to hasten the flow of the waters of said creek to a point on appellees' land near appellants', where same were discharged from such ditch "in greater quantities by reason of running faster, thereby" overflowing appellants' land.
While the rulings in Rabinowitz v. Smith Co.,
*Page 526The judgment is affirmed.
Rabinowitz v. Smith Co. , 1916 Tex. App. LEXIS 1143 ( 1916 )
Walker v. Haley , 110 Tex. 50 ( 1919 )
Gulf, Texas & Western Railway Co. v. Dickey , 108 Tex. 126 ( 1916 )
Witt v. Young , 1917 Tex. App. LEXIS 454 ( 1917 )
Ft. Worth & D. C. Ry. Co. v. Miller , 1918 Tex. App. LEXIS 205 ( 1918 )
Brewster v. City of Forney , 1917 Tex. App. LEXIS 725 ( 1917 )
Schaff v. Scoggin , 1918 Tex. App. LEXIS 312 ( 1918 )
Roberts v. Houston Motor Car Co. , 1916 Tex. App. LEXIS 872 ( 1916 )
Hendrick v. Blount-Decker Lumber Co. , 1917 Tex. App. LEXIS 1182 ( 1917 )
City of Abilene v. Reed , 1927 Tex. App. LEXIS 311 ( 1927 )
Isbell v. Lennox , 116 Tex. 522 ( 1927 )
TEXAS EMPLOYERS'INSURANCE ASSOCIATION v. Jones , 393 S.W.2d 305 ( 1965 )
Lancaster v. Jarrett , 267 S.W. 518 ( 1924 )
Ansley v. Tarrant County Water Control & Improvement ... , 1973 Tex. App. LEXIS 2858 ( 1973 )