DocketNumber: No. 94-516 C
Citation Numbers: 39 Fed. Cl. 276, 1997 U.S. Claims LEXIS 265, 1997 WL 722813
Judges: III, Tidwell
Filed Date: 11/19/1997
Status: Precedential
Modified Date: 10/18/2024
ORDER
Following this court’s resolution of liability and damages in favor of plaintiff, defendant filed a Motion for Costs pursuant to Rule 68 of the United States Court of Federal Claims (RCFC 68). Plaintiff opposed the motion, and on February 18, 1997, filed an application for attorney fees and other expenses pursuant to the Equal Access to Justice Act (EAJA), 28 U.S.C. § 2412 (1994). For the reasons discussed herein, the court denies defendant’s Motion for Costs and partially grants plaintiffs EAJA application for fees in the amount of $50,205.16.
FACTS
The above-captioned ease arose from contract number 50-9JHA-3-1F153, entered into by plaintiff and the Forest Service of the United States Department of Agriculture (USDA) in September 1993. Under the contract, plaintiff was required to perform construction work on the Eagle Lake Ranger Station project in Redding, California.
Plaintiff submitted a certified claim to the contracting officer on May 16, 1994, on the ground that the default termination was improper and should be converted to a termination for convenience. The contracting officer failed to respond to plaintiffs claim within sixty days. On August 9, 1994, plaintiff filed a claim in this court seeking damages in the amount of $258,053. Plaintiff argued the termination was improper because: (1) plaintiff was not required to perform in the absence of a necessary change order; and (2) defendant did not consider any intervening factors that may have justified any delay in construction. Defendant asserted that the termination for default was justified as a result of plaintiffs alleged anticipatory repudiation of the contract. Defendant maintained that although the parties disagreed over the interpretation of the contract, plaintiff was still required to perform.
The court bifurcated trial into liability and damages phases. At the trial on liability, held on April 1-3, 1996, the court ruled in favor of plaintiff, holding that plaintiff was not in default and that defendant did not reasonably anticipate a failure by plaintiff to perform. The court also found that a change order was not required. Under the contract terms, therefore, the termination for default was converted to a termination for convenience.
On October 23, 1996, between the liability and damages phases of trial, defendant made an Offer of Judgment to plaintiff, pursuant to RCFC 68, in the amount of $58,000, with each party to bear its own costs.
DISCUSSION
There are two issues before the court. First, whether the court, in comparing plaintiffs final judgment to the RCFC 68 Offer of Judgment, should consider plaintiffs EAJA compensation. Second, whether, and to what extent, plaintiff is entitled to fees pursuant to its EAJA application.
In cases where a defendant has been found liable by order or judgment, but the amount of damages has not yet been determined, RCFC 68 allows the defendant to make an offer of judgment not less than ten days before the damages phase begins. R.U.S.Ct.Fed.Cls. 68. (RCFC 68). If this offer is rejected and “the judgment finally obtained by the offeree is not more favorable than the offer, the offeree must pay the costs incurred” by the offeror after such offer was made. Id. The rule thereby provides an incentive for plaintiffs to settle a case when presented with an attractive offer, especially under circumstances “in which there is a strong probability that the plaintiff will obtain a judgment but the amount of recovery is uncertain.” Delta Air Lines, Inc. v. August, 450 U.S. 346,101 S.Ct. 1146, 67 L.Ed.2d 287 (1981).
Plaintiff denies that defendant’s Offer of Judgment exceeds the judgment finally obtained, arguing that, when calculating a party’s final judgment, the court should include any pre-offer costs to which the party is entitled pursuant to the EAJA.
First, the court finds that the inclusion of pre-offer costs does not run counter to the purpose of Rule 68. In Marek v. Chesny, 473 U.S. 1, 105 S.Ct. 3012, 87 L.Ed.2d 1 (1985), the Supreme Court, while clearly rejecting the inclusion of post-offer costs in the Rule 68 comparison, indicated that pre-offer costs are properly added. The Court stated that:
[A]t the time an offer is made, the plaintiff knows the amount in damages caused by the challenged conduct. The plaintiff also knows, or can ascertain, the costs then accrued. A reasonable determination whether to accept the offer can be made by simply adding these two figures and comparing the sum to the amount of-fered____ [Pjostoffer costs merely offset part of the expense of continuing the litigation to trial, and should not be included in the calculus.
Id. at 7,105 S.Ct. at 3015; Accord Grosvenor v. Brienen, 801 F.2d 944, 948 (7th Cir.1986) (“[T]he amount of fees allowed the plaintiff for pre-offer legal services is relevant to the determination whether Rule 68 applies in a particular ease.”).
Second, as defendant correctly points out, the purpose of RCFC 68 is to cause “both parties to a suit to evaluate the risks and costs of litigation, and to balance them against the likelihood of success upon the trial on the merits.” Marek, 473 U.S. at 5, 105 S.Ct. at 3014. It appears that plaintiff evaluated its costs and potential gains before rejecting defendant’s offer. Defendant made an offer after plaintiff had prevailed on the entitlement phase of the litigation. That offer was for $58,000 with each party to bear them own costs. For plaintiff not to consider recoverable costs in evaluating the $58,000 offer, as defendant seems to advocate, plaintiff would have to ignore the likelihood of obtaining a favorable award pursuant to its success in the liability phase of trial and of recovering at least some of its costs pursuant to the EAJA See Weaver-Bailey Contractors, Inc. v. United States, 24 Cl.Ct. 576 (1991) (holding that a plaintiff’s success on the merits of a case creates a prima facie entitlement to attorney fees, thereby shifting the burden to the defendant to prove substantial justification); see also United States v. 313.3b Acres of Land, 897 F.2d 1473 (9th Cir.1989) (holding that the EAJA creates a rebuttable presumption that fees shall be awarded to a prevailing party in litigation against the government).
[T]he term “cost” ... was intended to refer to all costs properly awardable under the relevant substantive statute or other authority. In other words, all costs properly awardable in an action are to be considered within the scope of Rule 68 “costs.” Thus, absent congressional expressions to the contrary, where the underlying statute defines ‘costs’ to include attorney’s fee, we are satisfied such fees are to be included as costs for purposes of Rule 68.
473 U.S. at 9,105 S.Ct. at 3016. The underlying statute in Mwrek was 42 U.S.C. § 1988, which provides that a prevailing party in a section 1983 action may be awarded attorney fees as costs. In the present case, defendant argues that the Contract Disputes Act (CDA), 41 U.S.C. §§ 601-613 (1994), is the underlying statute and that plaintiff has not indicated how attorney fees constitute a “cost” therein. Defendant relies on the court’s order of November 12, 1996, which found in favor of plaintiff and awarded that party “costs and interest pursuant to the Contract Disputes Act, 41 U.S.C. § 611 (1994),” to support its claim that the CDA controls.
Defendant reads the court’s order incorrectly. The order refers only to section 611 of the CDA, rather than the entire act. Section 611, entitled “Interest,” merely establishes the first date that the government must pay interest and at what rate. It does not refer to costs. Thus, the court’s reference to section 611 modifies only the court’s order as to interest; it should not be read as the exclusive source for determining what costs are properly awardable in this ease. Furthermore, defendant overlooks the plain language of the Supreme Court’s decision in Mwrek. The Court explicitly stated that “costs” include “all costs properly awardable under the relevant substantive statute or other authority.” Marek, 473 U.S. at 9, 105 S.Ct. at 3016 (emphasis added). In the present case, the EAJA is such “authority”, supporting the proper award of attorney fees.
II. Plaintiffs EAJA Application
A. Whether Defendant’s Position Was Substantially Justified
Section 2412(b) of the EAJA specifies that a court shall award fees and expenses to a prevailing party in litigation against the government “unless the court finds that the position of the United States was substantially justified or that special circumstances make an award unjust.” 28 U.S.C. § 2412(b) (1994). The court’s decision must be based solely on the existing record. Gavette v. OPM, 808 F.2d 1456, 1467 (Fed. Cir.1986) (en banc). The government carries the burden of demonstrating the substantial justification of its position. Id. at 1465-66.
As required by the Act, plaintiffs application asserts that defendant’s position was not substantially justified, and alleges entitlement to $107,884.35 in fees and costs. Defendant disputes this application, asserting that its position was substantially justified under the circumstances. Given the record before it, this court finds no substantial justification for defendant’s position with respect to either the contracting agency’s original conduct or defendant’s position taken during the litigation of the parties’ liability. Moreover, even if the court were to find substantial justification for defendant’s stance during the damages phase of litigation, the court finds that defendant’s earlier conduct was so unreasonable that it would be inequitable to deny fees on the basis of such conduct.
The Supreme Court stated that the term “substantially justified” means “justi
Defendant contends that plaintiffs failure to give adequate assurances constituted an anticipatory repudiation of the contract that substantially justified the termination for default.
In the present case, the contractor had already performed a substantial portion of the contract and defendant’s termination interrupted that performance in midstream. At trial on April 3, 1996, the court found no reasonable basis for this interruption. Plaintiff had not demonstrated a clear, definite, and unequivocal intent to cease performance, nor could plaintiffs actions be reasonably interpreted as such. On the contrary, it was inherently unreasonable for defendant to believe that plaintiff had, in fact, repudiated the contract. Thus, defendant fails to carry its burden of proving substantial justification for its position.
B. Whether Plaintiffs Fees and Expenses Are Compensable Under the EAJA
Given defendant’s lack of substantial justification for its “position,” the court next must determine the amount of fees defendant owes plaintiff Pursuant to the EAJA, the court “may award reasonable fees and expenses of attorneys ... to the prevailing party in any civil action brought by or against the United States.” 28 U.S.C. § 2412(b) (1994). Thus, the overarching issue is the extent to which plaintiffs fees and expenses are reasonable.
Defendant challenges plaintiffs attorney fees on several bases. First, defendant argues that plaintiff lacks contemporaneous documentation for all of plaintiffs counsel’s services rendered. Alternatively, defendant states that plaintiffs fees should be reduced because plaintiffs itemization mistakenly includes: (1) attorney fees incurred prior to filing the complaint; (2) the costs of dealing with a surety; (3) accountant fees incurred by Pacific Cascade, rather than Prowest Diversified; and (4) insufficiently detailed accountant fee records. Defendant further disputes plaintiffs assertion of entitlement to a heightened hourly fee. Finally, defendant argues that plaintiff may only claim a prorata share of attorney fees incurred for assembling plaintiffs EAJA application. The court will discuss both parties’ arguments as
1. Sufficiency of Plaintiffs Counsel’s Documentation
The EAJA requires plaintiff to provide the court with an application specifying “the amount sought, including an itemized statement from any attorney or expert witness representing or appearing in behalf of the party stating the actual time expended and the rate at which fees and other expenses were computed.” 28 U.S.C. § 2412(d)(1)(B) (1994). Furthermore, “under EAJA contemporaneous records of attorney’s time and usual billing rates, as well as a breakdown of expenses are necessary in order to determine the reasonableness of charges.” Napomno Iron & Metal Co. v. United States, 825 F.2d 403, 404 (Fed.Cir. 1987). In the present ease, plaintiff appended an itemization of plaintiffs counsel’s services rendered to its EAJA application. (PL’s Appl. for Award of Fees & Other Expenses Pursuant to Provisions of Equal Access to Justice Act.) Plaintiff claims that it utilized 453.2 hours in attorney fees, expended $15,447 in expert or consultant fees, and incurred $1,797.35 in other expenses, to pursue its claims against the United States. The itemization lists plaintiffs specific tasks in chronological order and includes a description of the service, the amount of time spent performing it, the hourly fee charged, and the total amount charged per task. The printout is dated February 15,1997, although the itemized services were performed between May 5, 1994, and February 12, 1997. Plaintiff explains that the billing summary is dated February 15, 1997, because this was the date plaintiffs counsel, David A. Perkins, printed out a complete billing statement for plaintiff. Plaintiff stated that interim billing statements had been issued and were paid, excepting the last few billing statements.
First, defendant argues the itemization is not contemporaneous because plaintiff has not provided “attorney time sheets.” In response, plaintiff presents Perkins’ declaration that he entered the billing information directly onto a computer program, which generates billing statements to clients. As a result, Perkins does not use attorney time sheets. Thus, plaintiff represents that each item on the itemization is a contemporaneous entry by either Perkins or his staff.
The court finds that plaintiffs counsel’s failure to keep time sheets does not make counsel’s billing records per se non-contemporaneous. To deem Perkins’s computer records non-contemporaneous, by sheer virtue of the absence of a time sheet on paper, would be tantamount to denying technology a place in record-keeping. It is commonplace for attorneys to use computers for billing records, and although many attorneys still keep time sheets, the court sees no legitimate reason to require the use of a paper record over a computer-generated record.
Second, defendant argues that plaintiffs counsel’s records are not contemporaneous because the only proof of plaintiff’s counsel’s billing records was the itemization dated February 15,1997. Although plaintiff stated that counsel had sent interim billing statements, plaintiff did not append these interim billing statements to the EAJA application, filed February 18, 1997. Consequently, the court issued an order on August 19, 1997, permitting plaintiff to submit supplemental records, including plaintiffs counsel’s interim billing statements, usual billing rates, the nature of the fee arrangement, and a record of who performed which service. Plaintiff subsequently filed plaintiffs counsel’s monthly billing statements, which are dated between June 7, 1994, and April 16, 1997. As stated in Scherr Constr. Co. v. United States, 26 Cl.Ct. 248 (1992), the periodic nature of a billing statement does not “thwart the requirement that a statement of fees and expenses be contemporaneous with the work performed and costs incurred.” Id. at 251. The Scherr court found that a monthly billing statement satisfied the EAJA requirement for contemporaneous records. Id. at 250-51. In accordance with Scherr, the court finds that plaintiffs monthly statements satisfy the requirement that counsel’s record be kept in a contemporaneous fashion.
Defendant, however, also questions whether plaintiff established its counsel’s usual billing rate and the nature of its fee agreement.
2. Reasonableness of Fees and Expenses
a. Pre-Complaint Attorney fees
Plaintiffs counsel’s itemization lists 70.6 hours spent between May 5, 1994 and the filing of the complaint on August 9, 1994. Defendant argues that plaintiffs expenses incurred prior to filing its complaint are not recoverable to the extent that the hours were not spent drafting and filing the complaint. Plaintiff argues that it incurred these attorney fees in order to understand the facts of the case, analyze the termination for default, and prepare the pleadings. Further, plaintiff asserts these tasks needed to be performed, irrespective of when they occurred.
The court finds that many of the services rendered prior to filing the complaint are not compensable. In Levemier Constr., Inc. v. United States, 947 F.2d 497 (Fed.Cir.1991), the United States Court of Appeals for the Federal Circuit held that, of the fees incurred by a prevailing party prior to filing the complaint, recovery under the EAJA is “narrowly limited only to ‘fees for legal and factual research preparatory to Claims court litigation.’ ” Id. at 501 (citing Cox Constr. Co. v. United States, 17 Cl.Ct. 29, 33-34 (1989)). More specifically, the court held that, “at its earliest, EAJA coverage may begin after the decision of and in pursuit of an appeal from the decision of a contracting officer.” Id. at 502.
In the present case, plaintiff submitted a certified claim to the contracting officer on or around May 16,1994, arguing that the termination for default should be converted to a termination for convenience. The contracting officer failed to respond to the claim within the 60 day-period prescribed in the Contracts Disputes Act. 41 U.S.C. § 605(e) (1994). In light of this failure to respond, plaintiff interpreted the contracting officer’s inaction as a denial of its certified claim pursuant to 41 U.S.C. § 605(c)(5) (1994). Thus, plaintiff could not have pursued an appeal of the contracting officer’s “decision” until July 15, 1994. Thereafter, plaintiff legitimately interpreted the lack of response as a denial of the claim, and could direct counsel’s subsequent activities toward mounting an appeal of the decision. Only attorney fees incurred after July 15, 1994, are subject to EAJA coverage. Thus, none of plaintiff’s counsel’s services rendered prior to July 15, 1994, a total of 50.2 hours, are recoverable pursuant to the EAJA. (See Appendix, Table I.)
b. Fees Incurred for Dealings and Litigation with Plaintiffs Surety
Defendant argues that the attorney fees and accountant fees associated with litigation between plaintiff and its surety, ITT Hartford, are “outside the scope of this Court’s
In the present case, ITT Hartford issued a performance bond on the project at issue. After the USDA terminated the contract in December 1993, it requested that Hartford complete the project pursuant to the bond issued. Thereafter, plaintiff advised Hartford that the termination for default was improper, and accordingly, that Hartford should not honor the bond claim. In June 1994, USDA executed a Takeover Agreement with Hartford. Based on the Takeover agreement, Hartford completed the project and incurred additional costs of approximately $180,000. Hartford demanded payment of said cost overruns against plaintiff and its principals. (PL’s Memo, of Contentions of Facts and Law at 2-3, 8.)
The court finds the fees and expenses for plaintiff’s dealings with ITT Hartford to be outside the scope of the present litigation. In Lemelson v. United States, 8 Cl.Ct. 789 (1985), this court found that the “EAJA does not extend this court’s power to include an award of fees as between private parties, especially since this court had no such power prior to the enactment of the EAJA.” Id. at 792. The court further stated “[i]t is clear that this court has never had jurisdiction to decide a controversy between private parties.” Id. at 791 (citing United States v. Sherwood, 312 U.S. 584, 61 S.Ct. 767, 85 L.Ed. 1058 (1941)). Plaintiff and ITT Hartford are two such private parties. Any controversy between plaintiff and its surety is beyond the scope of this court’s jurisdiction.
Even if plaintiff’s interactions or litigation with a third party could somehow be reimbursed pursuant to the EAJA, it is clear that the relationship with ITT Hartford is outside the scope of the present action. Although plaintiffs litigation with Hartford began with defendant’s termination for default, the surety relationship existed independent of the contract between plaintiff and defendant. Plaintiff states it encouraged Hartford to refrain from honoring the performance bond because it believed the termination for default was improper. Such interactions, however, were irrelevant to the issues before the court. The primary substantive issue underlying the present case was whether defendant’s termination was for default or convenience. The issue of whether Hartford should have honored the performance bond is entirely irrelevant to the court’s decision. Thus, the court holds plaintiffs fees and expenses incurred for its litigation with ITT Hartford are not recoverable under the EAJA Of the 20.4 hours billed by Perkins prior to filing the complaint, the 12.5 hours attributable to the litigation with Hartford are not recoverable pursuant to the EAJA. The court finds the remaining 7.9 hours of plaintiff’s counsel’s billed time to be reasonable charges. Plaintiff is thus entitled to recovery for 7.9 hours billed to plaintiff for services rendered prior to filing the complaint.
c. Hours Billed by Plaintiff’s Counsel After Filing the Complaint
Defendant does not challenge the hours billed by plaintiff’s counsel between plaintiffs filing of the complaint on August 9, 1994, and plaintiffs work on the EAJA application, begun December 12, 1996.
d. Consultant/Expert Expenses
Defendant argues that plaintiff cannot recover $15,447 in consultant fees for services provided by plaintiffs accountant. Plaintiffs accountant’s billing statements evince services rendered to benefit plaintiff. However, the statements were not sent to plaintiff, Prowest Diversified; rather, the statements were sent to “Pacific Cascade.” Defendant asserts that pursuant to the EAJA, only the “prevailing party” in a civil action against the United States can recover consultant expenses. The court agrees. Because the prevailing party, Prowest Diversified, did not incur the expenses, plaintiff cannot recover the consultant expenses under the EAJA.
The EAJA states that, “a court shall award to a prevailing party other than the United States fees and other expenses ... incurred by that party in any civil action.” 28 U.S.C. § 2412(d)(1)(A) (1994) (emphasis added); see also 5 U.S.C. § 504(a)(1) (1994) (mandating recovery of fees and expenses “incurred by ... [a prevailing] party in an administrative adversary adjudication). Thus far, plaintiff has presented proof only that its accounting expenses were incurred
e. Other Expenses
Plaintiff also claims it incurred “other expenses,” in the amount of $1,797.35,
3. Hourly Rate
The parties disagree as to the hourly rate that plaintiff is entitled to recover pursuant to the EAJA. The EAJA provides that “attorney fees shall not be awarded in excess of $75 per hour unless the court determines that an increase in the cost of living or a special factor, such as the limited availability of qualified attorneys for the proceedings involved, justifies a higher fee.” 28 U.S.C. § 2412(d)(2)(A) (1994).
In Hensley v. Eckerhart, 461 U.S. 424, 103 S.Ct. 1933, 76 L.Ed.2d 40 (1983), the Court stated that, “[w]here a plaintiff obtained excellent results, his attorney should recover a fully compensatory fee. Normally this will encompass all hours reasonably expended on the litigation, and indeed in some eases of exceptional success an enhanced award may be justified.” Id. at 435, 103 S.Ct. at 1940. Plaintiff argues that such “excellent results” were achieved in the present case because plaintiff succeeded on the liability issues, with an “overwhelming weight of evidence” in plaintiffs favor. Although it is true that defendant was not substantially justified in its position, plaintiffs mere success on the merits is insufficient for an enhanced award. Contrary to plaintiffs assertion, the court does not have considerable “discretion” in awarding an enhanced fee. In Pierce v. Underwood, 487 U.S. 552, 108 S.Ct. 2541, 101 L.Ed.2d 490 (1988), the Court cautioned that exceptions to the EAJA cap on attorney fees “are not of broad and general application____ The ‘novelty and difficulty of issues,’ ‘the undesirability of the ease,’ the “work and ability of counsel,’ and ‘the results obtained, ’ ... are factors applicable to a broad spectrum of litigation; they are little more than routine reasons why market rates are what they are.” Id. at 573, 108 S.Ct. at 2554 (citation omitted) (emphasis added). In the present case, the court finds plaintiffs success unexceptional. To permit recovery of an enhanced award for such ordinary results would render the EAJA attorney fee cap meaningless.
The court further finds plaintiffs “expertise” with construction matters and government contracts cases an insufficient basis for an enhanced award. In Pierce, the Court stated that:
[T]he exception for “limited availability of qualified attorneys for the proceedings involved” must refer to attorneys “qualified for the proceedings” in some specialized sense, rather than just in their general legal competence. We think it refers to attorneys having some distinctive knowledge or specialized skill needful for the litigation in question — as opposed to an extraordinary level of the general lawyerly knowledge and ability useful in all litigation. Examples of the former would be an identifiable practice specialty such as patent law, or knowledge of foreign law or language. Where such qualifications are necessary and can be obtained only at rates in excess of the $75 cap, reimbursement above that limit is allowed.
Id. at 572, 108 S.Ct. at 2554. The present case does not require any specialized knowledge or skill of the kind described in Pierce. Id. Plaintiff did not require the use of a patent lawyer or a lawyer versed in a foreign law, and plaintiffs counsel accordingly did not possess such specialized skills. Rather, plaintiffs ease required only a level of general lawyerly knowledge and ability useful in all litigation. Thus, the court sees no justification for an hourly fee enhancement above the statutorily prescribed rate, plus the cost of living adjustment.
Therefore, the court denies plaintiffs request for an enhanced fee award of $200 per hour. Defendant does not oppose plaintiffs cost of living adjustment. The court finds the addition of the cost of living adjustment to the EAJA cap entirely appropriate, and therefore apples the $129 per hour rate.
The court finds the remaining 57.6 hours
The court orders plaintiff’s recovery of $50,205.16 pursuant to the EAJA for reasonable fees and expenses incurred in its civil action against the United States. Id.
III. RCFC 68 Comparison
As stated in Section I above, the court will take into consideration pre-offer attorney fees and costs awardable under the EAJA when ruling on defendant’s motion for costs. Thus, the court must determine the amount of pre-offer attorney fees and costs to which plaintiff is entitled, and use this amount in the RCFC 68 comparison.
Defendant made its Offer of Judgment on October 23,1996. Plaintiff’s counsel reasonably billed 224.6 hours to plaintiff for services rendered prior to this date. At an hourly rate of $129, plaintiffs awardable preoffer attorney fees amount to $28,973.40. Plaintiff’s pre-offer costs amount to $1,734.35. Thus, the court finds that plaintiff incurred pre-offer EAJA fees and expenses in the amount of $30,707.75. Plaintiff obtained a judgment of $46,476 from the court during the quantum phase of trial in November 1996. Plaintiffs judgment in combination with its EAJA compensation amounts to $77,183.75, an amount well in excess of defendant’s $58,000 offer of judgment. Thus, the court denies defendant’s motion for costs. (See Appendix, Table III.)
CONCLUSION
For the reasons set forth above, the court denies defendant’s Motion for Costs. The court grants plaintiff’s Application for Attorney Fees and Costs Pursuant to the EAJA and orders defendant to pay plaintiff $50,-205.16.
IT IS SO ORDERED.
Appendix
Table I: Plaintiffs Recoveiy of Fees & Expenses Under EAJA, Excluding Amounts Associated with Assembly of EAJA Application
Hourly
Dollar
Item
Hours
Rate
Amount
Total hours billed by plaintiff’s counsel pre-filing of complaint (5/4/94-8/9/94)
70.6
Disallowed hours between 5/4/94 and 7/15/94 — 50.2
Disallowed hours spent on litigation with surety — 12.5
Reimbursable hours pre-filing of complaint 7.9
Reimbursable hours after filing of complaint and before work began on EAJA application
244.4
Hours after work began on EAJA application, but not related to EAJA application
80.6
Total reimbursable attorney fees spent on EAJA application
332.9
$129
$42,944.10
Other Expenses
$1,797.35
Plaintiffs Recovery without EAJA Application Fees & Expense
$44,741.45
Table II: Recoverable Fees and Expenses for Plaintiffs Assembly of EAJA Application and Total EAJA Recovery
Hourly
%
Item
Hours
Rate
Recoverable
Dollar Amount
Plaintiffs Claimed Fees & Expenses without EAJA Application Fees & Expenses (at hourly rate of $129)
$60,846.35
Plaintiffs Recovery without EAJA Application Fees & Expenses
$44,741.45
Percent of Plaintiffs Claimed Fees Recovered
73.5%
Total Claimed Charges for Assembling Plaintiffs EAJA Application
57.6
$129
$7,430.40
Total Recoverable Fees for Assembly of EAJA Application
$7,430.40 X .735 = $5,463.71
Plaintiffs Recovery without EAJA
$44,741.45
Application Fees & Expenses Plaintiffs Total EAJA Recovery
$50,205.16
Table III: RCFC 68 Comparison
Item Hours Dollar Amount
Pre-Offer Attorney Fees at $129/hour 224.6 $28,973.40
Pre-Offer Costs $1,734.35
Pre-Offer Fees & Costs $30,707.75
Judgment $46,476
Judgment + Pre-Offer Fees & Costs $77,183.75
. This offer followed the liability phase of trial, and preceded the damages phase by ten days.
. Thus, plaintiff contends that defendant's Motion for Costs is untimely and asks the court to withhold decision on this motion until the EAJA application is considered.
. The EAJA provides that attorneys fees may be recovered by a “prevailing party in any civil action brought by or against the United States ... in any court having jurisdiction of such action.” 28 U.S.C. 2412(b) (1994).
. The court previously refuted this argument in its bench ruling during the liability phase of trial on April 3, 1996. (Liability Phase Trial, Apr. 3, 1996, Tr. at 407-08.) Nevertheless, the court will address this argument again to show defendant’s lack of substantial justification.
. Defendant also contends that the Disputes clause imposed a duty on plaintiff to proceed with its performance and that its failure to do so was substantial justification for repudiating the contract. The court finds this argument irrelevant and unpersuasive. As noted above, the court's findings of fact expose defendant’s lack of justification for terminating the contract due to plaintiff’s failure to return to work on December 17, 1993. The disputes clause cannot impute substantial justification on defendant’s overwhelmingly unjustified acts.
. Plaintiff asserts that oral fee arrangements are ethically permissible under the California rules of professional responsibility. (Decl. of David A. Perkins in Supp. of Pl.’s Appl. for Award of Fees and Other Expenses at 2.)
. Plaintiffs counsel did not bill plaintiff for surety litigation fees subsequent to filing the complaint.
. As stated above, defendant challenged the sufficiency of plaintiff's counsel’s documentation. The court found the documentation sufficient.
. Black’s Law Dictionary defines "incur” as follows:
To have liabilities cast upon one by act or operation of law, as distinguished from contract, where the party acts affirmatively. To become liable or subject to, to bring down upon oneself, as to incur debt, danger, displeasure and penalty, and to become through one’s own action liable or subject to.
Black’s Law Dictionary 768 (6th ed.1990).
. Defendant also argued that the description of the accountant’s fees were not sufficiently detailed to support an award. Defendant's argument is moot in light of the court's holding that plaintiff never incurred the accountant expenses.
. Plaintiff’s other expenses have been adjusted because plaintiff already received partial payment through its bill of costs filed December 20, 1996.
. The 1996 amendments to the Code raised the hourly attorney fee from $75 per hour to $125 per hour. 28 U.S.C.A. § 2412(d)(2)(A) (West Supp.1997). This amendment, however, applies only to civil actions commenced on or after March 29, 1996. Equal Access to Justice Act,
. Although defendant asserts that plaintiff’s counsel spent approximately 35 hours researching and drafting the EAJA application, the court’s analysis yielded a total of 57.6 hours.